2019-24892. Notice of Final Federal Agency Actions on Proposed Highway in City of Salem, Marion County, Oregon
-
Start Preamble
AGENCY:
Federal Highway Administration (FHWA), DOT.
ACTION:
Notice of limitation on claims for judicial review of actions by FHWA.
SUMMARY:
This notice announces actions taken by the FHWA that are final. The actions relate to a proposed highway project, Salem River Crossing Project, over the Willamette River, in City of Salem, Marion County, Oregon. Those actions grant approvals for the project.
DATES:
By this notice, FHWA is advising the public of final agency actions subject to 23 U.S.C. 139(l)(1). A claim seeking judicial review of the Federal agency actions on the highway project will be barred unless the claim is filed on or before April 17, 2020. If the Federal law that authorizes judicial review of a claim provides a time period of less than 150 days for filing such claim, then that shorter time period still applies.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Emily Cline, Environmental Program Manager, FHWA Oregon Division Office, 530 Center St. NE, Salem, OR 97301, Office Hours: 7:30 a.m. to 4:00 p.m., Office Phone: 503-316-2547, Email: Emily.cline@dot.gov. You may also contact Anna Henson, Senior Project Leader, ODOT Region 2, 455 Airport Road SE, Building B, Salem, OR 97301, Office Phone: 503-986-2639, Office Hours: 8:00 a.m. to 5:00 p.m., Email: Anna.Henson@odot.state.or.us.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
Notice is hereby given that FHWA has taken final agency action subject to 23 U.S.C. 139(l)(1) by issuing approvals for the following highway project in the State of Oregon. The Salem River Crossing Project proposed to construct a proposed new third bridge crossing of the Willamette River in Salem, Oregon, along with associated surface street improvements. The purpose of the project is to improve mobility and safety Start Printed Page 63958for people and freight for local, regional, and through travel across the Willamette River in the Salem-Keizer metropolitan area while alleviating congestion on the existing bridges and connecting highway and arterial street systems. [Federal ID No. S000(287) & S000(288)]. The actions by the agencies, and the laws under which such actions were taken, are described in the Final Environmental Impact Statement (FEIS) and Record of Decision (ROD) for the project, approved on September 5, 2019. The Salem River Crossing FEIS/ROD and other project records are available by contacting FHWA or Oregon DOT at the addresses provided above. The FEIS and can be viewed and downloaded from the project website at: https://www.oregon.gov/odot/projects/pages/project-details.aspx?project=17317 or obtained from any contact listed above. This notice applies to all Federal agency decisions that are final as of the issuance date of this notice and all laws under which such actions were taken, including but not limited to:
1. General: National Environmental Policy Act (NEPA) [42 U.S.C. 4321-4351]; Federal-Aid Highway Act [23 U.S.C. 109 and 23 U.S.C. 128].
2. Air: Clean Air Act [42 U.S.C. 7401-7671q].
3. Land: Section 4(f) of the Department of Transportation Act of 1966 [49 U.S.C. 303; 23 U.S.C. 138]; Landscaping and Scenic Enhancement (Wildflowers) [23 U.S.C. 319].
4. Wildlife: Endangered Species Act [16 U.S.C. 1531-1544 and Section 1536]; Marine Mammal Protection Act [16 U.S.C. 1361-1423h]; Fish and Wildlife Coordination Act [16 U.S.C. 661-667d]; Migratory Bird Treaty Act [16 U.S.C. 703-712].
5. Historic and Cultural Resources: Section 106 of the National Historic Preservation Act of 1966, as amended [54 U.S.C. 306108]; Archeological Resources Protection Act of 1977 [54 U.S.C. 312501-312508]; Native American Grave Protection and Repatriation Act (NAGPRA) [25 U.S.C. 3001-3013].
6. Historic and Cultural Resources: Section 106 of the National Historic Preservation Act of 1966, as amended [54 U.S.C. 306108]; Archeological Resources Protection Act of 1977 [54 U.S.C. 312501-312508]; Native American Grave Protection and Repatriation Act (NAGPRA) [25 U.S.C. 3001-3013].
7. Social and Economic: American Indian Religious Freedom Act [42 U.S.C. 1996]; Farmland Protection Policy Act (FPPA) [7 U.S.C. 4201-4209].
8. Wetlands and Water Resources: Clean Water Act (Section 404, Section 401, Section 319) [33 U.S.C. 1251-1387]; Land and Water Conservation Fund (LWCF) [16 U.S.C. 4601-4604]; Safe Drinking Water Act (SDWA) [42 U.S.C. 300f-300j-26)]; Rivers and Harbors Act of 1899 [33 U.S.C. 401-406]; Wild and Scenic Rivers Act [16 U.S.C. 1271-1287]; Emergency Wetlands Resources Act, [16 U.S.C. 3901, 3921]; Wetlands Mitigation [23 U.S.C. 119(g) and 133(b)(14)]; Flood Disaster Protection Act, 42 U.S.C. 4012a, 4106].
9. Executive Orders: E.O. 11990 Protection of Wetlands; E.O. 11988 Floodplain Management; E.O. 12898, Federal Actions to Address Environmental Justice in Minority Populations and Low Income Populations; E.O. 11593 Protection and Enhancement of Cultural Resources; E.O. 13007 Indian Sacred Sites; E.O. 13287 Preserve America; E.O. 13175 Consultation and Coordination with Indian Tribal Governments; E.O. 11514 Protection and Enhancement of Environmental Quality; E.O. 13112 Invasive Species.
(Catalog of Federal Domestic Assistance Program Number 20.205, Highway Planning and Construction. The regulations implementing Executive Order 12372 regarding intergovernmental consultation on Federal programs and activities apply to this program.)
Start SignatureIssued on: November 4, 2019.
Phillip A. Ditzler,
Division Administrator, Salem, Oregon.
[FR Doc. 2019-24892 Filed 11-18-19; 8:45 am]
BILLING CODE 4910-RY-P
Document Information
- Published:
- 11/19/2019
- Department:
- Federal Highway Administration
- Entry Type:
- Notice
- Action:
- Notice of limitation on claims for judicial review of actions by FHWA.
- Document Number:
- 2019-24892
- Dates:
- By this notice, FHWA is advising the public of final agency actions subject to 23 U.S.C. 139(l)(1). A claim seeking judicial review of the Federal agency actions on the highway project will be barred unless the claim is filed on or before April 17, 2020. If the Federal law that authorizes judicial review of a claim provides a time period of less than 150 days for filing such claim, then that shorter time period still applies.
- Pages:
- 63957-63958 (2 pages)
- PDF File:
- 2019-24892.pdf
- Supporting Documents:
- » Final Federal Agency Actions: Proposed Highway in California
- » Final Federal Agency Actions: Proposed Highway Projects in Texas
- » Transfer and Sanction Programs
- » Experimental Project To Evaluate Proposals for Delegation of Certain Program-Wide FHWA Responsibilities to States
- » Environmental Impact Statements; Availability, etc.: Multiple Counties in Alabama; Rescission
- » Federal Agency Actions: SH 205 From North of John King (Rockwall County Line) to SH 78 in Collin County, TX
- » Federal Agency Actions: Interstate 95 in City of Fredericksburg and Counties of Spotsylvania, Stafford, Prince William, and Fairfax, VA
- » Environmental Impact Statements; Availability, etc.: I-495 and I-270 Managed Lanes Study, Montgomery and Prince George's Counties, MD and Fairfax County, VA
- » Federal Agency Actions: Proposed Highway in California
- » Federal Agency Actions: California; Proposed Highway