95-26937. Sequoyah Fuels Corporation; Issuance of Director's Decision Under 10 CFR Part 2.206  

  • [Federal Register Volume 60, Number 210 (Tuesday, October 31, 1995)]
    [Notices]
    [Pages 55384-55388]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-26937]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 40-8027]
    
    
    Sequoyah Fuels Corporation; Issuance of Director's Decision Under 
    10 CFR Part 2.206
    
    I. Introduction
    
        Notice is hereby given that the Director, Office of Nuclear 
    Material Safety and Safeguards, U.S. Nuclear Regulatory Commission 
    (NRC) has issued a Director's Decision under 10 CFR 2.206 regarding the 
    Sequoyah Fuels Facility in response to a petition received from Ms. 
    Diane Curran (Petitioner), dated March 14, 1995, on behalf of the 
    Native Americans for a Clean Environment. (NACE) The petition also 
    considered a subsequent letter from Petitioner dated March 31, 1995.
        The petition was referred to the staff for consideration pursuant 
    to 10 CFR 2.206 of the Commission's regulations. For the reasons stated 
    in the enclosed ``Director's Decision under 10 CFR 2.206,'' items 1, 3, 
    and 4 of the Petition have been denied, and item 2 is moot.
        Native Americans for a Clean Environment (NACE) submitted to the 
    Nuclear Regulatory Commission (NRC), a ``Petition for an Order 
    Requiring Sequoyah Fuels Corporation to File a Final Site 
    Characterization Plan (SCP) and for an Order to Obtain a License 
    Amendment'' (Petition) dated March 11, 1995. NACE requested NRC to take 
    action with respect to the Sequoyah Fuels Corporation (SFC or Licensee) 
    pursuant to 10 CFR 2.206. The Petitioner requests that NRC:
        (1) Reverse the NRC staff's decision to permit SFC to proceed with 
    site characterization without submitting a final Site Characterization 
    Plan (SCP), by issuing an Order or a Confirmatory Action Letter 
    obliging SFC to submit a final SCP by a date certain;
        (2) Obtain a copy of the Environmental Protection Agency's (EPA) 
    title search or perform a title search of all property used in 
    connection with the SFC license, in order to clarify the identity and 
    ownership of all property subject to NRC License No. SUB-1010;
        (3) Issue an order forbidding SFC, Sequoyah Fuels International 
    Corporation, Sequoyah Holding Corporation, or any other associated 
    corporation that holds title to property under NRC License No. SUB-1010 
    from transferring any interest in any of its property before SFC 
    applies for and receives a license amendment authorizing transfer; and
        (4) Before issuing any such license amendment, find reasonable 
    assurance that any entity acquiring an interest in the SFC property 
    fully understands the nature of the liabilities and responsibilities it 
    is undertaking for cleanup and long-term care of the site and that it 
    has the financial capability to carry out those responsibilities.
        The Petition alleges the following bases for its requests:
        (1) The NRC staff illegally and improperly excused SFC from its 
    obligation to submit a final SCP;
        (2) SFC is presenting a ``Trust Indenture'' to several towns and 
    the county of Sequoyah for the creation of an industrial park;
        (3) Neither SFC's letter to Mr. Main (Secretary of Commerce, 
    Oklahoma Department of Commerce), the Fact Sheet, nor the Trust 
    Agreement, itself, refers to the fact that SFC has been ordered by NRC 
    and EPA to characterize the extent of the contamination in the 1,400 
    acres that surround the 85-acre processing area, the focus of site 
    characterization and remediation efforts; nor do those documents refer 
    to the other sources of potential contamination, consisting of 
    groundwater migration from the admittedly contaminated processing area, 
    effluent streams and ditches, and the Carlisle School (located on the 
    land proposed for an industrial park, and used by SFC as a laboratory);
        (4) The Trust Indenture depicts the 1,400 acres of land subject to 
    NRC License No. SUB-1010 as the candidate area for the industrial park; 
    SFC has made conflicting representations regarding the size of the 
    ``facility'' or ``site'' to NRC and in the Trust Indenture. SFC 
    responded to the Petition by a letter dated March 29, 1995, and 
    requests that the Petition be denied in all respects.
        By letter dated March 31, 1995, NACE supplemented its Petition. 
    NACE states that SFC is conducting site characterization by utilizing 
    the EPA Facility Investigation Workplan (FIW), which was prepared for 
    the EPA pursuant to requirements of the Resource Conservation and 
    Recovery Act (RCRA). Petitioner asserts that by relying on the FIW to 
    conduct site characterization, SFC has neither understood nor 
    implemented NRC staff criticisms of the draft SCP. Petitioner asserts 
    that NRC should require SFC to submit a written final SCP because the 
    FIE does not:
        (1) Resolve NRC comments related to site hydrogeology and vertical 
    and lateral contamination;
        (2) Resolve NRC sample density concerns; or
        (3) Provide for characterization of the DUF4 processing, 
    decorative pond, and parking lot areas.
        By letter dated May 10, 1995, the Director, Office of Nuclear 
    Material Safety and Safeguards acknowledged receipt of the Petition, 
    and informed the Petitioner that the Petition would be evaluated under 
    10 CFR 2.206 of the Commission's regulations.
        I have completed my evaluation of the matters raised by the 
    Petitioner and have determined that, for the reasons stated below, the 
    Petition is denied in part, was satisfied in part, and NRC regulations 
    address the Petitioner's concerns related to the requests for issuance 
    of orders related to transfer of property.
    
