E9-27527. Indiana Michigan Power Company; Donald C. Cook Nuclear Plant, Unit 1; Exemption  

  • Start Preamble

    1.0 Background

    The Indiana Michigan Power Company (the licensee) is the holder of Facility Operating License Nos. DPR-58, which authorizes operation of the Donald C. Cook Nuclear Plant, Unit 1 (CNP-1). The license provides, among other things, that the facility is subject to all rules, regulations, and orders of the Nuclear Regulatory Commission (NRC, the Commission) now or hereafter in effect.

    The facility consists of two pressurized-water reactors located in Berrien County in Michigan.

    2.0 Request/Action

    Title 10 of the Code of Federal Regulations (10 CFR), part 26, section 205(d)(4) [10 CFR 26.205(d)(4)] provides that during the first 60 days of a unit outage, licensees need not meet the requirements of 10 CFR 26.205(d)(3) for individuals specified in 10 CFR 26.4(a)(1) through 10 CFR 26.4(a)(4), while those individuals are working on outage activities. However, 10 CFR 26.205(d)(4) also provides that the licensee shall ensure that the individuals specified in 10 CFR 26.4(a)(1) through (a)(3) have at least 3 days off in each successive (i.e., non-rolling) 15-day period and that the individuals specified in 10 CFR 26.4(a)(4) have at least 1 day off in any 7-day period.

    The less restrictive requirements of 10 CFR 26.205(d)(4) would be applied following a period of normal plant operation in which the workload and overtime levels are controlled by 10 CFR 26.205(d)(3). As stated in 10 CFR 26.205(d)(4), the less restrictive work hour requirements are permitted during the first 60 days of a unit outage. Since the current CNP-1 extended outage commenced in September 2008, the first 60 days of the unit outage have already elapsed.

    The licensee adopted the regulations of 10 CFR 26, subpart I, on October 1, 2009, and has been controlling work hours accordingly. The proposed scheduler exemption would allow the less restrictive working hours of 10 CFR 26.205(d)(4) during a 60-day period beginning within three days of issuance of the exemption, rather than during the first 60 days of the current unit outage (which commenced in September 2008). The exemption would include those operations and maintenance personnel required to support outage-related activities, including preparations for unit restart. The licensee would ensure that the affected individuals in these departments would not work excessive overtime during the period immediately preceding the application of 10 CFR 26.205(d)(4).

    The exemption would continue to serve the underlying purpose of 10 CFR 26, subpart I, in that assurance would be provided such that cumulative fatigue of individuals to safely and competently perform their duties will not be compromised.

    3.0 Discussion

    Pursuant to 10 CFR 26.9, the Commission may, upon application by any interested person or upon its own initiative, grant exemptions from the requirements of 10 CFR part 26 when (1) the exemptions are authorized by law, will not present an undue risk to public health or safety, are consistent with the common defense and security, and are otherwise in the public interest.

    Authorized by Law

    This scheduler exemption would allow the licensee to use the less restrictive working hour limitations provided in 10 CFR 26.205(d)(4) during a 60 day period beginning within three days of issuance of the exemption. Because CNP-1 was already in an extended outage during the implementation of 10 CFR part 26, Subpart I, the licensee has not been able to apply the less restrictive working hours provided for in 10 CFR 26.205(d)(4). This scheduler exemption would merely place CNP-1 in a similar position as licensees with outages that commenced after implementing Subpart I. As stated above, 10 CFR 26.9 allows the NRC to grant exemptions from the requirements of 10 CFR Part 26. The NRC staff has determined that granting of the licensee's proposed exemption will not result in a violation of the Atomic Energy Act of 1954, as amended, or the Commission's regulations. Therefore, the exemption is authorized by law.

    No Undue Risk to Public Health and Safety

    The underlying purpose of 10 CFR 26.205(d)(4) is to provide licensees flexibility in scheduling required days off while accommodating the more intense work schedules associated with a unit outage, while assuring that cumulative fatigue does not compromise the abilities of individuals to safely and competently perform their duties. Therefore, no new accident precursors are created by invoking the less restrictive work hour limitations on a date commensurate with the start of those activities supporting the restart of CNP-1, provided that the licensee has effectively managed fatigue for the affected individuals prior to this date. Thus, the probability of postulated accidents is not increased. Also, based on the above, the consequences of postulated accidents are not increased. Therefore, there is no undue risk to public health and safety.

    Consistent With Common Defense and Security

    The proposed scheduler exemption would allow for the use of the less restrictive work hour requirements of 10 CFR 26.205(d)(4) for operations and maintenance personnel to support restart activities for CNP-1, which has been in an extended outage since September 20, 2008. This change to the operation of the plant has no relation to security issues. Therefore, the common defense and security is not impacted by this exemption.

    Consistent With the Public Interest

    The proposed scheduler exemption would allow the licensee to implement the less restrictive work hour requirements of 10 CFR 26.205(d)(4) to allow flexibility in scheduling required days off while accommodating the more intensive work schedules that accompany a unit outage. During the CNP-1 restart period, the workload for operations and maintenance personnel will undergo a temporary but significant increase due to filling, venting, flushing, calibration, and testing evolutions necessitated by the repairs to the secondary and electrical generation systems and components. These evolutions are in addition to the normal unit startup activities involving operation and surveillance testing of primary systems and components. Ensuring a sufficient number of qualified personnel are available to support these activities is in the interest of overall public health and safety. Therefore, this scheduler exemption is consistent with the public interest.Start Printed Page 59270

    4.0 Conclusion

    Accordingly, the Commission has determined that, pursuant to 10 CFR 26.9, the exemption is authorized by law, will not endanger life or property nor present an undue risk to the public health and safety, is consistent with the common defense and security, and is otherwise in the public interest. Therefore, the Commission hereby grants Indiana Michigan Power Company an exemption from the requirements of 10 CFR 26.205(d)(4) for the Donald C. Cook Nuclear Plant, Unit 1.

    Pursuant to 10 CFR 51.32, the Commission has determined that the granting of this exemption will not have a significant effect on the quality of the human environment (74 FR 58063).

    This exemption is effective upon issuance, and implementation of the work hour limitations as specified in 10 CFR 26.205(d)(4) for CNP-1 operations and maintenance personnel working on outage activities associated with unit restart will commence no later than November 13, 2009. The licensee may implement the work hour provisions of 10 CFR 26.205(d)(4) for 60 days or until completion of the current CNP-1 forced outage, whichever is shorter. The licensee may implement the provisions of 10 CFR 26.205(d)(6), if applicable.

    Start Signature

    Dated at Rockville, Maryland, this 10th day of November 2009.

    For the Nuclear Regulatory Commission.

    Joseph G. Giitter,

    Director, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.

    End Signature End Preamble

    [FR Doc. E9-27527 Filed 11-16-09; 8:45 am]

    BILLING CODE 7590-01-P

Document Information

Comments Received:
0 Comments
Published:
11/17/2009
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
E9-27527
Pages:
59269-59270 (2 pages)
Docket Numbers:
NRC-2009-0503l, Docket No. 50-315
PDF File:
e9-27527.pdf