2016-27862. Air Plan Approval/Disapproval; AL Infrastructure Requirements for the 2010 1-Hour NO2  

  • Start Preamble

    AGENCY:

    Environmental Protection Agency (EPA).

    ACTION:

    Final rule

    SUMMARY:

    The Environmental Protection Agency (EPA) is taking final action to approve in part, and disapprove in part, portions of the April 23, 2013, and December 9, 2015, of the State Implementation Plan (SIP) submissions, submitted by the State of Alabama, through the Alabama Department of Environmental Management (ADEM), to demonstrate that the State meets certain infrastructure requirements of the Clean Air Act (CAA or Act) for the 2010 1-hour nitrogen dioxide (NO2) national ambient air quality standards (NAAQS). The CAA requires that each state adopt and submit a SIP for the implementation, maintenance and enforcement of each NAAQS promulgated by EPA, which is commonly referred to as an “infrastructure” SIP. ADEM certified that the Alabama SIP contains provisions that ensure the 2010 1-hour NO2 NAAQS is implemented, enforced, and maintained in Alabama. With the exception of the provisions pertaining to prevention of significant deterioration (PSD) permitting, and visibility in other states, for which EPA is proposing no action through this notice, and the provisions respecting state boards, for which EPA is finalizing disapproval, EPA has determined portions of Alabama's infrastructure SIP submissions, provided to EPA on April 23, 2013, and updated on December 9, 2015, satisfy certain required infrastructure elements for the 2010 1-hour NO2 NAAQS.

    DATES:

    This rule will be effective December 21, 2016.

    ADDRESSES:

    EPA has established a docket for this action under Docket Identification No. EPA-R04-OAR-2014-0756. All documents in the docket are listed on the www.regulations.gov Web site. Although listed in the index, some information is not publicly available, i.e., Confidential Business Information or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, is not placed on the Internet and will be publicly available only in hard copy form. Publicly available docket materials are available either electronically through www.regulations.gov or in hard copy at the Air Regulatory Management Section, Air Planning and Implementation Branch, Air, Pesticides and Toxics Management Division, U.S. Environmental Protection Agency, Region 4, 61 Forsyth Street SW., Atlanta, Georgia 30303-8960. EPA requests that if at all possible, you contact the person listed in the FOR FURTHER INFORMATION CONTACT section to schedule your inspection. The Regional Office's official hours of business are Monday through Friday 8:30 a.m. to 4:30 p.m., excluding Federal holidays.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Richard Wong, Air Regulatory Management Section, Air Planning and Implementation Branch, Pesticides and Toxics Management Division, Region 4, U.S. Environmental Protection Agency, 61 Forsyth Street SW., Atlanta, Georgia 30303-8960. The telephone number is (404) 562-8726. Mr. Richard Wong can also be reached via electronic mail at wong.richard@epa.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background and Overview

    On January 22, 2010 (75 FR 6474, February 9, 2010), EPA promulgated a new 1-hour primary NAAQS for NO2 at a level of 100 parts per billion (ppb), based on a 3-year average of the 98th percentile of the yearly distribution of 1-hour daily maximum concentrations. Pursuant to section 110(a)(1) of the CAA, states are required to submit SIPs meeting the requirements of section 110(a)(2) within three years after promulgation of a new or revised NAAQS or within such shorter period as EPA may prescribe. Section 110(a)(2) requires states to address basic SIP elements such as requirements for monitoring, basic program requirements and legal authority that are designed to assure attainment and maintenance of the NAAQS. States were required to submit such SIPs for the 2010 NO2 NAAQS to EPA no later than January 22, 2013.