    II. Background
    
        From 1970 until July 6, 1993, SFC operated a uranium conversion 
    facility at a site located in Gore, Oklahoma, under the authority of 
    NRC License No. SUB-1010, issued pursuant to 10 CFR Part 40. The main 
    process was the conversion of uranium oxide (yellowcake) to uranium 
    hexafluoride. A second process, initiated in 1987, consisted of the 
    conversion of depleted uranium hexafluoride to uranium tetrafluoride, 
    the first step in producing depleted uranium metal.
        After the discovery of contaminated soil surrounding structures 
    used by SFC for its licensed activities, NRC staff issued an order 
    suspending SFC's authorization to operate its conversion facilities. 
    See ``Order Modifying License (Effective Immediately) and Demand for 
    Information,'' EA 91-067 (October 3, 1991). After studies by SFC, 
    operational and organizational changes by SFC, extensive NRC 
    inspections, and several public meetings, NRC, on April 16, 1992, 
    lifted the order suspending the SFC license and authorized SFC to 
    resume operation of its conversion facility. 
    
    [[Page 55385]]
    
        In November 1992, SFC (and subsequently in writing) informed NRC 
    that operation of its main process for the conversion of uranium oxide 
    (yellowcake) to uranium hexafluoride was permanently terminated and 
    that the second process, the conversion of depleted uranium 
    hexafluoride to uranium tetrafluoride, would be terminated by July 
    1993. SFC formally notified NRC of its intentions to terminate all 
    conversion processes and seek license termination in accordance with 10 
    CFR 40.42(e), in a letter dated February 16, 1993. In addition, a 
    proposed plan to address decommissioning issues related to the SFC 
    facility, entitled ``Preliminary Plan for Completion of Decommissioning 
    (PPCD),'' was enclosed in its letter of February 16, 1993.
        By letter dated March 23, 1993, NRC staff notified SFC that its 10 
    CFR 40.42(e) notification had been accepted, and that activities at the 
    site should be limited to those related to decommissioning. By letter 
    dated July 7, 1993, SFC notified NRC staff that SFC had ceased all 
    operational licensed activities. Since that time, SFC has restricted 
    its activities to disposal of contaminated material and planning for 
    decommissioning.
        On August 4, 1993, SFC and EPA Region VI signed an Administrative 
    Order on Consent (AOC), establishing a schedule for compliance with 
    Section 3008(h) of the Solid Waste Disposal Act, as amended by the 
    RCRA, as further amended by the Hazardous and Solid Waste Amendments of 
    1984, 42 USC 6928(h). The AOC required SFC to perform a number of tasks 
    aimed at monitoring site conditions, site characterization, corrective 
    measures, and financial assurance. A key element of the AOC is the RCRA 
    Facility Investigation (RFI) Workplan. The RFI Workplan data needs 
    closely parallel those of an NRC SCP. For SFC's site, both the RFI 
    Workplan and the SCP involve characterization of much of the same 
    property. The major difference between the RFI Workplan and the SCP 
    rests only on the constituents that are analyzed (nonradioactive 
    materials for EPA and radioactive materials for NRC).
        Common to both plans is the characterization of the soil, bedrock, 
    and groundwater underlying the site. SFC agreed to drill a series of 
    wells to the next lower water-bearing strata to better define the 
    geology underlying the site and to sample for contamination. These 
    wells are in addition to the 100 wells previously install by SFC at the 
    site. Whether or not the deeper wells planned by SFC to address EPA 
    concerns will also satisfy NRC concerns related to the vertical extent 
    of radiological contamination will have to await the evaluation of 
