97-28910. Record of Decision for the Navajo Transmission Project (DOE/EIS- 0231)  

  • [Federal Register Volume 62, Number 211 (Friday, October 31, 1997)]
    [Notices]
    [Pages 58966-58968]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-28910]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Western Area Power Administration
    
    
    Record of Decision for the Navajo Transmission Project (DOE/EIS-
    0231)
    
    AGENCY: Western Area Power Administration, DOE.
    
    ACTION: Record of Decision.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Based upon the analysis and information contained in the 
    Navajo Transmission Project (NTP) Draft and Final Environmental Impact 
    Statements (EIS), the Department of Energy (DOE), Western Area Power 
    Administration (Western), has decided that should the NTP be built, it 
    should follow the preferred alternative described in the NTP Final EIS. 
    This is the alternative identified in the EIS documents as the Kaibito 
    1 (K1) for the eastern half of the project area, and the Northern 1 
    West (N1W) for the western half. The K1 lies between the Shiprock 
    Substation and either the Red Mesa, Copper Mine, or Moenkopi Substation 
    sites. It parallels the existing Western 230-kilovolt (kV) Shiprock-to-
    Glen Canyon and 345-kV Glen Canyon-to-Pinnacle Peak transmission lines 
    for most of its route. The N1W lies between the Moenkopi and 
    Marketplace Substation sites and parallels an existing 500-kV 
    transmission line for most of its route.
        In making this decision, Western evaluated: (1) alternatives to the 
    proposed project, and (2) alternatives that cover the reasonable range 
    of options for siting and constructing a 500-kV transmission line. 
    Western released the NTP Draft EIS in September 1996. The Notice of 
    Availability for the Final EIS was published on August 8, 1997. This 
    Record of Decision is pursuant to the Council on Environmental Quality 
    regulations (40 CFR Parts 1500-1508), which implement the procedural 
    provisions of the National Environmental Policy Act, and DOE's 
    regulations (10 CFR Part 1021).
    
    DATES: This decision will become effective October 31, 1997.
    
    FOR FURTHER INFORMATION CONTACT: Mr. Nicholas Chevance, NTP EIS Project 
    Manager, Corporate Services Office, Western Area Power Administration, 
    1627 Cole Boulevard, Golden, CO 80123-3398, (303) 275-1713.
    
    SUPPLEMENTARY INFORMATION:
    
    Background
    
        Dine Power Authority (DPA), an enterprise of the Navajo Nation, 
    requested assistance from Western in 1993 in planning for the 
    construction, operation, and maintenance of a 500-kV transmission line 
    from the Four Corners area in northwestern New Mexico across northern 
    Arizona to a terminus in southern Nevada. As a Federal power marketing 
    agency, Western is responsible for marketing and transmitting power 
    from Federal power projects in the region. Since the 1960's, Western 
    and its predecessor agency, the Bureau of Reclamation, have been 
    assisting the Navajo Nation in meeting its energy needs through firm-
    energy agreements with the Navajo Tribal Utility Authority, a Navajo 
    Nation enterprise providing utility services and various energy related 
    projects. Western has provided technical assistance to DPA with the 
    NTP, invested funds in the project, administered DOE grants to DPA for 
    the project, and anticipates owning a portion of the NTP capacity 
    commensurate with its final pro rata investment in the project.
        The DPA proposal was developed in response to needs of the electric 
    industry and of the Navajo Nation. These include the following:
         Relieve the constraints on the transmission of electricity 
    west of the Four Corners area.
         Improve the operational flexibility and reliability of the 
    extra-high-voltage transmission system in the region.
         Allow increased economical power transfers, sales, and 
    purchases in the region.
         Improve economic conditions of the Navajo Nation.
         Facilitate the development of Navajo Nation energy 
    resources and its participation in the electrical utility industry.
        Western agreed to assist DPA in this endeavor by participating as 
    the lead Federal agency for the preparation of the EIS. Federal 
    involvement was provided because of the need to acquire rights-of-way 
    across public lands, construction of the project could benefit Western 
    and Western's customers, and because DOE supports the development of 
    Native American energy programs pursuant to
    
    [[Page 58967]]
    
    Title XXVI of the Energy Policy Act of 1992.
    