    In a proposed rulemaking published on July 20, 2016 (81 FR 47124), EPA proposed to approve Alabama's 2010 1-hour NO2 NAAQS infrastructure SIP submissions submitted on April 23, 2013, and December 9, 2015, with the exception of the PSD permitting requirements for major sources of sections 110(a)(2)(C), prong 3 of D(i), and (J) and the interstate transport requirements of section 110(a)(2)(D)(i)(I) and (II) (prongs 1, 2, and 4), and the state board requirements of section Start Printed Page 83143110(a)(2)(E)(ii). On March 18, 2015, EPA approved Alabama's April 23, 2013, infrastructure SIP submission regarding the PSD permitting requirements for major sources of sections 110(a)(2)(C), prong 3 of D(i) and (J) for the 2010 1-hour NO2 NAAQS. See 80 FR 14019.[1] Therefore, EPA is not taking any action today pertaining to sections 110(a)(2)(C), prong 3 of D(i) and (J). With respect to the interstate transport requirements of section 110(a)(2)(D)(i)(I) (prongs 1, 2 and 4), Alabama provided a separate submissions. EPA is considering action on Alabama's submission related to 110(a)(2)(D)(i)(I) (prongs 1, 2 and 4) through a separate actions. Additionally, with respect to Alabama's infrastructure SIP submissions related to section 110(a)(2)(E)(ii) requirements respecting the section 128 state board requirements, EPA is disapproving this element of Alabama's submissions in this rulemaking. The details of Alabama's submission and the rationale for EPA's actions for this final rulemaking are explained in the July 20, 2016, proposed rulemaking. Comments on the proposed rulemaking were due on or before August 19, 2016. EPA received no adverse comments on the proposed action.

    II. Final Action

    EPA is taking final action to approve Alabama's infrastructure SIP submissions for the 2010 1-hour NO2 NAAQS, with the exception of the PSD permitting requirements for major sources of sections 110(a)(2)(C), prong 3 of D(i), and (J) and the interstate transport requirements of section 110(a)(2)(D)(i)(I) and (II) (prongs 1, 2, and 4). With regard to the state board majority requirements of section 110(a)(2)(E)(ii), EPA is finalizing a disapproval of Alabama' April 23, 2013, and December 9, 2015, infrastructure submissions. Under section 179(a) of the CAA, final disapproval of a submittal that addresses a requirement of a CAA Part D Plan or is required in response to a finding of substantial inadequacy as described in CAA section 110(k)(5) (SIP call) starts a sanctions clock. The portion of section 110(a)(2)(E)(ii) provisions (the provisions being disapproved in this notice) were not submitted to meet requirements for Part D or a SIP call, and therefore, no sanctions will be triggered. However, this final action will trigger the requirement under section 110(c) that EPA promulgate a Federal Implementation Plan (FIP) no later than two years from the date of the disapproval unless the State corrects the deficiency, and EPA approves the plan or plan revision before EPA promulgates such FIP.

    III. Statutory and Executive Order Reviews

    Under the CAA, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable federal regulations. See 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, EPA's role is to approve state choices, provided that they meet the criteria of the CAA. Accordingly, this action merely approves state law as meeting federal requirements and does not impose additional requirements beyond those imposed by state law. For that reason, this action:

    • Is not a significant regulatory action subject to review by the Office of Management and Budget under Executive Orders 12866 (58 FR 51735, October 4, 1993) and 13563 (76 FR 3821, January 21, 2011);
    • does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
    • is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.);
    • does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4);
    • does not have Federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999);
    • is not an economically significant regulatory action based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997);
    • is not a significant regulatory action subject to Executive Order 13211 (66 FR 28355, May 22, 2001);
    • is not subject to requirements of Section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA; and
    • does not provide EPA with the discretionary authority to address, as appropriate, disproportionate human health or environmental effects, using practicable and legally permissible methods, under Executive Order 12898 (59 FR 7629, February 16, 1994).

    The SIP is not approved to apply on any Indian reservation land or in any other area where EPA or an Indian tribe has demonstrated that a tribe has jurisdiction. In those areas of Indian country, the rule does not have tribal implications as specified by Executive Order 13175 (65 FR 67249, November 9, 2000), nor will it impose substantial direct costs on tribal governments or preempt tribal law.

    The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. EPA will submit a report containing this action and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rule in the Federal Register. A major rule cannot take effect until 60 days after it is published in the Federal Register. This action is not a “major rule” as defined by 5 U.S.C. 804(2).

