E6-16419. Defense Federal Acquisition Regulation Supplement; Congressional Notification of Architect-Engineer Services/Military Family Housing Contracts (DFARS Case 2006-D015)
-
Start Preamble
AGENCY:
Defense Acquisition Regulations System, Department of Defense (DoD).
ACTION:
Interim rule with request for comments.
SUMMARY:
DoD has issued an interim rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to implement Section 1031(a)(37) of the National Defense Authorization Act for Fiscal Year 2004. Section 1031(a)(37) amended the requirements for submission of a notification to Congress before the award of a contract for architectural and engineering services or construction design in connection with military construction, military family housing, or restoration or replacement of damaged or destroyed facilities.
DATES:
Effective date: October 4, 2006.
Comment date: Comments on the interim rule should be submitted in writing to the address shown below on or before December 4, 2006, to be considered in the formation of the final rule.
ADDRESSES:
You may submit comments, identified by DFARS Case 2006-D015, using any of the following methods:
- Federal eRulemaking Portal: http://www.regulations.gov. Follow the instructions for submitting comments.
- E-mail: dfars@osd.mil. Include DFARS Case 2006-D015 in the subject line of the message.
- Fax: (703) 602-0350.
- Mail: Defense Acquisition Regulations System, Attn: Ms. Debra Overstreet, OUSD(AT&L)DPAP(DARS), IMD 3C132, 3062 Defense Pentagon, Washington, DC 20301-3062.
- Hand Delivery/Courier: Defense Acquisition Regulations System, Crystal Square 4, Suite 200A, 241 18th Street, Arlington, VA 22202-3402.
Comments received generally will be posted without change to http://www.regulations.gov, including any personal information provided.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Ms. Debra Overstreet, (703) 602-0310.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
A. Background
This interim rule revises DFARS 236.601 to implement Section 1031(a)(37) of the National Defense Authorization Act for Fiscal Year 2004 (Public Law 108-136). Section 1031(a)(37) amended the requirements at 10 U.S.C. 2807, for submission of a notification to Congress before the award of a contract for architectural and engineering services or construction design in connection with military construction, military family housing, or restoration or replacement of damaged or destroyed facilities. The amendments increased the contract dollar threshold for submission from $500,000 to $1,000,000; and reduced the time period for submission, from 21 to 14 days before obligation of funds, when the notification is provided in electronic medium.
This rule was not subject to Office of Management and Budget review under Executive Order 12866, dated September 30, 1993.
B. Regulatory Flexibility Act
DoD does not expect this rule to have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because the rule relates to reporting requirements that are internal to the Government. Therefore, DoD has not performed an initial regulatory flexibility analysis. DoD invites comments from small businesses and other interested parties. DoD also will consider comments from small entities concerning the affected DFARS subpart in accordance with 5 U.S.C. 610. Such comments should be submitted Start Printed Page 58541separately and should cite DFARS Case 2006-D015.
C. Paperwork Reduction Act
The Paperwork Reduction Act does not apply, because the rule does not impose any information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq.
D. Determination to Issue an Interim Rule
A determination has been made under the authority of the Secretary of Defense that urgent and compelling reasons exist to publish an interim rule prior to affording the public an opportunity to comment. This interim rule implements Section 1031(a)(37) of the National Defense Authorization Act for Fiscal Year 2004 (Public Law 108-136). Section 1031(a)(37) amended the statutory requirements for submission of a notification to Congress before the award of a contract for architectural and engineering services or construction design in connection with military construction, military family housing, or restoration or replacement of damaged or destroyed facilities. Comments received in response to this interim rule will be considered in the formation of the final rule.
Start List of SubjectsList of Subjects in 48 CFR Part 236
- Government procurement
Michele P. Peterson,
Editor, Defense Acquisition Regulations System.
Therefore, 48 CFR Part 236 is amended as follows:
End Amendment Part Start PartPART 236—CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS
End Part Start Amendment Part1. The authority citation for 48 CFR Part 236 continues to read as follows:
End Amendment Part Start Amendment Part2. Section 236.601 is revised to read as follows:
End Amendment PartPolicy(1) Written notification to the congressional defense committees is required if the total estimated contract price for architect-engineer services or construction design, in connection with military construction, military family housing, or restoration or replacement of damaged or destroyed facilities, exceeds $1,000,000. In accordance with 10 U.S.C. 480, unclassified notifications must be provided by electronic medium.
(i) For military construction or military family housing (10 U.S.C. 2807(b)), the notification—
(A) Must include the scope of the project and the estimated contract price; and
(B) (1) If provided by electronic medium, must be provided at least 14 days before the initial obligation of funds; or
(2) If provided by other than electronic medium, must be received by the congressional defense committees at least 21 days before the initial obligation of funds.
(ii) For restoration or replacement of damaged or destroyed facilities (10 U.S.C. 2854(b)), the notification—
(A) Must include the justification for the project, the estimated contract price, and the source of the funds for the project; and
(B) (1) If provided by electronic medium, must be provided at least 7 days before the initial obligation of funds; or
(2) If provided by other than electronic medium, must be received by the congressional defense committees at least 21 days before the initial obligation of funds.
(2) During the applicable notice period, synopsis of the proposed contract action and administrative actions leading to the award may be started.
[FR Doc. E6-16419 Filed 10-3-06; 8:45 am]
BILLING CODE 5001-08-P
Document Information
- Comments Received:
- 0 Comments
- Published:
- 10/04/2006
- Department:
- Defense Acquisition Regulations System
- Entry Type:
- Rule
- Action:
- Interim rule with request for comments.
- Document Number:
- E6-16419
- Pages:
- 58540-58541 (2 pages)
- RINs:
- 0750-AF41
- Topics:
- Government procurement
- PDF File:
- e6-16419.pdf
- CFR: (1)
- 48 CFR 236.601