    Development of Alternatives
    
        The development of alternatives for the NTP EIS first focused on 
    alternatives to the project proposed by DPA that might meet their 
    needs. Six alternatives were developed: (1) achieve results through 
    energy conservation and electric load management, (2) construct new 
    generation facilities, (3) utilize the existing transmission system, 
    (4) utilize alternative transmission technologies (different voltages, 
    direct current versus alternating current, underground construction, 
    and the use of new technologies), (5) no action, and (6) construct a 
    new transmission line. The first four alternatives (1, 2, 3, and 4) 
    were analyzed and found not to be responsive to the purpose and need 
    for the project. While these would achieve some of the needs addressed 
    by the proposal, none would satisfy all of them. Western then conducted 
    a detailed analysis of the no action alternative and the proposed 
    action alternative, which is to construct, operate, and maintain the 
    transmission line. Western found that the no action alternative would 
    not meet the needs addressed by the proposal.
        For the proposed action alternative, several general alternative 
    corridors (approximately 1,800 miles) were identified through a 
    regional environmental feasibility study (June 1992) and introduced to 
    agencies and the public during the scoping process for the EIS. This 
    regional feasibility study evaluated the most reasonable means of 
    placing a right-of-way corridor from proposed starting point to end 
    point. It was assumed that to reduce impacts to all resources and 
    issues associated with transmission line construction, paralleling an 
    existing utility corridor was preferable. Therefore, the majority of 
    routes explored in the environmental feasibility study paralleled other 
    power lines, fiber optic cables and buried pipelines wherever possible.
        Scoping and public outreach employed on this project were 
    extensive. A Notice of Intent to prepare an EIS was published in the 
    Federal Register on July 13, 1993, that announced the intent to conduct 
    public meetings. A total of 17 meetings were held in the project area, 
    in addition to several letters, fact sheets, media releases and notices 
    posted on and off the Navajo Nation. These resulted in public input 
    that led to the development of five issues of concern, which were 
    addressed in the Draft EIS: (1) need for the project, (2) benefits of 
    the project, (3) siting issues, (4) rights-of-way issues, and (5) 
    health and safety issues.
        Also, a non-environmental factor, the cost to construct, was 
    tracked throughout the analysis to make sure that the environmental 
    analysis was not leading to a solution that could not be accomplished. 
    While this was not the deciding factor, the cost of constructing the 
    project was monitored over the 4 years it has taken to reach a decision 
    on the project and was considered in the determination of the final 
    preferred alternative.
        Through scoping, some alternative routes were eliminated and some 
    were added, resulting in approximately 2,200 miles of alternative 
    routes studied in detail for the EIS. The alternative routes were then 
    systematically analyzed considering human, natural, and cultural 
    environmental factors including, but not limited to, land use, 
    socioeconomics, visual/aesthetics issues, human and animal health and 
    safety, air and water quality issues, soil erodibility, and 
    paleontological, biological and cultural resources. This analysis 
    resulted in narrowing the number of alternative routes addressed in the 
    EIS.
    