    sample analyses.
        To avoid unnecessary duplicative regulatory actions, EPA and NRC 
    drafted a site-specific Memorandum of Understanding (MOU). Under the 
    terms of this MOU, EPA and NRC will exchange pertinent documents, keep 
    each other informed of planned actions, and, to the extent possible, 
    coordinate major characterization and remediation tasks on similar 
    schedules. The MOU was signed by EPA on September 21, 1995, and by NRC 
    on September 25, 1995.
        SFC submitted to EPA a draft RFI Workplan in January 1994. EPA 
    reviewed the draft RFI Workplan and provided SFC comments in a letter 
    dated August 25, 1994. Based on the comments provided by EPA, SFC made 
    changes to the draft RFI Workplan and a final Workplan was approved by 
    EPA in December 1994. In accordance with the requirements of the AOC, 
    SFC must submit a final RFI Report to EPA by December 1995.
        SFC submitted a draft SCP to NRC in January 1994. Interested 
    persons, including EPA, the United States Geological Survey (USGS), and 
    NACE reviewed the draft SCP and provided comments to NRC. Consistent 
    with the staff's commitment to NACE, in a letter from J.H. Austin (NRC) 
    to D. Curran (NACE), dated December 9, 1993, to keep NACE involved in 
    the review process, the NACE comments were discussed with 
    representatives of NACE, NRC and SFC in a May 31, 1994, meeting.
        NRC staff performed an extensive review of the draft SCP and of all 
    the comments regarding the draft SCP. Where appropriate, NRC staff 
    factored those comments into NRC staff's comments, which were 
    transmitted to SFC by letter dated November 3, 1994. The essence of NRC 
    staff's comments was that SFC must do substantially more sampling than 
    proposed in the draft SCP. Additional sampling is necessary to reliably 
    identify the types and extent of contamination on and around the SFC 
    site. NRC staff requested that SFC address the staff's comments, or 
    provide the basis for not making changes to the SCP.
        In its November 1994 quarterly report to EPA, required by the AOC, 
    SFC raised concerns related to possible duplication of SFC's 
    decontamination and decommissioning efforts that could result in 
    unnecessarily increased costs.
        In January and February 1995, NRC staff engaged in technical 
    discussions with SFC regarding the November 3, 1994, comments of the 
    staff concerning the draft SCP. The discussions covered a broad range 
    of issues related to site characterization and scheduling.
        By letter dated February 5, 1995, the Director, Division of Waste 
    Management, Office of Nuclear Material Safety and Safeguards, confirmed 
    NRC staff's understanding of SFC's verbal commitment, by telephone in 
    early February 1995, to use NRC staff's comments of November 3, 1994, 
    during site characterization and in SFC's preparation of its Site 
    Characterization Report (SCR). Furthermore, NRC agreed with SFC that 
    the schedule for the SCR should parallel that for the RFI Report, in 
    order to minimize possible redundancy and associated costs, and to 
    facilitate the effective utilization of SFC resources. Accordingly, NRC 
    gave SFC a due date of January 15, 1996, for submission of a draft SCR. 
    The staff also reminded SFC that NRC may establish legally binding 
    requirements, if necessary, to ensure timely and effective remediation 
    of Site Decommissioning Management Plan (SDMP) sites. The SFC facility 
    is an SDMP site. In its March 29, 1995, response to the Petition, SFC 
    again committed to address the NRC's comments on the SCP during conduct 
    of the site characterization effort. SFC confirmed its understanding of 
    the staff's November 3, 1994, comments by a letter dated June 2, 1995, 
    in which SFC again committed to incorporate those staff comments into 
    its SCR.
    
