03-25093. Financial Assurance for Materials Licensees  

  • Start Preamble

    AGENCY:

    Nuclear Regulatory Commission.

    ACTION:

    Final rule.

    SUMMARY:

    The Nuclear Regulatory Commission (NRC) is amending its regulations for financial assurance for certain materials licensees, including all waste brokers, to bring the amount of financial assurance required more in line with current decommissioning costs. The objective of this action is to ensure that licensees maintain adequate financial assurance so that timely decommissioning can be carried out following shutdown of a licensed facility.

    EFFECTIVE DATE:

    December 2, 2003.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    James Morris, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington, Start Printed Page 57328DC 20555-0001, telephone (301) 415-0191, e-mail jem2@nrc.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Introduction

    When NRC published the “General Requirements for Decommissioning Nuclear Facilities” final rule the Commission noted that inadequate or untimely consideration of decommissioning, specifically in the areas of planning and financial assurance, could result in significant adverse health, safety and environmental impacts (53 FR 24018, June 27, 1988). Additionally, they stated an intention that the regulations make clear that the licensee is responsible for the funding and completion of decommissioning in a manner which protects public health and safety.

    Availability of adequate decommissioning funding is necessary for assuring that timely decontamination of facilities takes place following cessation of licensed operations. If a nuclear materials facility remains in a nonoperating status without being decommissioned, public health and safety could be compromised by leakage and contamination and/or loss of control of nuclear materials. Also, when decommissioning is delayed for long periods following cessation of operations, there is a risk that safety practices may become lax as key personnel relocate and management interest wanes. The Commission stated in the “Timeliness in Decommissioning of Materials Facilities” final rule that the rule was intended to reduce the potential risk to public health and the environment from radioactive material remaining for long periods of time at such facilities after licensed activities have ceased (59 FR 36026, July 15, 1994).

    Background

    On October 7, 2002, the NRC published a proposed rule (67 FR 62403) that would amend the requirements for financial assurance for certain materials licensees. The proposed rule was developed in response to a need to update financial assurance requirements to ensure that licensees maintain adequate financial assurance coverage. The NRC regulations requiring financial assurance for decommissioning are designed to ensure that adequate funding will be available for timely decommissioning by licensees following shutdown of normal operations. The financial assurance regulations are part of the overall NRC strategy to maintain safety and protection of the public and the environment during and after decommissioning and decontamination of nuclear facilities.

    Financial assurance is composed of several parts: (1) Appropriate identification of licensees for which financial assurance should be required; (2) the amount of financial assurance required for each licensee must be adequate to fund current decommissioning costs; and (3) appropriate financial assurance mechanisms (surety bonds, escrow accounts, parent or self-guarantee, etc.) must be required.

    The NRC is amending its financial assurance requirements for certain materials licensees to bring required financial assurance amounts more in line with actual current decommissioning costs. The objective of this rulemaking is to maintain adequate financial assurance by addressing gaps in the current regulatory framework regarding (1) and (2) above.

    Under current decommissioning regulations, materials licensees that use substantial quantities of nuclear materials must provide financial assurance for decommissioning (most materials licensees do not need to provide financial assurance because their possession limits are below the threshold for requiring financial assurance). NRC has approximately 4900 materials licensees, of which approximately 10 percent require financial assurance. The financial assurance requirements were established in 1988 as part of the decommissioning rulemaking (53 FR 24018; June 27, 1988). The amount of financial assurance that must be provided can be based on either: (1) A facility-specific decommissioning cost estimate provided by the licensee in a decommissioning funding plan;[1] or (2) one of several dollar amounts prescribed by regulation (certification amounts), that are based on possession limits. Revision to some of the financial assurance requirements for materials licensees are needed because there have been changes in decommissioning costs since that rulemaking was issued. Also, experience has revealed that for certain types of licensees, such as waste brokers,[2] special circumstances exist that require different financial assurance considerations.

    The financial assurance regulations no longer provide adequate coverage of decommissioning costs for certain types of materials licensees, mainly due to large increases in decommissioning costs since the financial assurance regulations were put in place. Allowing these financial assurance coverage shortfalls to remain could increase the likelihood of inadequate funding for timely decommissioning.

    To address these financial assurance coverage issues NRC considered two alternatives which were: (1) No action; and (2) carrying out this rulemaking. NRC performed a regulatory analysis studying the costs and benefits of the two alternatives and reached the following conclusions.

    (1) No Action

    Under this alternative, no rulemaking would be done. The amount of financial assurance required would not be adequate to fully fund decommissioning activities for a large number of licensees. This shortfall in financial assurance would increase the likelihood that decommissioning of some facilities would not be carried out in a timely manner. This could result in adverse impacts on public health and safety, and also could have adverse environmental effects. It would also increase the likelihood that State or local governments and/or the general public would have to bear the costs of decommissioning.

    No costs to licensees or NRC would be involved for this alternative. Licensees would not be subject to any cost increases, and NRC would not incur costs associated with developing and implementing the rulemaking.

    (2) Rulemaking to Revise the Financial Assurance Requirements for Materials Licensees

    Under this alternative, certification amounts would be raised by 50 percent, providing approximately $80 million in additional financial assurance.[3] Large irradiator and waste broker licensees would have to base financial assurance on a site-specific decommissioning cost estimate. All waste brokers would have to provide financial assurance to cover the amount of the cost estimate. The decommissioning cost estimates would have to be updated at least every 3 years. A rulemaking to revise the financial assurance requirements for materials licensees would increase the assurance of adequate funding for decommissioning activities. This increased assurance would make timely decommissioning more likely, contributing to maintaining public health and safety and protection of the environment. This action would also Start Printed Page 57329decrease the likelihood that State and local governments and/or the general public would have to bear the costs of decommissioning, should a licensee be unable to do so.

    The benefit of the rulemaking is enhanced assurance of adequate funding for timely decommissioning. As stated above, there are gaps in the current financial assurance regulations permitting some licensees to provide financial assurance that does not cover the full cost of decommissioning, mainly due to large increases in decommissioning costs since the financial assurance regulations were put in place. Allowing these gaps to remain could increase the likelihood of inadequate funding for timely decommissioning.

    The effect of inadequate/untimely funding of decommissioning may have adverse impacts on public health and safety. If a site is not decommissioned due to insufficient funds there is an increased likelihood of contamination and/or exposure of members of the public. The changes to the regulations are concentrated in areas where the likelihood of inadequate funding relative to decommissioning costs appears to be relatively high. First, the financial assurance requirements are imposed only on those licensees having the highest possession limits, and thus the potential for highest doses. Only about 10 percent of materials licensees must provide financial assurance. Second, the changes in this plan address situations where risk of inadequate funding of decommissioning obligations is greatest—where required amounts of financial assurance appear to be substantially less than decommissioning costs.

    Failure to provide adequate financial assurance for decommissioning also has equity considerations. The potential public costs involved in cleanup of contaminated facilities where financial assurance is inadequate must be considered. Equity considerations call for adequate financial assurance so that a licensee's decommissioning costs are borne by the licensee.