    Under section 307(b)(1) of the CAA, petitions for judicial review of this action must be filed in the United States Court of Appeals for the appropriate circuit by January 20, 2017. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this action for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements. See section 307(b)(2).

    Start List of Subjects

    List of Subjects in 40 CFR Part 52

    • Environmental protection
    • Air pollution control
    • Incorporation by reference
    • Intergovernmental relations
    • Nitrogen dioxide
    • Ozone
    • Reporting and recordkeeping requirements
    • Volatile organic compounds
    End List of Subjects Start Signature

    Dated: November 4, 2016.

    Heather McTeer Toney,

    Regional Administrator, Region 4.

    End Signature

    40 CFR part 52 is amended as follows:

    Start Part

    PART 52—APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS

    End Part Start Amendment Part

    1. The authority citation for part 52 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 42 U.S.C. 7401 et seq.

    End Authority Start Printed Page 83144

    Subpart B—Alabama

    Start Amendment Part

    2. Section 52.50(e), is amended by adding an entry for “110(a)(1) and (2) Infrastructure Requirements for the 2010 1-hour NO 2 NAAQS” at the end of the table to read as follows:

    End Amendment Part
    Identification of plan.
    * * * * *

    (e) * * *

    EPA-Approved Alabama Non-Regulatory Provisions

    Name of nonregulatory SIP provisionApplicable geographic or nonattainment areaState submittal date/effective dateEPA approval dateExplanation
    *         *         *         *         *         *         *
    110(a)(1) and (2) Infrastructure Requirements for the 2010 1-hour NO2 NAAQSAlabama4/23/201311/21/2016 [Insert citation of publication]With the exception of sections: 110(a)(2)(C) and (J) concerning PSD permitting requirements; 110(a)(2)(D)(i)(I) and (II) (prongs 1 through 4) concerning interstate transport requirements and the state boards of section 110(a)(2)(E)(ii).
    Start Amendment Part

    3. Section 52.53 is amended by adding paragraph (c) to read as follows:

    End Amendment Part
    Approval status.
    * * * * *

    (c) Disapproval. Submittal from the State of Alabama, through the Alabama Department of Environmental Management (ADEM) on April 23, 2013, and December 9, 2015, to address the Clean Air Act section 110(a)(2)(E)(ii) for the 2010 1-hour nitrogen dioxide (NO2) National Ambient Air Quality Standards (NAAQS) concerning state board requirements. EPA is disapproving section 110(a)(2)(E)(ii) of ADEM's submittal because the Alabama SIP lacks provisions respecting state boards per section 128 of the CAA for the 2010 Nitrogen Dioxide National Ambient Air Quality Standards.

    End Supplemental Information

    Footnotes

    1.  ADEM clarified that its December 9, 2015, submission was not intended to address the PSD requirements that were approved by EPA on March 18, 2015. See www.regulations.gov using Docket ID No. EPA-R04-OAR-2014-0756.

    Back to Citation

    [FR Doc. 2016-27862 Filed 11-18-16; 8:45 am]

    BILLING CODE 6560-50-P

Document Information

Effective Date:
12/21/2016
Published:
11/21/2016
Department:
Environmental Protection Agency
Entry Type:
Rule
Action:
Final rule
Document Number:
2016-27862
Dates:
This rule will be effective December 21, 2016.
Pages:
83142-83144 (3 pages)
Docket Numbers:
EPA-R04-OAR-2014-0756, FRL-9955-29-Region 4
Topics:
Air pollution control, Environmental protection, Incorporation by reference, Intergovernmental relations, Nitrogen dioxide, Ozone, Reporting and recordkeeping requirements, Volatile organic compounds
PDF File:
2016-27862.pdf
Supporting Documents:
» Final AL Network Plan Response 11-19-15
» ADEMFY15EOY
» NO2 110(a)(2) Checklist
» Cover Letter
CFR: (2)
40 CFR 52.50
40 CFR 52.53