    III. Discussion
    
    A. Petitioner Requests That NRC Staff Reverse Its Decision To Permit 
    SFC To Proceed With Site Characterization Without Submitting a Revised 
    SCP, by Issuing an Order or Confirmatory Action Letter Requiring SFC To 
    Submit a Written Final SCP
    
        Petitioner contends that by not requiring SFC to submit a written 
    final SCP, NRC staff illegally and improperly excused SFC from its 
    obligations in violation of the:
        (a) Timeliness in Decommissioning Rule;
        (b) NRC's ``Action Plan to Ensure Timely Cleanup of Site 
    Decommissioning Management Plan Sites'' (Action Plan), 57 Fed. Reg. 
    13389 (April 16, 1992);
        (c) NRC's December 29, 1992, Demand for Information to SFC;
        (d) MOU between NRC and EPA; and
        (e) NRC's commitments to Petitioner in a letter dated December 9, 
    1993, that SFC would be required to demonstrate how it would sample all 
    potentially contaminated areas as part of the SCP.
        NRC staff weighed the potential benefits, and the increased costs 
    of and 
    
    [[Page 55386]]
    delays in decommissioning, of requesting SFC to revise its draft SCP in 
    accordance with NRC staff comments, which SFC understood and had 
    already agreed to incorporate into the site characterization process 
    and SCR. NRC staff concluded that the objectives of site 
    characterization could be met, and data appropriate to support a 
    proposed decommissioning alternative could be produced, if NRC staff's 
    comments were implemented during site characterization. NRC staff's 
    action was intended to avoid potentially costly delays in 
    decommissioning and to prevent duplication of regulatory actions, based 
    on work already underway as a part of the EPA-approved RFI Workplan.
        Additionally, the staff's action was consistent with agency efforts 
    to streamline the Site Decommissioning Management Plan (SDMP) 
    regulatory review process.1 The SFC site is an SDMP site. This 
    streamlining involves, among other things, discontinuance of NRC staff 
    review of SCPs and SCRs prior to the submittal of decommissioning 
    plans. Site characterization information will be considered by NRC 
    staff in its review of decommissioning plans. NRC regulations do not 
    require the submission of SCPs or SCRs, but do require site 
    characterization data to be submitted with the decommissioning plan. 
    See 10 CFR 40.42(f)(4)(i). Streamlining the SDMP process is consistent 
    with NRC regulations.
    
        \1\ On May 19, 1995, the NRC staff briefed the Commission on 
    SDMP Policy and Program issues, including the staff's implementation 
    of streamlining. 10 CFR 40.42(f)(4)(i). Streamlining the SDMP 
    process is consistent with NRC regulations.
    ---------------------------------------------------------------------------
    
        Streamlining promotes a more coordinated and focused review of the 
    licensee's characterization information and place greater emphasis on 
    issues that affect the selection and implementation of a 
    decommissioning approach.
        Contrary to Petitioner's assertion, NRC staff's action was 
    consistent with the Timeliness in Decommissioning rule. Those 
    amendments to NRC regulations establish specific time periods for 
    submission of a decommissioning plan and completion of decommissioning, 
    and were intended to reduce potential risk to public health and the 
    environment at facilities after licensed activities have ceased. See 
    ``Timeliness in Decommissioning of Materials Facilities,'' 59 Fed. Reg. 
    36026 (July 15, 1994). The staff's February 5, 1995, letter allowed SFC 
    to proceed with site characterization on the condition that SFC include 
    in its SCR the staff's November 3, 1994, comments regarding the draft 
    SCP. The staff determined that inclusion of those comments would 
    produce adequate site characterization and would reduce delay. Although 
    site characterization and the data derived during site characterization 
    are necessary inputs to a decommissioning plan, 2 SCPs and SCRs 
    are not expressly required by NRC regulations. The staff did not 
    release SFC from the ``timeliness'' rule or from the requirement to 
    submit a decommissioning plan. See 10 CFR 40.42(f)(1). The staff's 
    action reduced potential delays in site characterization and 
    decommissioning, and cannot be considered to have contributed to any 
    delay in SFC's decommissioning the SFC site.
    