    Description of Alternatives Evaluated in Detail
    
        Once the scoping process was completed, resource inventories were 
    conducted for each of the alternative routes to establish the baseline 
    information from which to evaluate potential impacts. As inventory 
    information was collected, a process was begun to sort this information 
    and make decisions about further information needs. The 
    interdisciplinary teams ranked the potential impacts for each 
    alternative route in terms of the resources that might be impacted, the 
    likely mitigation measures that would be required, and the residual 
    impacts remaining after mitigation. The team then made decisions to 
    eliminate routes with high potential for impacts. The results were then 
    presented to the public during a set of 20 meetings held throughout the 
    project area to obtain comments prior to preparing the Draft EIS.
        The alternative routes finally addressed in the Draft EIS included 
    four alternative routes in the eastern portion of the project area and 
    six alternative routes in the western portion. The project area seemed 
    naturally to split into halves, with different concerns and issues in 
    the eastern portion than in the western portion. In the east, of major 
    concern were those residual impacts associated with Navajo and Hopi 
    traditional cultural places, and to a lesser degree, impacts to land 
    use patterns, which is also related to traditional land uses. In the 
    west, concerns centered around Hualapai traditional cultural places and 
    land use, as well as visual impacts and impacts to historic resources.
        These alternative routes were chosen for detailed analysis since 
    they had minimal resource impacts. Impacts on visual resources could be 
    mitigated to some degree. Other impacts are associated with Navajo and 
    Hopi traditional cultural places in the Marsh Pass/Northern Black Mesa 
    area, and to Hualapai traditional cultural places in the western 
    portion of the project area. Because of the sensitivity of these 
    resources, specific locations of these resources were not known. Zones 
    of potential impacts were very general. The direct impacts associated 
    with the environmentally preferred alternatives on specific resource 
    locations, when known, can be lessened once engineering on a final 
    route is completed.
        The interdisciplinary team selected a single route in each half of 
    the project area that avoided to the greatest degree possible impacts 
    on these resources. The eastern alternative presented as the 
    environmentally preferred alternative, the Kaibito 1 (K1) route, had 
    the least amount of potential impacts on visual resources and Navajo 
    and Hopi traditional cultural places. However, some impacts would 
    result along a short segment of the proposed route in areas of new 
    corridor (no existing transmission line) near Red Mesa, Black Mesa, 
    Marsh Pass, and across the Kaibito Plateau. The Northern 1 West (N1W) 
    route was chosen as the preferred alternative in the western half of 
    the project area. Because of an issue associated with where the 
    proposed line would cross the Colorado River, a termination at 
    Marketplace was determined to be the least damaging. Therefore, this 
    alternative would have no potential for significant impacts on 
    resources.
    
    Decision Process
    
        Following the release of the Draft EIS in early October 1996, 44 
    public hearings were held throughout the project area, which included 
    hearings held at each of the 36 Navajo chapters crossed by the 
    alternative routes. Each of these hearings was preceded by public 
    information meetings, where information on the project was presented 
    and questions and comments by the public could be addressed. In 
    addition, 13 written comments were submitted by the public, and 20 
    letters from the public and other agencies were
    
    [[Page 58968]]
    
    received. This information was summarized and addressed in the Final 
    EIS, released to the public on August 8, 1997.
        The verbal comments could be summarized into six issues of concern, 
    expressed mainly but not exclusively by residents of the Navajo Nation. 
    These were: (1) concerns over the distribution of project revenues to 
    Navajo chapters, (2) concerns about extending the local electrical 
    distribution system, (3) concerns for health and safety, (4) concerns 
    over involving the public in the project status, (5) concerns over the 
    acquisition of rights-of-way, and (6) concerns for employment 
    opportunities. In addition, a few comments identified other issues.
        Each of the concerns expressed orally or in writing was addressed 
    in the Final EIS, by providing a reference to a previous discussion in 
    the Draft EIS, by expanding on those previous discussions in the Final, 
    and/or by providing new information. A standard answer was provided to 
    each of the six issues discussed above, rather than respond 
    individually to multiple questions on the same issues. Only one minor 
    modification to the environmentally preferred alternative in the 
    eastern half of the project area was presented in the Final EIS. This 
    was in response to concerns expressed by the public during and 
    immediately following the public meetings. Local land users in the 
    Dennehotso, Arizona area expressed concerns over the preferred 
    alternative passing through areas of dispersed but common use, though 
    the alternative would not impact any residences directly. The route of 
    the alternative was modified slightly to satisfy these concerns.
    
