97-30821. Environmental Impact Statement for the High Flux Beam Reactor Transition Project at the Brookhaven National Laboratory, Upton, NY  

  • [Federal Register Volume 62, Number 226 (Monday, November 24, 1997)]
    [Notices]
    [Pages 62572-62576]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-30821]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    
    Environmental Impact Statement for the High Flux Beam Reactor 
    Transition Project at the Brookhaven National Laboratory, Upton, NY
    
    AGENCY: Department of Energy.
    
    ACTION: Notice of intent (NOI).
    
    -----------------------------------------------------------------------
    
    SUMMARY: The U.S. Department of Energy (DOE) announces its intent to 
    prepare an Environmental Impact Statement (EIS), pursuant to the 
    National Environmental Policy Act (NEPA), for the High Flux Beam 
    Reactor (HFBR) at the Brookhaven National Laboratory (BNL) in Upton, 
    New York. The EIS will evaluate the range of reasonable alternatives 
    regarding the future of the reactor, as required by NEPA, including: 
    (1) No action (maintaining HFBR in a shutdown and defueled condition); 
    (2) resume operation at a power level of 30 megawatt (MW) or up to 60 
    MW; (3) resume operation and enhance the facility; and (4) permanent 
    shutdown with eventual decontamination and decommissioning (D&D). DOE 
    invites individuals, organizations, and agencies to present oral and/or 
    written comments concerning the scope of the EIS, including the 
    environmental issues and alternatives the EIS should analyze.
    
    DATES: The public scoping begins with publication of this NOI in the 
    Federal Register and continues until January 23, 1998. Written comments 
    submitted by mail should be postmarked by that date to ensure 
    consideration. Comments mailed after that date will be considered to 
    the extent practicable.
        DOE will conduct public scoping meetings to assist it in defining 
    the appropriate scope of the EIS, including the significant 
    environmental issues to be addressed. DOE plans to hold scoping 
    meetings in the vicinity of BNL in December 1997 and January 1998. The 
    December meeting will be held at the following date, time and location:
        December 10, 1997, Mastic Beach Property Owners Association, 31 
    Neighborhood Road, Mastic Beach, New York 11951; Time: 4:00 p.m.-9:00 
    p.m.
        Locations of additional scoping meetings to be held in January will 
    be announced through the local media as soon as possible, but at least 
    15 days prior to the date of the meetings.
    
    ADDRESSES: Please direct comments or suggestions on the scope of the 
    EIS, requests to speak at the public scoping meetings, requests for 
    special arrangements to enable participation at scoping meetings (e.g., 
    interpreter for the hearing-impaired) and questions concerning the 
    project to: Michael Holland, Brookhaven Group, U.S. Department of 
    Energy, 53 Bell Avenue, Bldg. 464, P.O. Box 5000, Upton, NY 11973-5000, 
    (516) 344-3552, telefax (516) 344-1377, or by electronic mail to 
    mholland@bnl.gov.
    
    FOR FURTHER INFORMATION CONTACT: For general information associated 
    with the research aspects of the HFBR, please contact: Iran Thomas, 
    Deputy Associate Director, Office of Basic Energy Sciences, Office of 
    Energy Research, U.S. Department of Energy, ER-10, Germantown, MD 
    20874, telephone: (301) 903-3427.
        For technical information associated with reactor operation, please 
    contact: Robert Lange, Associate Director, Office of Facilities, Office 
    of Nuclear Energy,
    
    [[Page 62573]]
    
    U.S. Department of Energy, NE-40, 19907 Germantown Rd., Germantown, MD 
    20874, telephone: (301) 903-2915.
        For general information on the DOE NEPA process, please contact: 
    Carol M. Borgstrom, Director, Office of NEPA Policy and Assistance, EH-
    42, U.S. Department of Energy, 1000 Independence Avenue, S.W., 
    Washington, D.C. 20585-0119, telephone: (202) 586-4600 or leave a 
    message on (800) 472-2756.
    