        \2\ The licensee's decommissioning plan must include a 
    description of the site, buildings, and outside areas affected by 
    licensed activities. 10 CFR 40.42(f)(4)(i).
    ---------------------------------------------------------------------------
    
        Contrary to being in violation of the NRC's Action Plan, NRC 
    staff's February 5, 1995, letter to SFC was consistent with the plan. 
    The Action Plan was intended to encourage compliance with NRC 
    timeliness in decommissioning regulations. The Action Plan is not 
    itself a rule and contains no enforceable standards. The Action Plan 
    refers to submittal of an SCP, but does not require NRC approval. The 
    Action Plan encourages licensees to enter into early consultation with 
    NRC staff regarding site characterization and decommissioning issues. 
    Such consultation is intended to address site-specific conditions to 
    ensure that site characterization is appropriately planned and 
    conducted, and of sufficient depth to support a selected 
    decommissioning option. Consistent with the Action Plan, NRC staff 
    engaged in site-specific technical discussions with SFC regarding not 
    only NRC's comments on the draft SCP, but also the comments of NACE, 
    the USGS and EPA. See Section II, supra. The NRC staff's February 5, 
    1995, letter to SFC was consistent with the Action Plan, and cannot be 
    considered to have contributed to any delay in compliance with 
    timeliness requirements for decommissioning, for the same reasons that 
    the staff's action was consistent with the Timeliness in 
    Decommissioning Rule.
        Petitioner does not explain, nor is it apparent how, the NRC 
    staff's February 5, 1995, letter contravened the December 29, 1992, 
    Demand for Information (DFI) to SFC. As Petitioner notes, the February 
    13, 1993, Preliminary Plan for Decommissioning, submitted by SFC in 
    response to the DFI, commits SFC to submission of an SCP to NRC and to 
    implementation of the SCP by early 1994. The staff in its February 5, 
    1995, letter did not delay the submission or implementation of the SCP. 
    To the contrary, the staff permitted SFC to proceed expeditiously with 
    an SCP which NRC had reviewed and considers adequate, as long as the 
    staff's November 3, 1994, comments are incorporated, which SFC has 
    undertaken to do.
        Contrary to Petitioner's assertion, NRC staff's action in its 
    letter of February 5, 1995, did not violate the (then draft) MOU 
    between NRC and EPA. The then draft MOU, as well as the final MOU, 
    state that NRC will ensure that SFC develops and implements an SCP, 
    which NRC staff has done. Moreover, in the spirit of the EPA and NRC 
    site-specific MOU, NRC and EPA have worked together to avoid 
    unnecessary duplicative regulatory actions and their attendant costs. 
    Specifically, after consultation with the EPA, NRC staff agreed in its 
    February 5, 1995, letter to SFC's request that the schedule for site 
    characterization and submission of the SCR should parallel that of the 
    EPA RFI Workplan. The development of the EPA MOU and NRC MOU was a 
    major consideration in NRC staff's action allowing SFC to proceed with 
    site characterization and to incorporate NRC staff's comments in the 
    SCR, rather than to require submission of yet another version of the 
    SCP.
        Contrary to the Petitioner's assertions, NRC staff's action by its 
    letter of February 5, 1995, did not violate NRC's commitments to 
    Petitioner, made in a letter dated December 9, 1993, that SFC would be 
    required to demonstrate how it would sample all potentially 
    contaminated areas as part of the SCP. The December 9, 1993, letter 
    also stated that NACE's concerns would be addressed during NRC staff's 
    review of the SCP.
        NRC staff met these commitments to NACE. NACE reviewed the SFC 
    draft SCP and provided comments to NRC staff. NACE's comments were 
    discussed in a meeting on May 31, 1994, with representatives from NACE, 
    NRC, and SFC. All applicable NACE comments were incorporated into NRC 
    staff's comments and transmitted to SFC by letter dated November 3, 
    1994. SFC verbally committed, by telephone in early February 1995, to 
    use NRC staff's comments of November 3, 1994, during site 
    characterization and in SFC's preparation of its SCR. SFC confirmed its 
    understanding of the staff's November 3, 1994, comments by a letter 
    dated June 2, 1995, in which SFC again committed to incorporate those 
    staff comments into its SCR. Accordingly, 
    
