2022-25596. Columbia Gas Transmission, LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline  

  • Start Preamble Start Printed Page 71595

    Take notice that on November 7, 2022, Columbia Gas Transmission, LLC (Columbia), 700 Louisiana Street, Suite 1300, Houston, Texas 77002, filed in the above referenced docket, a prior notice pursuant to Section 157.205, 157.208 and 157.216 of the Federal Energy Regulatory Commission's regulations under the Natural Gas Act and the blanket certificate issued by the Commission in Docket No. CP83-76-000,[1] seeking authorization to replace approximately 1.2 miles of 18-inch steel pipeline and related facilities on its existing Line R300 lateral pipeline and to reduce the maximum allowable operating pressure (MAOP) from 200 pounds per square inch gauge (psig) to 125 psig in Lawrence County, Ohio (Project).

    Columbia asserts that Replacing Line R300 with new pipeline will ensure compliance with the Pipeline and Hazardous Materials Safety Administration and enable Columbia to continue to provide reliable, safe, and efficient service. The proposed construction is estimated to cost approximately $3,700,000 all as more fully set forth in the request which is on file with the Commission and open to public inspection.

    In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( http://ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission's Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID-19), issued by the President on March 13, 2020. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY, (202) 502-8659.

    Any questions concerning this application should be directed to David A. Alonzo, Manager, Project Authorizations, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 1300, Houston, Texas, 77002, by telephone (832) 320-5477, or by email david_alonzo@tcenergy.com.

    Public Participation

    There are three ways to become involved in the Commission's review of this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on January 16, 2023. How to file protests, motions to intervene, and comments is explained below.

    Protests

    Pursuant to section 157.205 of the Commission's regulations under the NGA,[2] any person [3] or the Commission's staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission.

    Protests must comply with the requirements specified in section 157.205(e) of the Commission's regulations,[4] and must be submitted by the protest deadline, which is January 16, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor.

    Interventions

    Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission's orders in the U.S. Circuit Courts of Appeal.

    To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission's Rules of Practice and Procedure [5] and the regulations under the NGA [6] by the intervention deadline for the project, which is January 16, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/​resources/​guides/​how-to/​intervene.asp.

    All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission's Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties.

    Comments

    Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before January 16, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding.

    How To File Protests, Interventions, and Comments

    There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23-13-000 in your submission.

    (1) You may file your protest, motion to intervene, and comments by using the Commission's eFiling feature, which is located on the Commission's website ( www.ferc.gov) under the link to Documents and Filings. New eFiling Start Printed Page 71596 users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; first select General” and then select “Protest”, “Intervention”, or “Comment on a Filing.” The Commission's eFiling staff are available to assist you at (202) 502-8258 or FercOnlineSupport@ferc.gov.

    (2) You can file a paper copy of your submission. Your submission must reference the Project docket number CP23-13-000.

    To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426

    To mail via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852

    Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: David A. Alonzo, Manager, Project Authorizations, Columbia Gas Transmission, LLC, 700 Louisiana Street, Suite 1300, Houston, Texas 77002, by telephone (832) 320-5477, or by email david_alonzo@tcenergy.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online.

    Tracking the Proceeding

    Throughout the proceeding, additional information about the project will be available from the Commission's Office of External Affairs, at (866) 208-FERC, or on the FERC website at www.ferc.gov using the “eLibrary” link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.

    In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/​docs-filing/​esubscription.asp.

    Start Signature

    Dated: November 17, 2022.

    Debbie-Anne A. Reese,

    Deputy Secretary.

    End Signature End Preamble

    Footnotes

    1.   Columbia Gas Transmission Corporation (predecessor to Columbia Gas Transmission, LLC), 22 FERC ¶ 62,029 (1983).

    Back to Citation

    3.  Persons include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d).

    Back to Citation

    [FR Doc. 2022-25596 Filed 11-22-22; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
11/23/2022
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2022-25596
Pages:
71595-71596 (2 pages)
Docket Numbers:
Docket No. CP23-13-000
PDF File:
2022-25596.pdf