    SUPPLEMENTARY INFORMATION:
    
    Background
    
        The Brookhaven National Laboratory was established in 1947 as a 
    multi-disciplinary scientific research center. It is located close to 
    the geographic center of Suffolk County, Long Island, about 56 miles 
    (91 kilometers) east of New York City. The Laboratory site consists of 
    8.2 square miles (21.3 square kilometers, 2,130 hectares) with most 
    principal facilities located near the center. The Laboratory carries 
    out basic and applied research in the following areas: High-energy and 
    nuclear physics; solid state physics; materials sciences and chemical 
    sciences; nuclear medicine; biomedical and environmental sciences; and 
    selected energy technologies.
        The HFBR, which is centrally located within the BNL site (about 1 
    mile from the eastern site boundary and 1.5 miles from the southern 
    boundary), was commissioned in 1965 as a scientific facility dedicated 
    to neutron scattering research and other research programs in solid 
    state physics, nuclear physics, materials technology, structural 
    biology, medicine and chemistry. Neutron scattering techniques are used 
    to study the structure and properties of materials. The HFBR has 
    provided about two-thirds of the Department's experimental capability 
    at reactors for neutron scattering.
        The HFBR uses heavy water (deuterium) for cooling and a highly 
    enriched uranium core to produce beams of thermal neutrons that are 
    guided to experimental areas by nine horizontal aluminum alloy tubes 
    called ``beam tubes.'' In addition, there are seven vertical tubes for 
    irradiating research samples in the reactor. The entire reactor and its 
    control room are enclosed within a confinement dome. This reactor does 
    not produce electric power. The HFBR staff presently consists of about 
    110 scientists, engineers, technicians, and administrative personnel. 
    The HFBR scientific user community numbers about 300 researchers, 
    including several from Japan and Europe.
        In some research areas the HFBR is the best facility in the United 
    States. For example, the facility's Small Angle Neutron Scattering 
    (SANS) capability is regarded as a particularly useful technique by 
    structural biologists, who represent a rapidly growing user community 
    for neutron scattering. The HFBR SANS offers unique capabilities for 
    the study of biological samples and is the best resource in the United 
    States for this type of work. In addition, the HFBR's Single Crystal 
    Neutron Diffraction equipment complements x-ray techniques in 
    determining the structure of complex organic molecules because of its 
    ability to locate hydrogen atoms. The HFBR facility has also been used 
    for radioisotope production, neutron activation analysis, and material 
    irradiation.
        The reactor was originally designed for operation at a power level 
    of 40 megawatts (MW). An equipment upgrade in 1982 allowed operation at 
    60 MW, which greatly enhanced the reactor's scientific capability. 
    Beginning in 1991, the operating power of the reactor was limited to 30 
    MW until additional analysis could be performed to address safety 
    concerns associated with a hypothetical loss of reactor coolant 
    accident while operating at 60 MW. Subsequent analyses, currently under 
    review as part of an on-going Safety Analysis Report revision program, 
    indicate that the HFBR could be safely operated at 60 MW. Scientific 
    users have recommended operating the reactor at 60 MW, and that the 
    Department upgrade and modernize the scientific instrumentation and 
    other features such as the beam tubes.
    
