96-27825. Williams Natural Gas Company; Notice of Amendment to a Request Under Blanket Authorization  

  • [Federal Register Volume 61, Number 211 (Wednesday, October 30, 1996)]
    [Notices]
    [Page 55983]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-27825]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP96-762-001]
    
    
    Williams Natural Gas Company; Notice of Amendment to a Request 
    Under Blanket Authorization
    
    October 24, 1996.
        Take notice that on October 9, 1996, Williams Natural Gas Company 
    (WNG), P.O. Box 3288, Tulsa, Oklahoma 74101, filed an amendment to its 
    prior notice request filed September 4, 1996, in Docket No. CP96-762-
    000 pursuant to Sections 157.205, 157.212(a), and 157.216(b) of the 
    Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 
    157.212, and 157.216) for authorization to replace and relocate the 
    Missouri Public Service (MPS) Sedalia town border setting, under WNG's 
    blanket certificate issued in Docket No. CP82-479-000, pursuant to 
    Section 7 of the Natural Gas Act, all as more fully set forth in the 
    request that is on file with the Commission and open to public 
    inspection.
        WNG proposes to reclaim the Sedalia double run, 10-inch orifice 
    meter setting and appurtenant facilities located in Section 34, 
    Township 46 North, Range 22 West, Pettis County, Missouri, and to 
    install a new triple 6-inch run orifice meter setting and appurtenant 
    facilities at the site of WNG's mainline gate in Section 35, Township 
    46 North, Range 23 West, Pettis County, Missouri. WNG originally stated 
    that the $175,886 estimated cost to replace the Sedalia town border 
    setting would be fully reimbursed by MPS. WNG now states that the 
    statement that the project will be fully reimbursed by MPS was made in 
    error and the project will, in fact, be only partially reimbursed by 
    MPS.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-27825 Filed 10-29-96; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
10/30/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-27825
Pages:
55983-55983 (1 pages)
Docket Numbers:
Docket No. CP96-762-001
PDF File:
96-27825.pdf