    The changes to the regulations are focused on areas where the likelihood of inadequate funding relative to decommissioning costs is high. The changes address situations where currently required amounts of financial assurance appear to be substantially less than decommissioning costs. The changes would provide approximately $80 million in additional financial assurance.[4]

    These amendments were developed prior to recent heightened concerns about security of nuclear material. Because the objective of the amendments is to ensure that adequate funds are available to provide for the timely decommissioning of nuclear facilities with appropriate disposal of radioactive materials, these amendments should also enhance security of nuclear materials.

    Changes are being made in four areas:

    (1) Large sealed source licensees, i.e., large irradiators, would not be permitted to use the certification amounts, and would have to base their financial assurance on a site-specific decommissioning cost estimate;

    (2) All waste broker licensees (waste processors and waste collectors) would have to provide financial assurance, would not be permitted to use the certification amounts, and would have to base their financial assurance on a site-specific decommissioning cost estimate;

    (3) The certification amounts for licensees would be increased by 50 percent; and

    (4) Decommissioning cost estimates would have to be updated at least every 3 years.

    Analysis of Public Comments

    Eight comment letters were received. Three were from industry organizations, four from corporations, and one from an individual health physics professional. The comments and staff responses are summarized below:

    A. Comments Regarding Requirements for Large Sealed Source Licensees

    NRC's previous requirements allowed all sealed source licensees to use a certification amount as a basis for financial assurance. The proposed revisions modified this requirement by requiring sealed source licensees above a specified threshold (i.e., possession limits in excess of 1012 times the applicable quantities of appendix B to part 30) to prepare and submit site-specific decommissioning cost estimates in place of certifications of financial assurance. The comments raised three issues related to this proposed change.

    1. Residual Market Value of Sealed Sources

    Comment: Several commenters argued that NRC's proposed rule is based on an overestimate of large irradiator decommissioning costs because NRC fails to take into account the residual market value of sealed sources. The residual market value of the sources is substantial, and should be considered as an offset to decommissioning costs. The NRC is unjustified in ending the use of certification amounts by large irradiators because actual decommissioning costs for large irradiators, considering the residual value of sources, would still be less than the proposed certification amount for sealed source licensees of $113K. With the cost of removal and transport being recovered from the resale or redistribution value of the sources, there is little difference in decommissioning costs of large versus small irradiators, and the $113K figure should be adequate.

    One commenter asserted that the cobalt-60 used in large irradiators sells for about $1 per curie or more; therefore, a facility with 2 million curies should be able to sell its inventory for some significant fraction of its $2 million market value. Decommissioning such a facility would likely result in little or no out of pocket cost (such as the supplier handling charge assumed by NRC in NUREG/CR-6280) and perhaps a positive cash flow. The commenter then provided two examples where the commenter decommissioned licensee facilities in part to obtain title to cobalt-60 worth between $0.25-$1 per curie or more. As a result of this residual value, NRC's proposal to require large irradiators to prepare a site-specific decommissioning cost estimate actually would result in reduced amounts of financial assurance (due to consideration of the value of the sources), while placing an unnecessary burden on licensees.

    Another commenter extended a similar argument to items in finished goods inventory, other saleable goods in inventory, and active or contaminated equipment that could be used elsewhere. This commenter stated that it is unfair and beyond the boundaries of good business practices to consider assets as liabilities just because they are radioactive, and NRC has not established within its regulations the difference between radioactive materials with residual value and radioactive materials as waste.

    Response: The NRC agrees that the proposed rule does not take into account the residual market value of sealed sources. This approach is both appropriate and consistent with existing NRC policy. For example, current Start Printed Page 57330guidance in NUREG-1727 states the following: [5]

    The cost estimate should clearly state that it does not take credit for any salvage value that might be realized from the sale of potential assets (e.g., recovered materials or decontaminated equipment) during or after decommissioning. If estimated credits are taken for salvage value but are not fully realized at the time of decommissioning, the cost estimate (as well as the financial assurance) may be significantly low.

    The NRC believes that it would be inappropriate to incorporate salvage value into certification amounts when the actual residual value can vary substantially depending on the number and type of sources at a given facility, as well as on the curies present at the time of decommissioning (which generally is not known when a licensee's certification of financial assurance is put in place). Any residual value also would be subject to variability arising from changing market conditions. Therefore, it would be inappropriate to consider these characteristics when establishing generic certification levels.

    Furthermore, NRC is concerned that it may be impossible at the time of decommissioning to realize (i.e., as cash) any inherent value contained in sealed sources, even if the sources have substantial value to the licensees that possess them. Irradiator licensees convert this inherent value into cash through the course of their business operations. However, these business operations cease at the time of decommissioning. Assuming that licensees decommission their facilities at the most economical point in time, then their sources will probably have decayed just to the point where they can no longer be used cost-effectively. In this case at least, the sources are unlikely to have value to anyone unless they can be re-processed.

    Another significant concern to NRC is the possibility that some sources may have no residual value at all and may need to be disposed of as low-level waste (LLW). If sources must be disposed as LLW, then decommissioning costs would be considerably higher. For example, NUREG/CR-6280 concludes that decommissioning costs for a clean reference large irradiator facility may range (in 1993 dollars) from $289,000, if the sources are returned to the supplier, up to $3.0 million if it is necessary to dispose of the sources as LLW.[6]

    If the potential salvage value of a source were to be used to offset the estimated cost of decommissioning, the effect would be to reduce the amount of funds guaranteed by financial instruments that possess a very high level of assurance, such as a prepaid escrow fund or an irrevocable letter of credit. However, the estimated salvage value of a source does not guarantee that funds will be available when needed. Even where a potential buyer provides a contractual promise to buy the source for a specified sum, the contract provides a lower level of assurance than the protection provided by the fiduciary obligations required of financial institutions that act as trustees or guarantors of funds. A contractual arrangement between the licensee and a buyer does not include the NRC as a beneficiary with the right to demand that funds be placed into a standby trust which restricts use of the funds for decommissioning only. In contrast, a letter of credit, for example, does establish the NRC as a beneficiary and gives the NRC that right. Therefore, permitting a licensee to reduce its decommissioning cost estimate by the potential salvage value of a source would decrease the level of financial assurance as compared to the financial instruments required by current regulations.

    For all these reasons, NRC concludes that its current approach not to permit credit for residual salvage value in setting certification amounts is reasonable.

    2. Exemption Threshold Too Low

    Comment: One commenter noted that, under the proposed rule, sealed source licensees are exempt from financial assurance requirements if the licensed material is less than or equal to 1010 times the applicable quantities of appendix B to part 30, which becomes 10,000 Ci for cobalt (1010 times 1.0 μCi). The commenter asserted that this causes problems for owners of cobalt teletherapy units, wherein a new source typically decays to below 10,000 Ci in the first 2 years of use. The complication, according to the commenter, is that financial assurance is initially required but then becomes unnecessary for the remainder of the source's life. The commenter requested that the exempted amount be raised to 5×1010 times the applicable Appendix B quantity as no teletherapy source exceeds 15,000 Ci.

    Response: The certification levels and calculations described in the regulations are based on licensed possession limits, rather than actual possession. If a licensee for a cobalt teletherapy unit is allowed to possess cobalt in excess of 10,000 Ci under its license, then financial assurance is required even if the activity of the source decays to lower than that level. In fact, financial assurance must be maintained until NRC terminates the license, even if the licensee no longer possesses any radioactive material (unless the license is modified to reflect different possession limits). This approach ensures that licensees maintain adequate financial assurance for activities that are authorized under the license. Also, requiring a constant amount of financial assurance avoids the complication of constantly adjusting financial assurance levels to account for decay, changing inventories, etc.