    Current Status of HFBR
    
        On December 21, 1996, the HFBR was shut down for refueling and 
    maintenance, a routine activity which normally occurs almost every 
    month. Before the reactor returned to scheduled scientific operations, 
    however, monitoring indicated that a plume of tritiated water was 
    contaminating the groundwater in excess of drinking water standards 
    south and down gradient of the reactor. DOE, in cooperation with the 
    U.S. Environmental Protection Agency (EPA), New York State Department 
    of Conservation (NYSDEC), and Suffolk County Department of Health 
    Services (SCDHS), immediately initiated activities to identify and 
    eliminate the source of the tritium plume. These activities, now 
    collectively called the Tritium Remediation Project, continue as part 
    of the Department's commitment to remediate the contaminated 
    groundwater.
        Data collection and analysis identified the HFBR spent fuel pool as 
    the likely source of the tritium plume. In May 1997, a short-term 
    removal action, in the form of a groundwater extraction system, was 
    undertaken to ensure that tritium contaminated groundwater in excess of 
    drinking water standards does not leave the BNL site boundary.
        The short-term removal action has been incorporated into the site's 
    cleanup program in accordance with the Interagency Agreement among DOE, 
    EPA and NYSDEC entered into pursuant to the Comprehensive Environmental 
    Response, Compensation and Liability Act (CERCLA). A description of the 
    removal action taken, alternatives considered, regulatory interaction, 
    and public participation activities associated with the short-term 
    removal action are documented in the Action Memorandum for Operable 
    Unit III Tritium Removal Action, dated May 9, 1997, which is available 
    in the reading rooms identified in this notice.
        The final remedial action will be determined through the CERCLA 
    Operable Unit III Remedial Investigation/Feasibility Study (RI/FS) 
    process and will be based on additional data collected, groundwater 
    modeling, and evaluations of various remediation options, including 
    those activities which comprise the Tritium Remediation Project. The 
    CERCLA Record of Decision that completes this process is scheduled to 
    be published in the fall of 1998. The potential environmental impacts 
    associated with this CERCLA action will be reflected and accounted for 
    in the environmental analysis contained in the EIS.
        In addition to the activities associated with the cleanup of the 
    contaminated groundwater plume, all fuel has been removed from the 
    reactor and the pool and shipped off-site in preparation for removing 
    all water from the fuel pool. Decontamination and dewatering of the 
    storage pool is underway in order to eliminate the current source of 
    the tritium to the groundwater beneath the HFBR. Operation of the 
    groundwater plume pumping, treatment, and recharge system continues. 
    The groundwater tritium plume has been characterized and modeled, and 
    continues to be sampled and monitored. Removal of the water from the 
    spent fuel pool is scheduled for completion by the end of 1997.
    
    Purpose and Need for the Agency Action
    
        The Department of Energy needs to make a decision regarding the 
    future of the HFBR at BNL. This EIS will aid DOE in its decisionmaking 
    process. In July
    
    [[Page 62574]]
    
