    Florida Gas Transmission Company; Notice of Request Under Blanket 
    Authorization
    
    November 17, 1995.
        Take notice that on November 14, 1995, Florida Gas Transmission 
    Company (FGT), 1400 Smith Street, P.O. Box 1188, Houston, Texas 77251-
    1188, filed in Docket No. CP96-66-000 a request pursuant to Sections 
    157.205 and 157.212 of the Commission's Regulations under the Natural 
    Gas Act (18 CFR 157.205, 157.212) for authorization to upgrade the 
    existing Martin North Meter Station in Martin County, Florida under 
    FGT's blanket certificate issued in Docket No. CP82-553-000 pursuant to 
    Section 7 of the Natural Gas Act, all as more fully set forth in the 
    request that is on file with the Commission and open to public 
    inspection.
        FGT states that the proposed construction was requested to give 
    Florida Power and Light Company (FPL) more deliverability options at 
    the Martin North Meter Station. The proposed upgrade will not increase 
    the certificated level of service or contractual gas quantities which 
    FGT is currently providing FPL. FGT's peak day and annual deliveries 
    would not be impacted, there is sufficient capacity to accommodate 
    service without detriment or disadvantage to FGT's existing customers 
    and FGT's existing tariff does not prohibit the proposed upgrading.
        FGT proposes to install an additional 12-inch meter tube and 
    appurtenant facilities to accommodate a total gas measurement of up to 
    8,500 Mcf per hour at 250 psig. The estimated cost is 
    
    [[Page 58082]]
    $75,000, inclusive of tax gross-up, and FPL will reimbruse FGT for all 
    direct and indirect costs. The location of the proposed upgrade is 
    Section 14, Township 38 South, Range 40 East, Martin County, Florida.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 95-28569 Filed 11-22-95; 8:45 am]
    BILLING CODE 6717-01-M
    
    

Document Information

Published:
11/24/1995
Department:
Energy Department
Entry Type:
Notice
Document Number:
95-28569
Pages:
58081-58082 (2 pages)
Docket Numbers:
Docket No. CP96-66-000
PDF File:
95-28569.pdf