    The commenter may be correct that an increase in the exemption threshold would benefit teletherapy unit licensees. However, it also would eliminate the added protections achieved by the financial assurance requirements (even in cases where decommissioning occurred before any significant decay of the radioactive sources).

    3. “Arbitrary” Upper Certification Limit

    Comment: One commenter stated that decommissioning costs are driven more by the size and complexity of the facility than the size or activity of the source used, e.g., a newer facility with twice as large a source as an older facility may require half the cost to decommission due to new design features. Therefore, the upper limit (of 10 12 times the applicable quantities of appendix B to part 30) for sealed source certifications is arbitrary and should be removed.

    Response: NRC agrees that both the size and complexity of a facility are important decommissioning cost drivers. Although newer facilities may be more likely to incorporate design features that will tend to reduce decommissioning costs, this correlation is untested and may only be true in general terms. There is no assurance that a new facility will cost less to decommission than an older facility or, conversely, that older facilities (which may have been remodeled) cost more to decommission. Moreover, research indicates that the characteristics of the sealed sources constitute an important and potentially critical cost driver. Therefore, the proposed activity-based upper limit is not arbitrary, but rather provides a reasonably effective and simple method for distinguishing those licensees for whom preparation of a Start Printed Page 57331facility-specific cost estimate (including a discussion of the fate of the sealed sources) is warranted. NRC believes that an upper limit based on activity is considerably easier to implement than one that would account for additional or alternative factors.

    B. Comments on Waste Broker Definition

    Commenters raised three issues regarding NRC's proposed definition of “waste broker.” The proposed definition stated that waste broker means any licensee that collects or accepts radioactive material from other entities for the purpose of processing, compacting, repackaging, or otherwise preparing it for disposal, or storage.

    1. Applicability to Storage and Radioactive Materials

    Comment: Two commenters stated that the proposed definition of waste broker should be reconsidered, particularly its applicability to storage activities and to radioactive material (as opposed to radioactive waste). Otherwise, these commenters stated, NRC's waste broker requirements will inadvertently subject some licensees that are not waste brokers to NRC's waste broker requirements, including the following:

    • Manufacturers (who receive radioactive material from a supplier for storage and future use);
    • Distributors (who receive radioactive material from a supplier for storage and distribution);
    • Service companies (who are authorized to receive sources from a supplier to be used for source exchanges);
    • Contractors (who receive radioactive material in generally-licensed devices as part of a turnkey job, then place them in storage until they are turned over to the user); and
    • Carriers (who, as general licensees, store radioactive material or waste prior to delivery, or who deliver material or waste prior to storage by the recipient).

    Response: The NRC agrees that the proposed definition is problematic as suggested by these commenters. The final rule does not establish a definition of waste broker, but instead uses the existing definitions of waste processor and waste collector in 10 CFR part 20, appendix G. § 30.35 (c)(5) now requires waste collectors and waste processors to have financial assurance and base the amount of financial assurance on a site-specific decommissioning cost estimate.

    2. Collectors vs. Processors

    Comment: One commenter stated that the proposed rule's definition of waste broker appropriately covers waste processors and should, but does not, include waste collectors. There are certain licensees that have as their principal purpose to collect and consolidate packaged radioactive waste from others and transfer it to waste processors or disposal facilities. Facilities for interim storage of waste should have adequate financial assurance to cover decommissioning whether the licensee is a collector or processor.

    Response: NRC agrees that the waste “collectors” described in the comment should be subject to the waste broker requirements. A change has been made to Section 30.35 (c)(5) to place requirements on waste collectors and waste processors as defined in 10 CFR part 20, appendix G.

    3. Need to Define Radioactive “Waste”

    Comment: One commenter stated that the proposed term “waste broker” cannot be defined when there is no clear standard definition of “waste” anywhere in NRC regulation or statute. The commenter stated that, historically, the term “waste” has been generally applied to sealed sources at the end of intended use regardless of whether they can be reused by someone else or their contents recovered as feedstock or reworked to extend the useful life of the sources. The commenter noted that there are differing definitions in 10 CFR 63.2 and 10 CFR 110.2, with the latter specifically exempting sealed sources being returned to any qualified manufacturer from the waste import and export regulations. In other contexts, there is no meaningful definition of radioactive “waste” as it applies to sealed sources or other radioactive materials. The commenter asserted that regardless of the lack of a clear definition of radioactive “waste,” there is also a conflict in NRC policy and regulation as, on one hand, some sealed sources are exempted from the definition of “waste” while, on the other hand, sources are included in the scope of licensed material subject to decommissioning financial assurance.

    Response: The NRC has decided not to define “waste” or “waste broker” in this rule. Although “waste” is not defined in NRC regulations, it is used in other NRC regulations and guidance in various contexts; therefore, defining the term for this rulemaking could result in unintended consequences. The apparent conflict in NRC policy and regulations that was raised by one commenter regarding the inconsistency of the use of this term as applied to sealed sources, is easily resolved by placing in context the exemption the commenter cited in 10 CFR 110.2 (vs. the inclusion of sealed sources in the scope of licensed material subject to the decommissioning financial assurance in this rule). As the Statements of Consideration for the exemption explain (60 FR 37556, published on 7/21/95), the exemption refers to sealed sources that are being returned to the United States or another country for reconditioning, recycling, or reprocessing. These types of transfers help to ensure that the materials are handled responsibly and not left in dispersed and perhaps unregulated locations around the world. Therefore, the NRC determined that they should not be subject to specific licensing, in this context, if the radioactive material involved would not be otherwise subject to such licensing. The disposition of sealed sources in this context differs radically from the disposition of sealed sources addressed by the rule.

    As noted in the Statement of Considerations accompanying the proposed rule, the waste broker provisions of the rule are intended to be applied to licensees that (1) are likely to have fluctuating amounts of radioactive waste generated by other licensees, and (2) have a financial interest in maximizing the amount of radioactive waste they handle (i.e., because their revenue is directly correlated to the amount of waste accepted). However, the existing definitions of “waste processor” and “waste collector” in 10 CFR part 20, appendix G, “Requirements for Transfers of Low-level Radioactive Waste Intended for Disposal at Licensed Land Disposal Facilities and Manifest,” encompass the activities of the licensees the proposed term “waste broker” sought to address. These activities, which are well understood by the regulated community, make such licensees stand out among other NRC licensees from a financial assurance perspective and support the inclusion of these licensees in this rule.

    C. Comments on Requirements for Decommissioning Cost Updates

    1. Three vs. Five Year Updates

    Comment: Several commenters stated that the 3-year time frame for periodic decommissioning cost estimate updates is too frequent and that every 5 years would be more reasonable. One of the three stated that cost estimates should be reassessed every 5 years in order to coincide with the license renewal process. This commenter stated that, for irradiators, decommissioning does not involve disposal of materials as radioactive waste and, therefore, that the stated impetus for the 3-year period Start Printed Page 57332(i.e., recent increases in radioactive waste disposal costs) does not apply. Another of these commenters stated that NRC's proposal will be burdensome and appears to be driven by short-term investment performance and anticipation of higher waste disposal costs. This commenter countered that the history of investments over long periods of time (e.g., 40-plus year facility lifetimes) is very positive, and that licensees have taken steps to lower their waste disposal costs by reducing the volume of decommissioning waste that will be generated and by increasing the recycling of materials to other nuclear facilities.