    The Decision
    
        Western has decided that should the NTP be built, it should follow 
    the preferred alternative described in the NTP Final EIS. The project 
    would satisfy the needs identified in the EIS: it would relieve the 
    constraints on the transmission of electricity out of the region; it 
    would improve the flexibility and reliability of the existing system; 
    it would allow the economical transfer, sales, and purchases of power 
    in the region; and it would provide an opportunity for the Navajo 
    Nation to improve economic conditions. Based upon the information 
    gathered throughout the EIS process, Western provided the public and 
    the decisionmaker with complete information on the environmental 
    impacts associated with the project. Western analyzed several 
    alternatives to the proposed action in terms of their ability to 
    satisfy the identified needs. Western then analyzed many routing 
    alternatives in order to arrive at the least environmentally damaging 
    alternative routes.
        The following factors were taken into account in arriving at the 
    preferred alternative: (1) environmental acceptability, (2) siting and 
    permitting requirements that vary by land status (i.e., Federal, state, 
    tribal, and local), (3) public and agency preferences, especially those 
    of the Cooperating Agencies, (4) electrical system considerations such 
    as power flow and the impacts on system interconnections, (5) 
    engineering factors leading to an increase in costs, such as the length 
    of route, construction difficulty, accessibility, extent of mitigation 
    required, and the extent of design modifications needed for mitigation, 
    (6) rights-of-way acquisition considerations, and (7) consideration of 
    the statutory obligations of the permitting agencies.
        In making this decision, Western believes that all practicable 
    means to avoid or minimize significant impacts have been presented in 
    the NTP EIS in the form of standard and specific mitigation measures.
        The Kaibab National Forest; Bureau of Indian Affairs, Navajo and 
    Phoenix Area Offices; Bureau of Land Management, Arizona State Office 
    (representing the state BLM offices in Arizona, Nevada, and New 
    Mexico); and the National Park Service, Colorado Plateau Systems 
    Support Office, participated in the NTP EIS as Cooperating Agencies. In 
    addition to the Federal agencies, the Hopi Tribe, Hualapai Tribe, and 
    the Navajo Nation participated as Cooperating Agencies. These agencies 
    and tribes have decisions to make concerning the granting of rights-of-
    way for the alignment described in the EIS, provided a Construction, 
    Operation, and Maintenance Plan for the construction of the NTP, 
    including a plan for all necessary environmental mitigation, is 
    prepared and agreed upon by all parties.
    
    Mitigation Action Plan
    
        The Final EIS presents reasonable and practicable mitigation 
    measures to reduce the severity of the impacts associated with 
    construction of the line. The preferred action, given the analysis 
    process and the proposed mitigation, will not have a significant impact 
    on environmental factors, with the exception of the potential for 
    impacts on visual resources and Hopi, Hualapai, and Navajo traditional 
    cultural places as discussed above. Western will issue a Mitigation 
    Action Plan (MAP), as required by DOE NEPA implementing procedures 
    found at 10 CFR Sec. 1021.331, at a later date. The MAP will detail the 
    mitigation and monitoring required to reduce impacts to less than 
    significant. Western's final decision is contingent upon the 
    construction of the line consistent with the requirements of the MAP, 
    and acceptance of the MAP by the Cooperating Agencies.
    
        Dated: October 23, 1997.
    Michael S. Hacskaylo,
    Acting Administrator.
    [FR Doc. 97-28910 Filed 10-30-97; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Effective Date:
10/31/1997
Published:
10/31/1997
Department:
Western Area Power Administration
Entry Type:
Notice
Action:
Record of Decision.
Document Number:
97-28910
Dates:
This decision will become effective October 31, 1997.
Pages:
58966-58968 (3 pages)
PDF File:
97-28910.pdf