99-26028. Sam Rayburn Dam Project Power Rate  

  • [Federal Register Volume 64, Number 193 (Wednesday, October 6, 1999)]
    [Notices]
    [Pages 54293-54295]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-26028]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Southwestern Power Administration
    
    
    Sam Rayburn Dam Project Power Rate
    
    AGENCY: Southwestern Power Administration, DOE.
    
    ACTION: Notice of power rate extension.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Secretary of Energy, acting under the authorities as 
    implemented in 10 CFR 903.22(h) and 903.23(a)(3), has approved and 
    placed into effect on an interim basis Rate Order No. SWPA-40.
    
    SUPPLEMENTARY INFORMATION: Southwestern Power Administration 
    (Southwestern) currently markets 2.2 million kilowatts of power from 24 
    multiple-purpose reservoir projects, in all or portions of the states 
    of Arkansas, Kansas, Louisiana, Missouri, Oklahoma and Texas, with 
    power facilities constructed and operated by the U.S. Army Corps of 
    Engineers. The Integrated System, comprised of 22 of the projects, is 
    interconnected through a transmission system presently consisting of 
    138-kV and 161-kV high-voltage transmission lines, 69-kV transmission 
    lines, and numerous bulk power substations and switching stations. In 
    addition, contractual transmission arrangements provide for integration 
    of other projects into the system.
        The remaining two projects, Sam Rayburn Dam and Robert Douglas 
    Willis, are isolated hydraulically and electrically from the 
    Southwestern transmission system, and their power is marketed under 
    separate contracts through which the customer purchases
    
    [[Page 54294]]
    
    the entire power output of the project at the dam. A separate Power 
    Repayment Study (PRS) is prepared for each isolated project.
        The existing rate schedule for the Sam Rayburn Dam Project was 
    confirmed and approved on a final basis by the Federal Energy 
    Regulatory Commission (FERC) on December 7, 1994, for the period 
    October 1, 1994, through September 30, 1998. The Deputy Secretary of 
    Energy extended the existing rate schedule for a one year period, 
    through September 30, 1999. The FY 1999 Sam Rayburn Dam Project PRS 
    indicates the need for a rate adjustment of $4,692 annually, or 0.2 
    percent.
        Pursuant to implementing authority in 10 CFR 903.22(h) and 
    903.23(a)(3), the Secretary of Energy may extend a FERC-approved rate 
    on an interim basis. The Southwestern Administrator, published notice 
    in the Federal Register on June 29, 1999, 64 FR 34797, announcing a 30-
    day period for public review and comment concerning the proposed 
    interim rate extension. Written comments were accepted through July 29, 
    1999. In a letter dated July 27, 1999, a Sam Rayburn Dam Electric 
    Cooperative (SRDEC) official stated that SRDEC has no objection to the 
    proposed rate extension. No other comments were received.
    
    Discussion
    
        The existing Sam Rayburn Dam Project rate is based on the FY 1994 
    PRS. PRSs have been completed on the Sam Rayburn Dam Project each year 
    since approval of the existing rates. Rate changes identified by the 
    PRSs since that period have indicated the need for minimal rate 
    increases or decreases. Since the revenue changes reflected by the PRSs 
    were within the plus-or-minus two percent Rate Adjustment Threshold 
    established by Southwestern's Administrator on June 23, 1987, these 
    rate adjustments were deferred in the best interest of the government 
    and provided for the next year's PRS to determine the appropriate level 
    of revenues needed for the next rate period.
        The FY 1999 PRS indicates the need for an annual revenue increase 
    of 0.2 percent. As has been the case since the existing rate was 
    approved, the FY 1999 rate adjustment falls within Southwestern's plus-
    or-minus two percent Rate Adjustment Threshold and would normally be 
    deferred. However, the existing rate expires on September 30, 1999. 
    Consequently, Southwestern proposes to extend the existing rate for a 
    one-year period ending September 30, 2000, on an interim basis under 
    the implementation authorities noted in 10 CFR 903.22(h) and 
    903.23(a)(3).
        Southwestern continues to make significant progress toward 
    repayment of the Federal investment in the Sam Rayburn Dam Project. 
    Through FY 1998, cumulative amortization for the Sam Rayburn Dam 
    Project was $12,339,699, which represents approximately 48 percent of 
    the $25,734,878 Federal investment. Repayment has increased almost 34 
    percent since the existing rate was placed in effect.
        Information regarding this rate extension, including studies and 
    other supporting material, is available for public review and comment 
    in the offices of Southwestern Power Administration, Suite 1400, One 
    West Third Street, Tulsa, Oklahoma 74103.
    
