2024-26075. Constellation Energy Generation LLC; Limerick Generating Station, Units 1 and 2; Exemption  

  • Exemption's Operational Constraints for a Period of 30-Days

    Maximum reactor thermal power Maximum number of SRVs out of service Manual initiation time for SLCS (minutes) Minimum suppression pool water level (feet) Additional system credited
    90% 0 5 23 Level 3 Recirculation Runback.
    87% 0 5 22 Level 3 Recirculation Runback.
    84% 1 5 22 Level 3 Recirculation Runback.