2024-26471. Mission Valley Power Project, Montana-Power Rate Adjustment  

  • Rate category Present rate Proposed 2024 rate Proposed 2025 rate Proposed 2026 rate
    Residential (See Note #1)
    Basic Charge per month * $17.50 $22.00 $23.50 $27.00
    Basic Charge (Pre-Pay Meters) * 21.00 26.40 28.20 32.40
    Basic Charge (Net Meters) * 20.00 27.00 28.50 32.00
    Energy Charge:
    Each kilowatt-hour between 0-1,000 * 0.0812 0.0828 0.0880 0.0901
    Each kilowatt-hour between 1,001-2,000 * 0.0908 0.0926 0.0983 0.1007
    Each kilowatt-hour over 2,000 * 0.1126 0.1148 0.1219 0.1249
    Demand charge per kilowatt * 0.25 0.40 0.60 0.80
    Small General Service (maximum monthly demand of 25 kilowatts or less) (See Note #1)
    Basic Charge per month * 17.50 22.00 23.50 27.00
    Basic Charge (Pre-Pay Meters) * 21.00 26.40 28.20 32.40
    Basic Charge (Net Meters) * 20.00 27.00 28.50 32.00
    Energy charge per kilowatt-hour * 0.1034 0.1046 0.1113 0.1136
    Demand charge per kilowatt * 0.30 0.50 0.75 1.00
    General Service (monthly demand of 26—1,000 kilowatts) (See Note #1)
    Basic charge per month:
    Single Phase * 32.50 40.75 43.50 50.00
    Single Phase (Net Meters) * 37.50 45.75 48.50 55.00
    Three Phase * 53.25 66.75 71.25 81.92
    Three Phase (Net Meters) * 61.50 75.00 79.50 90.17
    Energy Charge per kilowatt-hour * 0.0753 0.0761 0.0797 0.0797
    Demand Charge per kilowatt * ^ 4.50 5.00 5.25 5.75
    New Large Single Load (monthly demand over one megawatt) (See Note #2)
    Basic Charge per month 45.00 45.00 45.00 45.00
    Energy Charge:
    Each kilowatt-hour between 0-730,000 0.0753 0.0753 0.0753 0.0753
    Each kilowatt-hour over 730,000 0.06395 0.06395 0.06395 0.06395
    Demand charge ^ Per kilowatt up to 1,000 Per kilowatt over 1,000 4.50 4.10 4.50 4.10 4.50 4.10 4.50 4.10
    Area Lights
    LED Light * 10.05 12.57 13.43 15.43
    ( print page 90035)
    Unmetered Services (See Note #3)
    Basic Charge * 17.50 22.00 23.50 27.00
    Street Lighting (Metered)
    Basic Charge * 10.00 12.57 13.43 15.43
    Energy Charge * 0.1034 0.1046 0.1113 0.1136
    Street Lighting (Unmetered)
    LED Light * 7.20 8.50 9.10 9.55
    Irrigation (See Note #4)
    Basic charge per month * 5.00 10.00 15.00 20.00
    Energy charge per kilowatt hour * 0.0712 0.0719 0.0720 0.0746
    Demand Charge per kilowatt * ‸ 3.00 4.00 5.25 5.75
    * Notes rate categories proposed for adjustment.
    ^ We may apply a power factor penalty to Irrigation, General Service—Three Phase, and New Large Single Load customers.
    Note #1. Residential and Small General Service customers may opt into the “Pre-Pay Meters” or “Net Meters” programs. General Service customers may opt into the “Net Meters” program. For the Pre-Pay Meters program, customers must pre-pay a minimum of $50.00 fee at time of account setup. Any prepayment is credited to the account and applied to the customer's future usage and demand charges. Pre-Pay customers are required to keep a positive balance in their account, or the meter will shut off automatically. Net Metering allows customer-owned renewable generation to interconnect with MVP's distribution system.
    Note #2. Customers with monthly demand of over three megawatts will be subject to other rates, as determined by MVP on a case-by case basis, and may be required to make a deposit of two months of estimated service.
    Note #3. Unmetered Services refers to customers, using kilowatt hours without a meter, that do not fall under one of MVP's other rate categories. Includes traffic lights, billboards, and telephone booths.
    Note #4. Irrigation customers may receive a Bonneville Power Administration (BPA) discount for the months of May through September. BPA generally provides an irrigation discount to assist the agricultural sector in rural Northwest communities. After BPA provides MVP with the final irrigation discount rate, we will issue the discount as an annual credit on qualified irrigation customers' bills.

Document Information

Published:
11/14/2024
Department:
Indian Affairs Bureau
Entry Type:
Notice
Action:
Notice of proposed rate adjustment.
Document Number:
2024-26471
Dates:
Interested parties may submit comments on the proposed rate adjustments on or before December 16, 2024.
Pages:
90032-90036 (5 pages)
Docket Numbers:
245A2100DD/AAKC001030/A0A501010.999900
PDF File: