Table 1—Summary of Proposed Changes
CFR § Proposed provision 77.1 Establishes the requirement that all conditions and limitations in the determination are mandatory, including the requirement to mark newly constructed or altered meteorological towers with the highest point of the structure at least 50 feet AGL up to and including 200 feet AGL at its site. 77.3 Add definitions for “airborne wind energy system (AWES),” “meteorological tower,” “sponsor,” and “wind energy system.” 77.5 A sponsor of a meteorological tower in existence before the effective date of a final rule must provide notice consistent with § 77.7(d). A sponsor proposing any construction or alteration of a meteorological tower with the highest point of the structure at least 50 feet up to and including 200 feet AGL at its site must provide adequate notice to the FAA of that construction or alteration pursuant to § 77.7(b). 77.7 Require a sponsor to file notice at least 45 days before the start of construction or alteration or the date of application for a construction permit for any new meteorological tower, whichever is earlier. A sponsor must submit FAA Form 7460-1 for any proposed construction or alteration of a permanent wind energy system and associated meteorological towers at least 90 days before the start date of the proposed construction or alteration, or the date an application for a construction permit is filed, whichever is earlier. A sponsor of a meteorological tower that exists prior to the effective date of a final rule with the highest point of the structure at least 50 feet AGL up to and including 200 feet AGL at its site must submit FAA Form 7460-1 within 90 days of the effective date of a final rule. 77.9 A sponsor must file notice of any construction or alteration of a meteorological tower with the highest point of the structure at least 50 feet AGL up to and including 200 feet AGL at its site. ( print page 90629) If a sponsor has an existing meteorological tower with the highest point of the structure at least 50 feet AGL up to and including 200 feet AGL at its site prior to the effective date of a final rule, the sponsor must file notice consistent with § 77.7(d). 77.10 Makes clear that a sponsor must file supplemental notice if otherwise requested by the FAA. 77.11 If the FAA requests additional information during any part of the aeronautical study process, pre- or post-any determination, the sponsor must provide that information within 30 days. 77.12 Except for structures that have received an FAA Determination of No Hazard to Air Navigation prior to the effective date of a final rule or any meteorological tower with the highest point of the structure at least 50 feet AGL up to and including 200 feet AGL at its site for which construction is complete prior to the effective date of a final rule, sponsors must comply with the conditions and limitations contained in a Determination of No Hazard to Air Navigation. This includes requiring newly constructed or altered meteorological towers with the highest point of the structure at least 50 feet AGL up to and including 200 feet AGL at its site to mark the tower. 77.27 The FAA will conduct an aeronautical study when: (1) notice required under § 77.9 has been received, or (2) the FAA determines a study is necessary. All other notices filed outside of these parameters will be screened within the automated OE/AAA system and provided an electronic letter response that indicates that no notice is required for the said proposal or alteration, and thus the FAA has no objections to the proposal. 77.32 In order to request a modification or deviation from the marking and lighting requirements contained in a Determination of No Hazard to Air Navigation, the sponsor must submit FAA Form 7460-1, Notice of Proposed Construction or Alteration. 77.33 Unless extended, revised, or terminated, each Determination of No Hazard to Air Navigation issued under subpart D of part 77 regarding a proposed permanent wind energy system, including an airborne wind energy system, and associated meteorological towers, expires 36 months after the effective date of the determination or on the date the proposed construction or alteration is abandoned, whichever is earlier.
Document Information
- Published:
- 11/18/2024
- Department:
- Federal Aviation Administration
- Entry Type:
- Proposed Rule
- Action:
- Notice of proposed rulemaking (NPRM).
- Document Number:
- 2024-26741
- Dates:
- Send comments on or before January 17, 2025.
- Pages:
- 90627-90646 (20 pages)
- Docket Numbers:
- Docket No. FAA-2024-2574, Notice No. 25-01
- RINs:
- 2120-AK77: Requirements to File Notice of Construction of Meteorological Evaluation Towers and Other Renewable Energy Projects
- RIN Links:
- https://www.federalregister.gov/regulations/2120-AK77/requirements-to-file-notice-of-construction-of-meteorological-evaluation-towers-and-other-renewable-
- Topics:
- Airspace, Aviation safety, Reporting and recordkeeping requirements
- PDF File:
- 2024-26741.pdf
- Supporting Documents:
- » U.S. DOT/FAA - Supplemental Documents
- CFR: (1)
- 14 CFR 77