97-30634. ANR Pipeline Company v. Transcontinental Gas Pipe Line Corporation; Notice of Complaint  

  • [Federal Register Volume 62, Number 225 (Friday, November 21, 1997)]
    [Notices]
    [Pages 62294-62295]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-30634]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP98-74-000]
    
    
    ANR Pipeline Company v. Transcontinental Gas Pipe Line 
    Corporation; Notice of Complaint
    
    November 17, 1997.
        Take notice that on November 7, 1997, ANR Pipeline Company (ANR), 
    500 Renaissance Center, Detroit, Michigan 48243, filed with the 
    Commission in Docket No. CP98-74-000 a complaint against 
    Transcontinental Gas Pipe Line Company (Transco) P.O. Box 1396, 
    Houston, Texas 77251 requesting that the Commission direct Transco to 
    establish an interconnection that will enable ANR to make deliveries to 
    Transco in Evangeline Parish, Louisiana, all as more fully set forth in 
    the complaint on file with the Commission and open to public 
    inspection.
        ANR states that since January 1997, ANR and Transco have discussed 
    the construction of an interconnection between their respective 
    mainline facilities in Evangeline Parish, Louisiana that would allow 
    ANR to make firm deliveries of up to 300 MMCF of gas per day to Transco 
    to satisfy requests of certain shippers on the ANR system. ANR 
    indicates that it has advised Transco that ANR will reimburse Transco 
    for the cost of these facilities. ANR claims that in July 1997, Transco 
    advised ANR that it would not consent to the construction of an 
    interconnection that would allow gas to be delivered on a firm basis 
    from ANR's mainline into Transco's mainline. ANR asserts that Transco 
    informed ANR that, as an alternative, it would be willing to accept 
    deliveries on behalf of ANR's shippers at an existing point of 
    interconnection between ANR's facilities and a lateral pipeline owned 
    by Transco and operated by Transco's affiliate, Williams Field 
    Services, which is located at Enice, Louisiana. ANR states that ANR 
    informed Transco that its alternate proposal for receiving gas from ANR 
    was not acceptable because it did not satisfy the needs of ANR's 
    shippers.
        ANR claims that because Transco has declined to construct the 
    facilities the dispute between ANR and Transco has reached an impasse. 
    ANR requests that the Commission promptly resolve the dispute by 
    ordering Transco to install the requested minor interconnection 
    facilities.
        Any person desiring to be heard or make a protest with reference to 
    ANR's complaint should file with the Federal Energy Regulatory 
    Commission, 888 First Street, NE., Washington, DC 20426, a motion to 
    intervene or protest in accordance with the Commission's Rules of 
    Practice and Procedure (18 CFR 385.211 or 385.214). All such motions, 
    together with the answer of Respondent to the complaint and motions, 
    should be filed on or before December 17, 1997. Any person desiring to 
    become a party must file a motion to intervene. Copies
    
    [[Page 62295]]
    
    of this filing are on file with the Commission and available for public 
    inspection. Answers to the complaint shall be due on or before December 
    17, 1997.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 97-30634 Filed 11-20-97; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
11/21/1997
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
97-30634
Pages:
62294-62295 (2 pages)
Docket Numbers:
Docket No. CP98-74-000
PDF File:
97-30634.pdf