    Response: The proposed requirement to update decommissioning cost estimates every 3 years will help ensure that financial assurance obtained by licensees will not become inadequate as a result of changing disposal prices or other factors. Increasing waste disposal costs have been and continue to be a concern for NRC. However, decommissioning costs also may change for a variety of licensee-specific reasons (e.g., due to changes in the size and scope of operations) as well as for other reasons that may be out of a licensee's control (e.g., inflation). The proposed 3-year cost estimate updates are intended to capture changes in estimated costs regardless of cause, and to help ensure that the level of financial assurance required of each licensee is appropriate. Therefore, the proposed requirement is appropriate even for licensees that are not expecting to incur any significant waste disposal costs, as well as for licensees that may be taking steps to reduce the volume of decommissioning waste (which is only one component of decommissioning costs).

    Although it would be less burdensome to require updates every 5 years as opposed to every 3 years, the NRC believes that this would entail too great of a risk that cost estimates could become significantly low. The NRC's experience indicates that decommissioning cost estimates may fluctuate significantly in less than five years. In one case, a licensee increased its decommissioning cost estimate from $55,000,000 to $67,000,000 in one year. Even where site conditions do not change as dramatically as in the case noted, inflation may increase costs significantly.

    For example, if decommissioning costs were to rise by five percent annually (due to higher disposal costs, increased operations, inflation, and/or other factors), then in only 3 years a previously accurate estimate would understate current costs by 15 percent. As a result, financial assurance would be low by the same amount. This would create an unacceptable risk of unfunded decommissioning obligations. This risk would increase even further over a 5-year period.

    2. Update Estimates Only When Warranted

    Comment: One commenter asserted that the reason costs can change significantly has to do with “internal” factors such as the size and scope of operations (as opposed to “external” factors such as the cost of disposal). Therefore, this commenter suggested that whenever an application for a license amendment is submitted due to changes in operations or materials possession (or other factors specified by NRC), an updated cost estimate should be required and considered as part of the amendment process. If no license amendments are required prior to license renewal, then an updated estimate should be required only at the time of license renewal. The commenter also described two alternatives to this approach. Under the first alternative, NRC could arrange for updates on a case-by-case basis by category and default history for that segment. Under the second alternative, licensees would update their cost estimate if estimated costs exceed a required contingency included in the previous estimate.

    Response: NRC agrees that internal factors are an important cause of significant changes to decommissioning costs. However, if the commenter's primary suggestion (i.e., to require an updated cost estimate as part of any license amendment application involving a change in operations or materials possession, or at the time of license renewal if there are no amendments) were enacted, licensees would update their cost estimates only once every 5 years, assuming there were no license amendments or other “internal” trigger events that might be specified by NRC. This would be true regardless of cost increases due to “external” factors (e.g., increased disposal costs, inflation). As discussed in Section C.1 above, this approach is not acceptable to NRC because it could result in a substantial portion of decommissioning costs not being covered by financial assurance.

    The first alternative approach would require that updates be provided by licensees on a case-by-case basis by “category” and “default history” for the relevant segment. NRC believes this approach would place an unreasonable administrative burden on NRC staff to analyze all changes and events applicable to each licensee individually, as well as to study default histories and other developments by segment. Even if NRC were to undertake such efforts, licensees still might be required to submit updated estimates (albeit on a case-by-case basis) with a frequency that approximates that of this rulemaking.

    The second alternative approach suggested in the comment would require that cost estimates be updated only when the new estimate exceeds the required contingency in the previously-submitted cost estimate. As do other types of engineering cost estimates, decommissioning cost estimates include a contingency factor to account for unanticipated costs. This contingency factor is typically equal to 25 percent of the total of all known decommissioning costs. One problem with this alternative is that, if the contingency factor were allowed to cover recent increases in known costs, then the contingency would not be available to address the unanticipated costs for which it was intended. This means that the outdated estimate could be inadequate by 25 percent, which is not acceptable to NRC. A second problem with this alternative is that, in order to avoid updating the cost estimate, licensees would have to develop an updated cost estimate so that they could determine whether costs have escalated to more than the contingency factor. Therefore, it would be more efficient and more protective of decommissioning funding for the licensee to submit the updated estimate to NRC as proposed in this rulemaking, using it as the most accurate basis for financial assurance.

    D. General Comments

    1. Rule Is Arbitrary and Unwarranted

    Comment: One commenter disagreed with the increase in certification amounts and with NRC's justification for the change, characterizing it as “arbitrary and unwarranted.” The commenter stated that although disposal costs have indeed risen, waste liabilities actually have been reduced by efforts to reduce weights and volumes and eliminate sources of waste streams, and by considering ease of decommissioning in the design, construction, and operation of new facilities. The commenter stated that Barnwell has been unable to achieve South Carolina targets for generation of volume-driven revenue due to changes in waste management practices by generators over the years.

    Response: NRC does not agree that the basis for the rulemaking is arbitrary or unwarranted. First, and as noted by the comment, disposal costs have indeed risen. Although some licensees have implemented waste reduction efforts, Start Printed Page 57333these efforts do not necessarily offset all (or even most) of the waste disposal cost increases for these licensees. Moreover, other licensees have not implemented such efforts. NRC believes that the greatest waste reduction efforts have been made by larger licensees, who are the least likely to use the certification amounts.

    Second, increased disposal costs are not NRC's only justification for increasing the certification amounts. Inflation that has occurred since the promulgation of the original certification amounts exceeds 50 percent, based on the Consumer Price Index.[7] Specific information on decommissioning costs also shows a substantial increase. NRC regulations for decommissioning of nuclear power reactor licensees at 10 CFR 50.75 contain a cost adjustment factor for licensees to update the minimum amount of financial assurance required. This adjustment factor, which takes into account labor, energy, and waste disposal costs, shows a minimum increase of approximately 65 percent in reactor decommissioning costs from 1986 to 2000.[8] Thus, inflation, by itself is more than adequate as a justification for the rule's 50 percent increase in the certification amounts. In addition, other research conducted by NRC for this rulemaking indicates that licensees using certifications have substantially less financial assurance than is warranted based on their estimated decommissioning costs.[9]

    2. NRC's Financial Assurance Rules too Complicated

    Comment: One commenter stated that the regulations addressing decommissioning plans and financial assurance are unnecessarily complicated. The commenter suggested that the rules be consolidated within a single chapter of 10 CFR, instead of spread through four chapters and appendices. The commenter suggested listing requirements in simpler language instead of burying them in complicated prose. The commenter also offered assistance to NRC.

