96-25612. Colorado River StorageConfirming and Approving an Extension of the Firm Transmission Service Rate  

  • [Federal Register Volume 61, Number 195 (Monday, October 7, 1996)]
    [Notices]
    [Pages 52448-52449]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-25612]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Rate Order No. WAPA-73]
    
    
    Colorado River Storage--Confirming and Approving an Extension of 
    the Firm Transmission Service Rate
    
    AGENCY: Western Area Power Administration, DOE.
    
    ACTION: Notice of a rate order.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The purpose of Rate Order No. WAPA-73 is to extend Rate 
    Schedule SP-FT4 until September 30, 1997.
    
    FOR FURTHER INFORMATION CONTACT: Mr. David Sabo, CRSP Manager, CRSP 
    Customer Service Center, Western Area Power Administration, P.O. Box 
    11606, Salt Lake City, UT 84147-0606, (801) 524-5493.
    
    SUPPLEMENTARY INFORMATION: By Amendment No. 3 to Delegation Order No. 
    0204-108, published November 10, 1993 (58 FR 59716), the Secretary of 
    Energy redelegated (1) the authority to develop long-term power and 
    transmission rates on a nonexclusive basis to the Administrator of 
    Western; (2) the authority to confirm, approve, and place such rates 
    into effect on an interim basis to the Deputy Secretary; and (3) the 
    authority to confirm, approve, and place into effect on a final basis, 
    to remand, or to disapprove such rates to the Federal Energy Regulatory 
    Commission (FERC). Existing Department of Energy procedures for public 
    participation in power rate adjustments (10 CFR Part 903) became 
    effective on September 18, 1985 (50 FR 37835).
        Pursuant to Delegation Order No. 0204-108, Western's Colorado River 
    Storage Project (CRSP) firm transmission rate case was submitted to the 
    Federal Energy Regulatory Commission for confirmation and approval on 
    August 13, 1992. On February 18, 1993, in Docket Nos. EF92-5172-000 and 
    EF92-5172-001, at 62 FERC para. 61,159, FERC issued an order 
    confirming, approving, and placing in effect on a final basis Rate 
    Schedule SP-FT4 for firm transmission service over the CRSP 
    transmission system. The rate was approved for the 4-year period 
    beginning October 1, 1992, and ending September 30, 1996.
        Western proposes to extend the existing CRSP firm transmission rate 
    until September 30, 1997. During the last firm-power rate adjustment 
    for the Salt Lake Integrated Projects, placed into effect on December 
    1, 1994 (SLIP-F5), the CRSP firm transmission rate was examined. It was 
    determined that the existing firm transmission rate was still adequate 
    to meet revenue requirements. The costs associated with the Salt Lake 
    City Integrated Projects' firm power rate increase were offset in the 
    CRSP firm transmission rate study by an increase in transmission 
    revenues not associated with the firm transmission rate.
    
        Issued in Washington, D.C., September 27, 1996.
    Charles B. Curtis,
    Deputy Secretary.
    
    Order Confirming and Approving an Extension of the Colorado River 
    Storage Project Firm Transmission Rate
    
    October 1, 1996.
        These power rates were established pursuant to Section 302(a) of 
    the Department of Energy (DOE) Organization Act, 42 U.S.C. 7152(a), 
    through which the power marketing functions of the Secretary of the 
    Interior and the Bureau of Reclamation (Reclamation) under the 
    Reclamation Act of 1902, ch. 1093, 32 Stat. 388, as amended and 
    supplemented by subsequent enactments, particularly section 9(c) of the 
    Reclamation Project Act of 1939, 43 U.S.C. 485h(c), and other acts 
    specifically applicable to the project system involved, were 
    transferred to and vested in the Secretary of Energy (Secretary).
        By Amendment No. 3 to Delegation Order No. 0204-108, published 
    November 10, 1993 (58 FR 59716), the Secretary redelegated (1) the 
    authority to develop long-term power and transmission rates on a 
    nonexclusive basis to the Administrator of the Western Area Power 
    Administration (Western); (2) the authority to confirm, approve, and 
    place such rates into effect on an interim basis to the Deputy 
    Secretary; and (3) the authority to confirm, approve, and place into 
    effect on a final basis, to remand, or to disapprove such rates to the 
    Federal Energy Regulatory Commission (FERC). Existing DOE procedures 
    for public participation in power rate adjustments (10 CFR Part 903) 
    became effective on September 18, 1985 (50 FR 37835). This rate 
    extension is issued pursuant to the Delegation Order and the rate 
    extension procedures in 10 CFR Part 903.
    
    Background
    
        Pursuant to Delegation Order No. 0204-108, in the order issued 
    February 18, 1993, at 62 FERC para. 61,159, in Docket Nos. EF92-5172-
    000 and EF92-5172-001, the FERC confirmed, approved, and placed in 
    effect on a final basis Rate Schedule SP-FT4 for firm transmission 
    service over the Colorado River Storage Project (CRSP) transmission 
    system. The rate was approved for the period from October 1, 1992, 
    through September 30, 1996.
    
    Discussion
    
        On September 30, 1996, Western's CRSP firm transmission rate will 
    expire. This makes it necessary to extend the
    
    [[Page 52449]]
    
    current Rate Schedule SP-FT4 to comply with 10 CFR 903.23.
        Western proposes to extend the existing CRSP transmission rate 
    until September 30, 1997.
        During the last firm-power rate adjustment for the Salt Lake 
    Integrated Projects, placed into effect on December 1, 1994 (SLIP-F5), 
    the CRSP firm transmission rate was also examined for possible 
    adjustment. It was determined that the existing firm transmission rate 
    was adequate to meet revenue requirements. The CRSP costs associated 
    with the Salt Lake City Integrated Projects' firm power rate increase 
    were offset in the CRSP firm transmission rate study by an increase in 
    transmission revenues not associated with the firm transmission rate.
    
    Order
    
        In view of the foregoing and pursuant to the authority delegated to 
    me by the Secretary, I hereby confirm and approve for a period 
    effective October 1, 1996, until September 30, 1997, the existing Rate 
    Schedule SP-FT4 for firm transmission service over the Colorado River 
    Storage Project transmission system.
    
        Issued in Washington, D.C., September 27, 1996.
    Charles B. Curtis,
    Deputy Secretary.
    [FR Doc. 96-25612 Filed 10-4-96; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Published:
10/07/1996
Department:
Energy Department
Entry Type:
Notice
Action:
Notice of a rate order.
Document Number:
96-25612
Pages:
52448-52449 (2 pages)
Docket Numbers:
Rate Order No. WAPA-73
PDF File:
96-25612.pdf