95-28569. Florida Gas Transmission Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 60, Number 226 (Friday, November 24, 1995)]
[Notices]
[Pages 58081-58082]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 95-28569]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP96-66-000]
Florida Gas Transmission Company; Notice of Request Under Blanket
Authorization
November 17, 1995.
Take notice that on November 14, 1995, Florida Gas Transmission
Company (FGT), 1400 Smith Street, P.O. Box 1188, Houston, Texas 77251-
1188, filed in Docket No. CP96-66-000 a request pursuant to Sections
157.205 and 157.212 of the Commission's Regulations under the Natural
Gas Act (18 CFR 157.205, 157.212) for authorization to upgrade the
existing Martin North Meter Station in Martin County, Florida under
FGT's blanket certificate issued in Docket No. CP82-553-000 pursuant to
Section 7 of the Natural Gas Act, all as more fully set forth in the
request that is on file with the Commission and open to public
inspection.
FGT states that the proposed construction was requested to give
Florida Power and Light Company (FPL) more deliverability options at
the Martin North Meter Station. The proposed upgrade will not increase
the certificated level of service or contractual gas quantities which
FGT is currently providing FPL. FGT's peak day and annual deliveries
would not be impacted, there is sufficient capacity to accommodate
service without detriment or disadvantage to FGT's existing customers
and FGT's existing tariff does not prohibit the proposed upgrading.
FGT proposes to install an additional 12-inch meter tube and
appurtenant facilities to accommodate a total gas measurement of up to
8,500 Mcf per hour at 250 psig. The estimated cost is
[[Page 58082]]
$75,000, inclusive of tax gross-up, and FPL will reimbruse FGT for all
direct and indirect costs. The location of the proposed upgrade is
Section 14, Township 38 South, Range 40 East, Martin County, Florida.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 95-28569 Filed 11-22-95; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 11/24/1995
- Department:
- Energy Department
- Entry Type:
- Notice
- Document Number:
- 95-28569
- Pages:
- 58081-58082 (2 pages)
- Docket Numbers:
- Docket No. CP96-66-000
- PDF File:
-
95-28569.pdf