    [[Page 55387]]
    contrary to Petitioner's assertion, there is no basis to conclude that 
    NACE's concerns will not in fact be addressed. Moreover, NRC remains 
    committed to ensuring that SFC conduct a complete and accurate 
    characterization of all radiological contamination on the SFC site and 
    on property affected by SFC's licensed activities, through reviews of 
    SFC's SCR and a subsequent decommissioning plan.
        By letter dated March 31, 1995, NACE supplemented its Petition. 
    NACE states that SFC is conducting site characterization by utilizing 
    the RCRA Facility Investigation Workplan. Petitioner asserts that by 
    relying on the EPA Workplan to conduct site characterization, SFC has 
    neither understood nor implemented NRC staff criticisms of the draft 
    SCP. Petitioner asserts that NRC should require SFC to submit a written 
    final SCP because the EPA Workplan does not:
        (1) Resolve NRC comments related to site hydrogeology and vertical 
    and lateral contamination;
        (2) Resolve NRC sample density concerns; or
        (3) Provide for characterization of the DUF4 processing, 
    decorative pond, and parking lot areas.
        As explained above, NRC staff concluded after a series of 
    discussions with SFC, that SFC does understand the staff's November 3, 
    1994, comments regarding the draft SCP. Moreover, SFC has committed 
    itself to incorporating those staff comments during site 
    characterization and in the SCR. In addition, NRC staff concludes, 
    after review of the EPA-approved RFI Workplan, that:
        (a) The approved RFI Workplan adequately addresses NRC comments 
    regarding questions of hydrogeology and the vertical and lateral extent 
    of contamination;
        (b) The RFI Workplan, draft SCP, and the SFC commitment to 
    incorporate NRC staff's comments on the draft SCP into site 
    characterization activities will together ensure adequate sampling for 
    site characterization; and
        (c) The SCP, provides for adequate characterization of the 
    DUF4 processing area (Unit 29), the decorative pond (Unit 26), and 
    parking lot (Unit 31) (see Figure 2 of the SCP).
        NRC staff has neither violated, nor excused SFC from complying 
    with, any NRC regulatory requirements, the MOU between NRC and EPA, any 
    NRC staff commitments to Petitioners, or the December 29, 1992, DFI to 
    SFC. Petitioner has raised no health and safety concern arising from 
    NRC staff's action by letter of February 5, 1995, permitting SFC to 
    address and implement the staff's November 3, 1994, comments during 
    site characterization and in the SCR. Additionally, the staff's action 
    was consistent with agency efforts to streamline the SDMP review 
    process. Furthermore, to require submission of a written final SCP 
    would unnecessarily delay decommissioning of the SFC site and unduly 
    raise the costs of decommissioning.
        In view of the above, there is no basis to require SFC to submit a 
    written final SCP.
    
    B. Petitioner Requests That NRC Obtain From EPA a Copy of Its Title 
    Search or Perform a Title Search of all Property Used in Connection 
    With the SFC License
    
        By letter dated April 20, 1995, Mark W. Potts (EPA Region VI), 
    provided to Lance Hughes, on behalf of NACE, a copy of a document 
    entitled ``Preliminary Property Search Document; Sequoyah Fuels 
    Corporation; Gore, Oklahoma.'' The document is dated July 26, 1994, and 
    was prepared by PRC Environmental Management, Inc. for EPA. The 
    document identifies SFC as the sole owner of the 85-acre process area 
    of the Sequoyah Fuels facility and the approximately 2,100 acres of 
    land surrounding the facility. A copy of this report has been placed in 
    the SFC licensing docket and is available through either NRC's Public 
    Document Room (PDR) at 2120 L St. NW., Washington, DC 20037, or the 
    local PDR (LPDR) at the Stanley Tubbs Memorial Library, 101 E. 
    Cherokee, Sallisaw, OK 21801.
        Petitioner has identified no inconsistencies between the Trust 
    Indenture and any representations to NRC regarding the size of the 
    ``facility'' or ``site''. The land subject NRC license SUB-1010 is 
    principally the 85-acre site along with any adjacent lands that have 
    been affected by licensed activities.\3\ The copy of a ``Trust 
    Indenture'' submitted by Petitioners neither describes the SFC facility 
    or site, nor does it describe any lands subject to the Trust 
    Indenture.\4\ Article V merely identifies the Trust Estate as all 
    property coming into the possession of the trustees pursuant to the 
    Trust Indenture. The enclosure to a letter dated August 18, 1994, from 
    John Ellis, President, SFC, to the Oklahoma Department of Commerce, 
    both of which were attached to the Petition, describes the proposed 
    industrial park as a site of 1,430 acres on the east bank of the Kerr-
    McClelland Waterway. Clearly the proposed industrial park surrounds or 
    includes, in part, the SFC site, but is not identified by the Trust 
    Indenture as all or part of the property subject to NRC License No. 
    SUB-1010.
    