    Response: The NRC agrees that plain language improvements may be needed. This rulemaking makes changes in only a part of NRC's overall financial assurance requirements. Its objective is to bring financial assurance requirements more in line with actual decommissioning costs. NRC is trying to close any such gaps in a timely manner. Any future rulemakings covering more general changes in the financial assurance requirements will be carried out with a view toward clarification and simplification, where practical. As an aid to understanding its requirements, the NRC staff has developed a guidance document, “NMSS Decommissioning Standard Review Plan,” NUREG-1727,[10] that explains how licensees can meet decommissioning requirements, including financial assurance requirements.

    3. Consider Costs to Agreement State Licensees

    Comment: One commenter stated that it appears NRC considered the cost of the rule only to its own licensees, and not to Agreement State licensees. It is unrealistic to expect Agreement States not to adopt the rule (even though they are not required to do so based upon its category D rating), so NRC should consider costs to all licensees.

    Response: NRC has considered these costs, and has provided several opportunities for Agreement States to comment. The comments that NRC has received from Agreement States have generally supported this rulemaking. However, NRC has revised the Regulatory Analysis for the rule to more clearly estimate costs to Agreement State licensees that adopt the rule.

    4. Comment Period Should Be Extended

    Comment: One commenter requested that the public comment period for the proposed rule be extended until 60 days after NUREG/CR-6477 is made available for review by the public.

    Response: NUREG/CR-6477 was published in mid-January, and placed on the website for this rulemaking. A Federal Register notice of availability of the NUREG report, with a 30-day public comment period, was published on January 30, 2003 (68 FR 4801). No comments were received on the report.

    Changes From the Proposed Rule

    The definition of waste broker in § 30.4 is being removed. In § 30.35(c)(5), the terms waste processors [11] and waste collectors [12] , as defined in 10 CFR part 20, appendix G, are being used instead. Implementation dates have been inserted at appropriate places in the rule as described below.

    Implementation

    The NRC is implementing these requirements in a way intended to minimize the burden on licensees and regulators. Licensees are being given a reasonable period of time to submit new decommissioning cost estimates and to obtain any additional financial assurance that may be required. The NRC is establishing different effective dates for revised financial assurance requirements, depending on the type of licensee, so that new financial assurance submittals would not all be filed at one time. Licensees currently using the $750K certification amount are required to obtain additional financial assurance to comply with the revised $1,125K certification amount within 12 months of the effective date of the final rule. Licensees currently using the $75K or $150K certification amounts are required to obtain additional financial assurance to comply with the revised $113K or $225K certification amounts within 18 months of the effective date of the final rule. In either case, these licensees could choose the option of basing financial assurance on a decommissioning cost estimate. Licensees that can no longer use the certification amounts, such as large irradiators and waste brokers, are allowed up to 24 months to submit a decommissioning cost estimate.

    Discussion of Amendments by Section

    Section 30.35 Financial Assurance and Recordkeeping for Decommissioning

    Paragraph (a) is amended to require licensees possessing large numbers of sealed sources to base financial assurance on a decommissioning funding plan. Section 30.35(c)(2) revises the certification amount. A new § 30.35(c)(5) requires waste processors and waste collectors to base financial Start Printed Page 57334assurance on a site-specific decommissioning cost estimate. Section 30.35(d) increases the certification amounts by 50 percent—new certification amounts are $113K, $225K, and $1,125K. Section 30.35(e) requires that decommissioning funding plans be updated at least every 3 years.

    10 CFR 40.36 Financial Assurance and Recordkeeping

    Section 40.36(b)(2) increases the applicable certification amount by 50 percent. Section 40.36(c)(2) revises the certification amount. Section 40.36(d) requires that decommissioning funding plans be updated at least every 3 years.

    10 CFR 70.25 Financial Assurance and Recordkeeping for Decommissioning

    Section 70.25(c)(2) revises the certification amount. Section 70.25(d) increases the applicable certification amounts by 50 percent. Section 70.25(e) requires that decommissioning funding plans be updated at least every 3 years.

    Agreement State Compatibility

    Under the “Policy Statement on Adequacy and Compatibility of Agreement State Programs” that became effective on September 3, 1997 (62 FR 46517), NRC program elements (including regulations) are placed into four compatibility categories. In addition, NRC program elements also can be identified as having particular health and safety significance or as being reserved solely to the NRC.

    The sections of 10 CFR parts 30, 40, and 70 dealing with financial assurance that are being changed and their respective compatibility categories are as follows:

    Section 30.35 Financial Assurance and Recordkeeping for Decommissioning

    Compatibility category D—paragraphs (c), (e), (f)

    Health and Safety—paragraphs (a), (b), (d), and (g).

    Compatibility category D for paragraphs (c), (e), and (f) is warranted because States are allowed the flexibility to specify different dollar amounts based on jurisdiction and local conditions. The Health and Safety designation for paragraphs (a), (b), and (d) is warranted because these paragraphs address decommissioning funding plans necessary to ensure that funding is available for timely decommissioning. The Health and Safety designation of paragraph (g) is warranted because of the requirement for transfer of certain records (e.g., spills or spread of contamination that could impact health and safety) important to subsequent licensees for decommissioning at the same facility.

    Section 40.36 Financial Assurance and Recordkeeping for Decommissioning

    Compatibility category D—paragraphs (c) and (e).

    Health and Safety—paragraphs (a), (b), (d), and (f).

    Compatibility category D for paragraphs (c), and (e) is warranted because States are allowed the flexibility to specify different dollar amounts based on jurisdiction and local conditions. The Health and Safety designation for paragraphs (a), (b), and (d) is warranted because these paragraphs address decommissioning funding plans necessary to ensure that funding is available for timely decommissioning. The Health and Safety designation of paragraph (f) is warranted because of the requirement for transfer of certain records (e.g., spills or spread of contamination that could impact health and safety) important to subsequent licensees for decommissioning at the same facility.

    Section 70.25 Financial Assurance and Recordkeeping for Decommissioning

    Compatibility category D—paragraphs (c), (e), and (f)

    NRC—paragraph (a)

    Health and Safety—paragraphs (b), (d), and (g).

    Compatibility category D for paragraphs (c), (e), and (f) is warranted because States are allowed the flexibility to specify different dollar amounts based on jurisdiction and local conditions. Paragraph (a) addresses areas reserved to the NRC because it concerns uranium enrichment facilities and special nuclear materials in quantities sufficient to form a critical mass. The Health and Safety designation for paragraphs (b) and (d) is warranted because these paragraphs address decommissioning funding plans necessary to ensure that funding is available for timely decommissioning. The Health and Safety designation of paragraph (g) is warranted because of the requirement for transfer of certain records (e.g., spills or spread of contamination that could impact health and safety) important to subsequent licensees for decommissioning at the same facility.

    Plain Language

    The Presidential Memorandum dated June 1, 1998, entitled “Plain Language in Government Writing” directed that the Government's writing be in plain language. One comment on this rule specifically addressed the clarity and effectiveness of the language used in the financial assurance regulations. The NRC response to the comment is included in the “Analysis of Public Comments” section of this notice.

    Voluntary Consensus Standards

    The National Technology Transfer Act of 1995 (Pub. L. 104-113) requires that Federal agencies use technical standards that are developed or adopted by voluntary consensus standards bodies unless the use of such a standard is inconsistent with applicable law or otherwise impractical. In this rule, the NRC is making revisions to certain financial assurance requirements for materials licensees. Financial assurance requirements are not standards that have been established by any voluntary consensus organizations.