    Order
    
        In view of the foregoing and pursuant to the authorities granted in 
    10 CFR 903.22(h) and 903.23(a)(3), I hereby extend on an interim basis, 
    for the period of one year, effective October 1, 1999, the current 
    FERC-approved Sam Rayburn Dam Project rate for the sale of power and 
    energy.
    
        Dated: September 15, 1999.
    Bill Richardson,
    Secretary.
    
    [Rate Order No. SWPA-40]
    
    Order Approving Extension of Power Rate on an Interim Basis
    
    October 1, 1999.
        In the matter of: Southwestern Power Administration--Sam Rayburn 
    Dam Project Rate .
    
        Pursuant to Sections 302(a) and 301(b) of the Department of Energy 
    Organization Act, Pub. L. 95-91, the functions of the Secretary of the 
    Interior and the Federal Power Commission under Section 5 of the Flood 
    Control Act of 1944, 16 U.S.C. 825s, for the Southwestern Power 
    Administration (Southwestern) were transferred to and vested in the 
    Secretary of Energy. By Delegation Order No. 0204-108, effective 
    December 14, 1983, 48 FR 55664, the Secretary of Energy delegated to 
    the Deputy Secretary of Energy on a non-exclusive basis the authority 
    to confirm, approve and place into effect on an interim basis power and 
    transmission rates, and delegated to the Federal Energy Regulatory 
    Commission (FERC) on an exclusive basis the authority to confirm, 
    approve and place in effect on a final basis, or to disapprove power 
    and transmission rates. Amendment No. 1 to Delegation Order No. 0204-
    108, effective May 30, 1986, 51 FR 19744, revised the delegation of 
    authority to confirm, approve and place into effect on an interim basis 
    power and transmission rates by delegating such authority to the Under 
    Secretary of Energy rather than the Deputy Secretary of Energy. This 
    delegation was reassigned to the Deputy Secretary of Energy by 
    Department of Energy (DOE) Notice 1110.29, dated October 27, 1988, and 
    clarified by Secretary of Energy Notice SEN-10-89, dated August 3, 
    1989, and subsequent revisions. By Amendment No. 2 to Delegation Order 
    No. 0204-108, effective August 23, 1991, 56 FR 41835, the Secretary of 
    the Department of Energy revised Delegation Order No. 0204-108 to 
    delegate to the Assistant Secretary, Conservation and Renewable Energy, 
    the authority which was previously delegated to the Deputy Secretary in 
    that Delegation Order. By Amendment No. 3 to Delegation Order No. 0204-
    108, effective November 10, 1993, the Secretary of Energy re-delegated 
    to the Deputy Secretary of Energy, the authority to confirm, approve 
    and place into effect on an interim basis power and transmission rates 
    of the Power Marketing Administrations. By notice dated April 15, 1999, 
    the Secretary of Energy rescinded the authority of the Deputy Secretary 
    of Energy under Delegation Order 0204-108. This rate order is issued by 
    the Secretary of Energy pursuant to Section 642 of the Department of 
    Energy Organization Act.
        This is an interim rate extension. It is made pursuant to the 
    authorities as implemented in 10 CFR 903.22(h) and 903.23(a)(3).
    