        \3\ Licensed activities do not include raffinate spreading 
    because the treated raffinate is released for unrestricted use prior 
    to spreading. However, if NRC determined that treated raffinate 
    spreading significantly affected adjacent lands, then NRC would 
    consider the need for additional characterization and remediation.
        \4\ SFC denies having contributed any corporate resources to 
    drafting or developing the proposed Trust Indenture or in 
    circulating it to local communities, but states that it has openly 
    pursued development of an industrial park with local and state 
    officials to replace jobs lost as a result of closing the SFC plant. 
    SFC states that a local community group, SAFEST, has been working on 
    the Trust Indenture with the Sequoyah County Commission. See Letter 
    of John H. Ellis, President, SFC, dated March 29, 1995, to James M. 
    Taylor, Executive Director for Operations, NRC.
    ---------------------------------------------------------------------------
    
        Petitioners have not raised a safety concern regarding the identity 
    and ownership of lands subject to NRC License No. SUB-1010. Moreover, 
    because EPA provided a copy of its title search the Petitioner's 
    request has been satisfied.
    
    C. Petitioner Requests That, Before Permitting Transfer of Land Subject 
    to License No. SUB-1010, NRC Find Reasonable Assurance That Any Entity 
    Acquiring an Interest in the SFC Property Fully Understands the Nature 
    of the Liabilities and Responsibilities It Is Undertaking for Cleanup 
    and Long-term Care of the Site and That It Has the Financial Capability 
    to Carry Out Those Responsibilities
    
        NRC regulations at 10 CFR 40.42(c)(2) and 40.42(d), and License 
    Condition No. 14 of NRC License No. SUB-1010, require that any real 
    property subject to the License or affected by licensed activities must 
    be remediated by SFC in accordance with an approved decommissioning 
    plan, such that the property is suitable for release in accordance with 
    NRC requirements. This means that SFC may not transfer nor release, by 
    sale or any other means, property subject to NRC License No. SUB-1010, 
    or property affected by SFC's licensed activities, until SFC remediates 
    such property and SFC demonstrates that the property meets NRC criteria 
    for release.
        It is not apparent from the NACE Petition, and no information has 
    come to the attention of NRC staff to indicate, that there has been a 
    transfer of any real property subject to or affected by activities 
    conducted pursuant to NRC License No. SUB-1010. It does appear that 
    several local governmental authorities, including Sequoyah County and 
    the cities of Gore, Vian and Webbers Falls, have entered into an 
    agreement to participate in the proposed Trust Indenture.
    
    [[Page 55388]]
    
        In its response to the Petition, SFC committed to inform NRC of any 
    proposal SFC receives for transfer of property adjacent to the 
    industrial area, before SFC acts on any such proposal. SFC also states 
    that at some future time, SFC may dispose of real property unaffected 
    by licensed operations at the SFC facility, and would do so only after 
    notifying NRC. In the case of affected areas, SFC states that it will 
    dispose of such property that has been released by NRC, after SFC 
    demonstrates that appropriate criteria have been met.
        Before real property used in connection with or affected by 
    activities conducted pursuant to NRC License No. SUB-1010 could be 
    transferred to a person without authority to engage in NRC-licensed 
    activities, that property must be decommissioned to meet the criteria 
    for release for unrestricted use. See 10 CFR 40.4 and 40.42, and 
    License SUB-1010, Condition 14. Since the proposed Trust Indenture 
    would involve the transfer of land for the purposes of an industrial 
    park, it appears that the potential transferees have no plan to engage 
    in NRC-licensed activities. Thus, the decommissioning criteria for 
    release of such property would be for unrestricted use.\5\ If SFC were 
    to decommission property used in connection with its licensed 
    activities to meet NRC criteria for release for unrestricted use, the 
    transferee would assume no obligation to remediate or to engage in 
    long-term care of such property, and NRC would have no regulatory 
    authority over the transfer of or the transferees of such property.
    