    Environmental Assessment and Finding of No Significant Environmental Impact

    The Commission has determined under the National Environmental Policy Act of 1969, as amended, and the Commission's regulations in subpart A of 10 CFR part 51, not to prepare an environmental impact statement for this rule because the Commission has concluded on the basis of the environmental assessment (contained in this notice below) that this rule is not a major Federal action significantly affecting the quality of the human environment.

    These amendments revise financial assurance requirements for certain materials licensees. The amendments require certain materials licensees to submit decommissioning cost estimates; increase the amount of financial assurance required by licensees using the certification amounts; and require updates of decommissioning cost estimates at least every 3 years. None of these actions have any adverse impact on the environment. The amendments would not lead to any increase in the effect on the environment of the decommissioning activities already considered in the final decommissioning rule published on June 27, 1988 (53 FR 24018), as analyzed in “Final Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities” (NUREG-0586, August 1988).[13] Actions conducted under this rule would not introduce any impacts on the Start Printed Page 57335environment not previously considered by the NRC.

    The determination of this environmental assessment is that there will be no significant adverse impact to the quality of the human environment from this action. This action should have a positive impact on the quality of the human environment by providing additional assurance of timely decommissioning. Timely decommissioning should reduce the possibility of contamination of sites, and should enhance safety and protection of the environment. This discussion constitutes the environmental assessment upon which a finding of no significant impact has been found for this rule.

    Paperwork Reduction Act Statement

    This final rule contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These requirements were approved by the Office of Management and Budget, approval numbers 3150-0009, -0017, and -0020.

    The burden to the public for the information collections contained in 10 CFR part 30 is estimated to average 10.4 hours per response, the burden for the information collections contained in 10 CFR part 40 is estimated to average 7.3 hours per response, and the burden for the information collections contained in 10 CFR part 70 is estimated to average 7.5 hours per response. This includes the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collection. Send comments on any aspect of these information collections, including suggestions for reducing the burden, to the Records Management Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to infocollects@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0009, -0017, and -0020), Office of Management and Budget, Washington, DC 20503.

    Public Protection Notification

    The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid OMB control number.

    Regulatory Analysis

    The Commission has prepared a regulatory analysis on this regulation. The analysis examines the costs and benefits of the alternatives considered by the Commission. The analysis is available for inspection and copying in the NRC Public Document Room at O-1F23, 11555 Rockville Pike, Rockville, MD. Single copies of the regulatory analysis are available from James Morris, telephone (301) 415-0191, e-mail, jem2@nrc.gov of the Office of Nuclear Material Safety and Safeguards.

    Regulatory Flexibility Certification

    In accordance with the Regulatory Flexibility Act of 1980 (5 U.S.C. 605(b)), the Commission certifies that this rule would not have a significant economic impact on a substantial number of small entities. Some licensees affected by this action may fall within the definition of “small entities” set forth in the Regulatory Flexibility Act or the Small Business Size Standards set out in regulations issued by the Small Business Administration at 13 CFR part 121. However, while the rule would change the financial assurance requirements for these licensees, such licensees may base their financial assurance on a site-specific decommissioning cost estimate. No licensee would be required to provide financial assurance in excess of what is needed to cover decommissioning costs. Increases in financial assurance amounts required are only the amounts necessary to maintain adequate financial assurance to cover increased decommissioning costs. The regulatory analysis cited for this action contains estimates of cost impacts on different types of licensees.

    Backfit Analysis

    There are no backfit requirements in 10 CFR parts 30 and 40, and, in accordance with the “Effective Date Note” regarding implementation of § 70.76, the provisions of 10 CFR 70.76 on backfitting have not yet gone into effect. Therefore, a backfit analysis is not required. However, the burdens and the benefits associated with this rule are addressed in the Regulatory Analysis.

    Small Business Regulatory Enforcement Fairness Act

    In accordance with the Small Business Regulatory Enforcement Fairness Act of 1996, the NRC has determined that this action is not a major rule and has verified this determination with the Office of Information and Regulatory Affairs of OMB.

    Start List of Subjects

    List of Subjects

    10 CFR Part 30

    • Byproduct material
    • Criminal penalties
    • Government contracts
    • Intergovernmental relations
    • Isotopes
    • Nuclear materials
    • Radiation protection
    • Reporting and recordkeeping requirements

    10 CFR Part 40

    • Criminal penalties
    • Government contracts
    • Hazardous materials transportation
    • Nuclear materials
    • Reporting and recordkeeping requirements
    • Source material
    • Uranium

    10 CFR Part 70

    • Criminal penalties
    • Hazardous materials transportation
    • Material control and accounting
    • Nuclear materials
    • Packaging and containers
    • Radiation protection
    • Reporting and recordkeeping requirements
    • Scientific equipment
    • Security measures
    • Special nuclear material
    End List of Subjects Start Amendment Part

    For the reasons set out in the preamble and under the authority of the Atomic Energy Act of 1954, as amended; the Energy Reorganization Act of 1974, as amended; and 5 U.S.C. 552 and 553; the NRC is adopting the following amendments to 10 CFR parts 30, 40, and 70.

    End Amendment Part Start Part

    PART 30—RULES OF GENERAL APPLICABILITY TO DOMESTIC LICENSING OF BYPRODUCT MATERIAL

    End Part Start Amendment Part

    1. The authority citation for part 30 continues to read as follows:

    End Amendment Part Start Authority

    Authority: Secs. 81, 82, 161, 182, 183, 186, 68 Stat. 935, 948, 953, 954, 955, as amended, sec. 234, 83 Stat. 444, as amended (42 U.S.C. 2111, 2112, 2201, 2232, 2233, 2236, 2282); secs. 201, as amended, 202, 206, 88 Stat. 1242, as amended, 1244, 1246 (42 U.S.C. 5841, 5842, 5846).

    End Authority

    Section 30.7 also issued under Pub. L. 95-601, sec. 10, 92 Stat. 2951 as amended by Pub. L. 102-486, sec. 2902, 106 Stat. 3123, (42 U.S.C. 5851). Section 30.34(b) also issued under sec.184, 68 Stat. 954, as amended (42 U.S.C. 2234). Section 30.61 also issued under sec. 187, 68 Stat. 955 (42 U.S.C. 2237).

    Start Amendment Part

    2. In § 30.35, paragraphs (a), (c)(2), (d), and (e) are revised and a new paragraph (c)(5) is added to read as follows:

    End Amendment Part
    Financial assurance and recordkeeping for decommissioning.

    (a)(1) Each applicant for a specific license authorizing the possession and use of unsealed byproduct material of half-life greater than 120 days and in quantities exceeding 105 times the applicable quantities set forth in appendix B to part 30 shall submit a Start Printed Page 57336decommissioning funding plan as described in paragraph (e) of this section. The decommissioning funding plan must also be submitted when a combination of isotopes is involved if R divided by 105 is greater than 1 (unity rule), where R is defined here as the sum of the ratios of the quantity of each isotope to the applicable value in appendix B to part 30.