    Background
    
        Southwestern currently markets for 2.2 million kilowatts of power 
    from 24 multiple-purpose reservoir projects, in the states of Arkansas, 
    Kansas, Louisiana, Missouri, Oklahoma and Texas, with power facilities 
    constructed and operated by the U.S. Army Corps of Engineers. The 
    Integrated System, comprised of 22 of the projects, is interconnected 
    through a transmission system presently consisting of 138-kV and 161-kV 
    high-voltage transmission lines, 69-kV transmission lines, and numerous 
    bulk power substations and switching stations. In addition, contractual 
    transmission arrangements provide for integration of other projects 
    into the system.
        The remaining two projects, Sam Rayburn Dam and Robert Douglas 
    Willis, are isolated hydraulically and electrically from the 
    Southwestern transmission system, and their power is marketed under 
    separate contracts through which the customer purchases the entire 
    power output of the project at
    
    [[Page 54295]]
    
    the dam. A separate Power Repayment Study (PRS) is prepared for each 
    isolated project.
        The existing rate schedule for the Sam Rayburn Dam Project was 
    confirmed and approved on a final basis by the FERC on December 7, 
    1994, for the period October 1, 1994, through September 30, 1998. The 
    rate was extended on an interim basis by the Deputy Secretary of 
    Energy, who had authority at that time pursuant to Delegation Order 
    0204-108, for a one-year period, October 1, 1998, through September 30, 
    1999. The FY 1999 Sam Rayburn Dam Project PRS indicates the need for a 
    rate adjustment of $4,692 annually, or 0.2 percent.
        Pursuant to implementing authority in 10 CFR 903.22(h) and 
    903.23(a)(3), the Secretary of Energy may extend a FERC-approved rate 
    on an interim basis. The Southwestern Administrator, published notice 
    in the Federal Register on June 29, 1999, 64 FR 34797, announcing a 30-
    day period for public review and comment concerning the proposed 
    interim rate extension. In addition, an informal meeting was held with 
    customer representatives in April 1999. Written comments were accepted 
    through July 29, 1999. One comment was received. This comment stated no 
    objection to the proposed interim extension.
    
    Discussion
    
        The existing Sam Rayburn Dam Project rate is based on the FY 1994 
    PRS. PRSs have been completed on the Sam Rayburn Dam Project each year 
    since approval of the existing rates. Rate changes identified by the 
    PRSs since that period have indicated the need for minimal rate 
    increases or decreases. Since the revenue changes reflected by the PRSs 
    were within the plus-or-minus two percent Rate Adjustment Threshold 
    established by Southwestern's Administrator on June 23, 1987, these 
    rate adjustments were deferred in the best interest of the government 
    and provided for the next year's PRS to determine the appropriate level 
    of revenues needed for the next rate period.
        The FY 1999 PRS indicates the need for an annual revenue increase 
    of $4,692 (0.2 percent). As has been the case since the existing rate 
    was approved, the FY 1999 rate adjustment falls within Southwestern's 
    plus-or-minus two percent Rate Adjustment Threshold and would normally 
    be deferred. However, the existing rate expires on September 30, 1999. 
    Consequently, Southwestern proposes to extend the existing rate for a 
    one-year period ending September 30, 2000, on an interim basis under 
    the implementation authorities noted in 10 CFR 903.22(h) and 
    903.23(a)(3).
        Southwestern continues to make significant progress toward 
    repayment of the Federal investment in the Sam Rayburn Dam Project. 
    Through FY 1998, cumulative amortization for the Sam Rayburn Dam 
    Project was $12,339,699, which represents approximately 48 percent of 
    the $25,734,878 Federal investment for the Sam Rayburn Dam Project. The 
    cumulative amortization has increased almost 34 percent since the 
    existing rate was placed in effect.
        Information regarding this rate extension, including studies and 
    other supporting material, is available for public review and comment 
    in the offices of Southwestern Power Administration, One West Third 
    Street, Tulsa, Oklahoma 74101.
    
    Order
    
        In view of the foregoing and pursuant to the authority delegated to 
    me in 10 CFR part 903, I hereby extend on an interim basis, for the 
    period of one year, effective October 1, 1999, the current FERC-
    approved Sam Rayburn Dam Project rate for the sale of power.
    
        Dated: September 15, 1999.
    Bill Richardson,
    Secretary.
    [FR Doc. 99-26028 Filed 10-5-99; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Published:
10/06/1999
Department:
Southwestern Power Administration
Entry Type:
Notice
Action:
Notice of power rate extension.
Document Number:
99-26028
Pages:
54293-54295 (3 pages)
PDF File:
99-26028.pdf