        \5\ The Commission is currently evaluating proposed changes to 
    the rules governing release criteria. See ``Radiological Criteria 
    for Decommissioning,'' 59 Fed. Reg. 43200 (August 22, 2994). SFC 
    will have to comply with all NRC requirements for release to 
    unlicensed individuals under any revised rules.
    ---------------------------------------------------------------------------
    
        If property used in connection with activities conducted pursuant 
    to NRC License No. SUB-1010 were transferred to a person who seeks 
    authority to engage in NRC-licensed activities, including 
    decommissioning activities such as remediation or long-term care, SFC 
    would be required to obtain written permission from NRC prior to the 
    transfer. See 10 CFR 40.46. At that time, it would be appropriate for 
    NRC to ensure that the transferee is capable of meeting NRC 
    requirements for decommissioning and all other applicable licensing 
    requirements and the transferee must obtain an NRC license. In view of 
    the above, Petitioners concerns about the potential transfer of 
    property to the Trust and state, and potential transferees of such 
    property, are adequately addressed by applicable regulations.
    
    D. Petitioner Requests That NRC Staff Issue an Order Forbidding SFC, 
    Sequoyah Fuels International Corporation, Sequoyah Holding Corporation, 
    or Any Other Associated Corporation That Holds Title to Property 
    Subject to NRC License No. SUB-1010, From Transferring Any Interest in 
    Such Property Before SFC Applies for and Receives a License Amendment 
    Authorizing Such a Transfer
    
        As explained above, SFC owns the land subject to NRC License No. 
    SUB-1010. Before SFC may transfer or release any property used in 
    connection with, or affected by, its licensed activity to a person not 
    authorized to engage in NRC-licensed activity, that property must be 
    remediated in accordance with an approved decommissioning plan to meet 
    NRC criteria for release for unrestricted use. See Section III.C, 
    supra. There is no NRC requirement that a licensee obtain NRC 
    permission to transfer property which has been remediated to meet NRC's 
    criteria for release for unrestricted use.
        If SFC were to transfer property subject to the license or affected 
    by licensed activity to persons for the purpose of engaging in licensed 
    activity, 10 CFR 40.46 requires that SFC obtain written permission from 
    NRC before transferring such property and the transferees must obtain 
    an NRC license. Petitioners, however, have provided no evidence that 
    such a transfer is contemplated or imminent.
        Petitioners have raised no safety concern regarding a potential 
    transfer of property used in connection with or affected by activities 
    pursuant to NRC License No. SUB-1010, or potential transferees of such 
    property. See Section III.C., supra. Moreover, since protection of the 
    public health and safety, in the event of a transfer of such property 
    to the proposed Trust Indenture, is already accomplished by NRC 
    regulations, there is no justification to issue the requested order.
    
    IV. Conclusion
    
        The institution of proceedings pursuant to 10 CFR 2.202 is 
    appropriate only where substantial health and safety issues have been 
    raised. See Consolidated Edison Company of New York (Indian Point, 
    Units 1, 2, and 3), CLI-75-8, 2 NRC 173, 175-176 (1975); Washington 
    Public Power Supply Systems (WPPSS Nuclear Project No. 2), DD-84-7, 19 
    NRC 899 (1984). This is the standard I have applied to determine 
    whether the action requested by Petitioner is warranted. For the 
    reasons given above, Petitioner's request that SFC ordered to submit a 
    written final SCP by a date certain is denied. Petitioner's request 
    that NRC perform a title search of property subject to NRC License No. 
    SUB-1010 was satisfied. Action on Petitioner's request for an order 
    forbidding the transfer of any interest in land subject to NRC License 
    No. SUB-1010 before SFC applies for and receives a license amendment 
    permitting such transfers is unnecessary because applicable regulations 
    address Petitioners concerns. Likewise, Petitioner's request that, 
    before granting such a license amendment application, NRC ensure that 
    potential purchasers of property be subject to NRC License No. SUB-1010 
    to fully be apprised of their obligations for site remediation and 
    long-term care and that NRC ensure such potential purchasers are 
    financially qualified to do so, is unnecessary because applicable 
    regulations address Petitioner's concerns.
        As provided by 10 CFR 2.206(c), a copy of this Decision will be 
    filed with the Secretary of the Commission for the Commission's review. 
    The Decision will become the final action of the Commission 25 days 
    after issuance, unless the Commission on its own motion institutes 
    review of the Decision within that time.
    
        Dated at Rockville, Maryland, this 23 day of October, 1995.
    
        For the Nuclear Regulatory Commission.
    Carl J. Paperiello,
    Director, Office of Nuclear Material Safety and Safeguards.
    [FR Doc. 95-26937 Filed 10-30-95; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
10/31/1995
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
95-26937
Pages:
55384-55388 (5 pages)
Docket Numbers:
Docket No. 40-8027
PDF File:
95-26937.pdf