    (2) Each holder of, or applicant for, any specific license authorizing the possession and use of sealed sources or plated foils of half-life greater than 120 days and in quantities exceeding 1012 times the applicable quantities set forth in appendix B to part 30 (or when a combination of isotopes is involved if R, as defined in § 30.35(a)(1), divided by 10 12 is greater than 1), shall submit a decommissioning funding plan as described in paragraph (e) of this section. The decommissioning funding plan must be submitted to NRC by December 2, 2005.

    * * * * *

    (c) * * *

    (2) Each holder of a specific license issued before July 27, 1990, and of a type described in paragraph (a) of this section shall submit a decommissioning funding plan as described in paragraph (e) of this section or a certification of financial assurance for decommissioning in an amount at least equal to $1,125,000 in accordance with the criteria set forth in this section. If the licensee submits the certification of financial assurance rather than a decommissioning funding plan, the licensee shall include a decommissioning funding plan in any application for license renewal.

    * * * * *

    (5) Waste collectors and waste processors, as defined in 10 CFR part 20, Appendix G, must provide financial assurance in an amount based on a decommissioning funding plan as described in paragraph (e) of this section. The decommissioning funding plan must include the cost of disposal of the maximum amount (curies) of radioactive material permitted by license, and the cost of disposal of the maximum quantity, by volume, of radioactive material which could be present at the licensee's facility at any time, in addition to the cost to remediate the licensee's site to meet the license termination criteria of 10 CFR part 20. The decommissioning funding plan must be submitted by December 2, 2005.

    (d) Table of required amounts of financial assurance for decommissioning by quantity of material. Licensees required to submit the $1,125,000 amount must do so by December 2, 2004. Licensees required to submit the $113,000 or $225,000 amount must do so by June 2, 2005. Licensees having possession limits exceeding the upper bounds of this table must base financial assurance on a decommissioning funding plan.

    Greater than 104 but less than or equal to 105 times the applicable quantities of appendix B to part 30 in unsealed form. (For a combination of isotopes, if R, as defined in § 30.35(a)(1), divided by 104 is greater than 1 but R divided by 105 is less than or equal to 1)$1,125,000
    Greater than 103 but less than or equal to 104 times the applicable quantities of appendix B to part 30 in unsealed form. (For a combination of isotopes, if R, as defined in § 30.35(a)(1), divided by 103 is greater than 1 but R divided by 104 is less than or equal to 1)225,000
    Greater than 1010 but less than or equal to 1012 times the applicable quantities of appendix B to part 30 in sealed sources or plated foils. (For a combination of isotopes, if R, as defined in § 30.35(a)(1), divided by 1010 is greater than, 1, but R divided by 1012 is less than or equal to 1)113,000

    (e) Each decommissioning funding plan must contain a cost estsimate for decommissioning and a description of the method of assuring funds for decommissioning from paragraph (f) of this section, including means for adjusting cost estimates and associated funding levels periodically over the life of the facility. Cost estimates must be adjusted at intervals not to exceed 3 years. The decommissioning funding plan must also contain a certification by the licensee that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning and a signed original of the financial instrument obtained to satisfy the requriements of paragraph (f) of this section.

    * * * * *
    Start Part

    PART 40—DOMESTIC LICENSING OF SOURCE MATERIAL

    End Part Start Amendment Part

    3. The authority citation for part 40 continues to read as follows:

    End Amendment Part Start Authority

    Authority: Secs. 62, 63, 64, 65, 81, 161, 182, 183, 186, 68 Stat. 932, 933, 935, 948, 953, 954, 955, as amended, secs. 11e(2), 83, 84, Pub. L. 95-604, 92 Stat. 3033, as amended, 3039, sec. 234, 83 Stat. 444, as amended (42 U.S.C. 2014(e)(2), 2092, 2093, 2094, 2095, 2111, 2113, 2114, 2201, 2232, 2233, 2236, 2282); sec. 274, Pub. L. 86-373, 73 Stat. 688 (42 U.S.C. 2021); secs. 201, as amended, 202, 206, 88 Stat. 1242, as amended, 1244, 1246 (42 U.S.C. 5841, 5842, 5846); sec. 275, 92 Stat. 3021, as amended by Pub. L. 97-415, 96 Stat. 2067 (42 U.S.C. 2022); sec. 193, 104 Stat. 2835, as amended by Pub. L. 104-134, 110 Stat. 1321, 1321-349 (42 U.S.C. 2243).

    End Authority

    Section 40.7 also issued under Pub. L. 95-601, sec. 10, 92 Stat. 2951 (42 U.S.C. 5851). Section 40.31(g) also issued under sec. 122, 68 Stat. 939 (42 U.S.C. 2152). Section 40.46 also issued under sec. 184, 68 Stat. 954, as amended (42 U.S.C. 2234). Section 40.71 also issued under sec. 187, 68 Stat. 955 (42 U.S.C. 2237).

    Start Amendment Part

    4. In § 40.36, paragraphs (b)(2), (c)(2), and (d) are revised to read as follows:

    End Amendment Part
    Financial assurance and recordkeeping for decommissioning.
    * * * * *

    (b) * * *

    (2) Submit a certification that financial assurance for decommissioning has been provided in the amount of $225,000 by June 2, 2005 using one of the methods described in paragraph (e) of this section. For an applicant, this certification may state that the appropriate assurance will be obtained after the application has been approved and the license issued but before the receipt of licensed material. If the applicant defers execution of the financial instrument until after the license has been issued, a signed original of the financial instrument obtained to satisfy the requirements of paragraph (e) of this section must be submitted to NRC prior to receipt of licensed material. If the applicant does not defer execution of the financial instrument, the applicant shall submit to NRC, as part of the certification, a signed original of the financial instrument obtained to satisfy the requirements of paragraph (e) of this section.

    (c) * * *

    (2) Each holder of a specific license issued before July 27, 1990, and of a type described in paragraph (a) of this section shall submit a decommissioning funding plan as described in paragraph (d) of this section or a certification of financial assurance for decommissioning in an amount at least equal to $1,125,000 in accordance with the criteria set forth in this section. If the licensee submits the certification of Start Printed Page 57337financial assurance rather than a decommissioning funding plan, the licensee shall include a decommissioning funding plan in any application for license renewal. Licensees required to submit the $1,125,000 amount must do so by December 2, 2004.

    * * * * *

    (d) Each decommissioning funding plan must contain a cost estimate for decommissioning and a description of the method of assuring funds for decommissioning from paragraph (e) of this section, including means for adjusting cost estimates and associated funding levels periodically over the life of the facility. Cost estimates must be adjusted at intervals not to exceed 3 years. The decommissioning funding plan must also contain a certification by the licensee that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning and a signed original of the financial instrument obtained to satisfy the requirements of paragraph (e) of this section.

    * * * * *
    Start Part

    PART 70—DOMESTIC LICENSING OF SPECIAL NUCLEAR MATERIAL

    End Part Start Amendment Part

    5. The authority citation for part 70 continues to read as follows:

    End Amendment Part Start Authority

    Authority: Secs. 51, 53, 161, 182, 183, 68 Stat. 929, 930, 948, 953, 954, as amended, sec. 234, 83 Stat. 444, as amended, (42 U.S.C. 2071, 2073, 2201, 2232, 2233, 2282, 2297f); secs. 201, as amended, 202, 204, 206, 88 Stat. 1242, as amended, 1244, 1245, 1246 (42 U.S.C. 5841, 5842, 5845, 5846). Sec. 193, 104 Stat. 2835 as amended by Pub.L. 104-134, 110 Stat. 1321, 1321-349 (42 U.S.C. 2243).

    End Authority

    Sections 70.1(c) and 70.20a(b) also issued under secs. 135, 141, Pub. L. 97-425, 96 Stat. 2232, 2241 (42 U.S.C. 10155, 10161). Section 70.7 also issued under Pub. L. 95-601, sec. 10, 92 Stat. 2951 (42 U.S.C. 5851). Section 70.21(g) also issued under sec. 122, 68 Stat. 939 (42 U.S.C. 2152). Section 70.31 also issued under sec. 57d, Pub. L. 93-377, 88 Stat. 475 (42 U.S.C. 2077). Sections 70.36 and 70.44 also issued under sec. 184, 68 Stat. 954, as amended (42 U.S.C. 2234). Section 70.81 also issued under secs. 186, 187, 68 Stat. 955 (42 U.S.C. 2236, 2237). Section 70.82 also issued under sec. 108, 68 Stat. 939, as amended (42 U.S.C. 2138).

    Start Amendment Part

    6. In § 70.25, paragraphs (c)(2), (d), and (e) are revised to read as follows:

    End Amendment Part
    Financial assurance and recordkeeping for decommissioning.
    * * * * *

    (c) * * *

    (2) Each holder of a specific license issued before July 27, 1990, and of a type described in paragraph (a) of this section shall submit a decommissioning funding plan as described in paragraph (e) of this section or a certification of financial assurance for decommissioning in an amount at least equal to $1,125,000 in accordance with the criteria set forth in this section. If the licensee submits the certification of financial assurance rather than a decommissioning funding plan, the licensee shall include a decommissioning funding plan in any application for license renewal.

    * * * * *

    (d) Table of required amounts of financial assurance for decommissioning by quantity of material. Licensees required to submit the $1,125,000 amount must do so by December 2, 2004. Licensees required to submit the $225,000 amount must do so by June 2, 2005. Licensees having possession limits exceeding the upper bounds of this table must base financial assurance on a decommissioning funding plan.

    Greater than 104 but less than or equal to 105 times the applicable quantities of appendix B to part 30. (For a combination of isotopes, if R, as defined in § 70.25(a), divided by 104 is greater than 1 but R divided by 105 is less than or equal to 1.)$1,125,000
    Greater than 103 but less than or equal to 104 times the applicable quantities of appendix B to part 30. (For a combination of isotopes, if R, as defined in § 70.25(a), divided by 103 is greater than 1 but R divided by 104 is less than or equal to 1.)$225,000

    (e) Each decommissioning funding plan must contain a cost estimate for decommissioning and a description of the method of assuring funds for decommissioning from paragraph (f) of this section, including means for adjusting cost estimates and associated funding levels periodically over the life of the facility. Cost estimates must be adjusted at intervals not to exceed 3 years. The decommissioning funding plan must also contain a certification by the licensee that financial assurance for decommissioning has been provided in the amount of the cost estimate for decommissioning and a signed original of the financial instrument obtained to satisfy the requirements of paragraph (f) of this section.

    * * * * *
    Start Signature

    Dated at Rockville, Maryland this 29th day of September, 2003.

    For the Nuclear Regulatory Commission.

    Annette Vietti-Cook,

    Secretary of the Commission.

    End Signature End Supplemental Information

    Footnotes

    1.  For some types of licensees using very large amounts of radioactive material, a facility-specific cost estimate must be used.

    Back to Citation

    2.  Waste brokers are waste processors and waste collectors as defined in 10 CFR part 20, appendix G.

    Back to Citation

    3.  Estimate based on current numbers of licensees using each certification amount.

    Back to Citation

    4.  The estimate is based on numbers of licensees using each of the 3 certification amounts, and the differential between the revised certification amounts and former certification amounts for each of the 3 groups.

    Back to Citation

    5.  NUREG-1727, “NMSS Decommissioning Standard Review Plan,” Appendix F, September 2000, p. F26.

    Back to Citation

    6.  NUREG/CR-6280, “Technology, Safety, and Costs of Decommissioning a Reference Large Irradiator and Reference Sealed Sources,” Pacific Northwest Laboratory, January 1996.

    Back to Citation

    7.  “CPI Inflation Calculator,” U.S. Department of Labor, Bureau of Labor Statistics, http://www.bls.gov/​cpi.

    Back to Citation

    8.  NUREG-1307, Revision 9, p.6.

    Back to Citation

    9.  “Analysis of Decommissioning Certification Amounts for Materials Licensees (parts 30, 40, and 70),” ICF Consulting, 2000.

    Back to Citation

    10.  NUREG-1727 is available in the NRC Public Document Room, Room O-1F23, 11555 Rockville Pike, Rockville, MD. The NRC maintains an Agencywide Document Access and Management System (ADAMS), which provides text and image files of NRC's public documents. These documents may be accessed through the NRC's Public Electronic Reading Room on the Internet at http://www.nrc.gov/​reading-rm/​adams.html. If you do not have access to ADAMS or if there are problems in accessing the documents located in ADAMS, contact NRC Public Document Room (PDR) Reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr@nrc.gov.

    Back to Citation

    11.  Waste processor means an entity, operating under a Commission or Agreement State license, whose principal purpose is to process, repackage, or otherwise treat low-level radioactive material or waste generated by others prior to eventual transfer of waste to a licensed low-level radioactive waste land disposal facility.

    Back to Citation

    12.  Waste collector means an entity, operating under a Commission or Agreement State license, whose principal purpose is to collect and consolidate waste generated by others, and to transfer this waste, without processing or repackaging the collected waste, to another licensed waste collector, licensed waste processor, or licensed land disposal facility.

    Back to Citation

    13.  Copies of NUREG-0586 are available for inspection or copying for a fee from the NRC Public Document Room at O-1F23, 11555 Rockville Pike, Rockville, MD. Copies may be purchased at current rates from the U.S. Government Printing Office, P.O. Box 370892, Washington, DC 20402-9328 (telephone (202) 512-2249); or from the National Technology Information Service by writing NTIS at 5285 Port Royal Road, Springfield, VA 22161.

    Back to Citation

    [FR Doc. 03-25093 Filed 10-2-03; 8:45 am]

    BILLING CODE 7590-01-P

Document Information

Effective Date:
12/2/2003
Published:
10/03/2003
Department:
Nuclear Regulatory Commission
Entry Type:
Rule
Action:
Final rule.
Document Number:
03-25093
Dates:
December 2, 2003.
Pages:
57327-57337 (11 pages)
RINs:
3150-AG85: Financial Assurance Amendments for Materials Licenses
RIN Links:
https://www.federalregister.gov/regulations/3150-AG85/financial-assurance-amendments-for-materials-licenses
Topics:
Government contracts, Hazardous materials transportation, Intergovernmental relations, Nuclear materials, Packaging and containers, Radiation protection, Reporting and recordkeeping requirements, Scientific equipment, Security measures, Uranium
PDF File:
03-25093.pdf
CFR: (3)
10 CFR 30.35
10 CFR 40.36
10 CFR 70.25