    1997, the Department issued its ``Action Plan for Improved Management 
    of Brookhaven National Laboratory,'' which summarized the Department's 
    planned process for deciding the future of the HFBR. The Action Plan 
    states that the Secretary of Energy will decide the future of the HFBR 
    and directs an appropriate environmental review process. That review 
    process consists of this EIS on the HFBR, which will incorporate the 
    results of the tritium remediation project being conducted in 
    conjunction with the ongoing CERCLA process. The Secretary is scheduled 
    to decide upon a preferred alternative for the future of the HFBR in 
    early 1998 for inclusion in this EIS. As stated in the Action Plan, 
    that decision will take into account several factors, including: public 
    input from the local Long Island community; input from the HFBR 
    scientific user community and the DOE Basic Energy Sciences Advisory 
    Committee; and the value of the scientific information produced using 
    the HFBR. The alternatives listed in this Notice for evaluation in the 
    EIS reflect the full range of options available for the future of the 
    HFBR. The results of the EIS scoping process will be considered in 
    selecting the preferred alternative. The preferred alternative will be 
    noted in the Draft EIS, but the EIS will analyze all reasonable 
    alternatives, as required by NEPA.
        The Conference Report accompanying Pub. L. 105-62, the Energy and 
    Water Development Appropriations Act of 1998, directed that an EIS be 
    prepared on the HFBR. The Report noted the conferees' expectation that 
    the EIS include a ``comprehensive survey of any environmental hazards 
    that the tritium leak or other contamination associated with the HFBR 
    pose to the drinking water and health of the people in the surrounding 
    communities, and that it will provide a detailed plan for 
    remediation.'' The EIS will provide this analysis, while concurrently 
    proceeding with, the Tritium Remediation Project and applicable 
    Interagency Agreement and CERCLA commitments. Long-term remediation 
    plans are being prepared under the ongoing CERCLA program and will be 
    discussed with the local community. Consistent with Congress' 
    direction, the EIS will summarize this remediation plan and program, 
    and assess the HFBR's potential for further contributing to groundwater 
    contamination.
        The Report also directed the Department to drain the spent fuel 
    pool, meet the requirements outlined in the Suffolk County Sanitary 
    Code Article 12, complete seismic upgrades, and repair and seal the 
    floor drains. These modifications and repairs, in addition to those 
    indicated in (3) below, are needed to place the HFBR into a 
    radiologically and industrially safe condition, regardless of which 
    alternative is selected for the future of the HFBR, and do not result 
    in any adverse environmental impacts. Accordingly, since these 
    activities do not have an adverse impact and do not limit the choice of 
    reasonable alternatives, DOE intends to proceed with these activities 
    prior to completion of the EIS. These modifications include repairs 
    needed to bring the HFBR into compliance with applicable Federal, 
    State, and local laws and requirements, including the requirements of 
    Suffolk County Sanitary Code Article 12, which is relevant to reducing 
    risks and preventing future leaks from the facility to the groundwater. 
    These four specific modifications and repairs include:
        (1) Several floor joints and conduit penetrations in the floor of 
    the HFBR would be repaired and sealed to ensure that there is no 
    leakage path to groundwater from any accidental spill within the 
    reactor confinement building. The potential for spills exists during 
    both reactor operations and deactivation activities, when there would 
    be a need to move large quantities of radioactive liquids into tanks 
    and drums for storage, treatment or disposal.
        (2) Several piping systems and sumps in the HFBR would be modified 
    and repaired by replacing single-walled piping and sumps with double-
    walled components, or installing new components above the floor, thus 
    meeting the requirements of Suffolk County Sanitary Code 12 for 
    protection of groundwater. These systems would be used during 
    operations and during deactivation activities to flush systems and 
    reduce contamination.
        (3) The drains from the 350-foot tall stack (handles exhaust gases 
    from HFBR and other nearby facilities) would be repaired, along with 
    the collection piping and sump, to convert them from a single-walled to 
    a double-walled system. This would enhance the confinement integrity of 
    the HFBR by providing a barrier against potential accidental release of 
    radioactive materials to groundwater.
        (4) The HFBR control room and operations level crane would be 
    reinforced to protect radiological monitoring and control systems, as 
    well as operations personnel, in the event of a design basis 
    earthquake. The control room and crane are needed to ensure safe 
    reactor operations or deactivation activities.
        The Department is also evaluating a proposal to construct and 
    install a stainless steel liner in the spent fuel pool during the 
    preparation of the EIS. The installation of this impervious liner and 
    appurtenant leak detection system would result in the pool containing a 
    double-walled barrier to ensure that the storage pool would not be a 
    source of groundwater contamination in the future. DOE considers the 
    storage pool to be an essential component of the HFBR regardless of 
    whether or not the reactor operates. It would be needed to store spent 
    fuel during operations. During deactivation activities, it would be 
    used to handle various highly radioactive reactor components which must 
    be dismantled or cut apart in preparation for shipment offsite. Much of 
    this work would be conducted within the storage pool. A usable pool may 
    also be necessary for maintenance of the HFBR during an extended period 
    of time in its present shutdown condition. As part of the CERCLA 
    cleanup of Operable Unit III, the Department committed to construct and 
    install the liner prior to any use of the pool. As a result, the spent 
    fuel liner is included at this time as part of all alternatives, except 
    No Action. DOE specifically solicits comments on whether the liner 
    should be installed, along with the other modifications and repairs, 
    prior to completion of this EIS. After hearing public comments on this 
    issue, the Department may decide to include installation of the liner 
    as part of all alternatives, including No Action.
    
    Alternatives To Be Evaluated
    
        While Pub. L. 105-62 prohibited the use of funds made available 
    under that Act or any other act to restart the HFBR, this EIS will 
    analyze the following reasonable alternatives for the future of the 
    HFBR, as required by NEPA:
    
    No Action Alternative
    
        Under this alternative, the reactor would be maintained in the 
    current shutdown and defueled condition for the indefinite future; the 
    four modifications and repairs listed above would be performed. The 
    Department regards this as a non-preferred alternative, because it does 
    not resolve the future of the HFBR.
    
    Resume Operation Alternative
    
        The earliest date that the reactor could be restarted is October 
    1999, following completion of the NEPA process and all of the 
    modifications and repairs described above (including installation of 
    the spent fuel liner). This alternative includes two subalternatives:
    
    [[Page 62575]]
    
        a. Startup and operation of the reactor at a power level of 30 MW 
    (the power level prior to the shutdown).
        b. Startup and operation of the reactor at a power level of 30 MW 
    with a planned increase in operation at a level of up to 60 MW.
    
    Resume Operation and Enhance Facility Alternative
    
        Under this alternative, the Department would restart the reactor 
    for operation at a power level of up to 60 MW, and eventually replace 
    the reactor vessel to extend the life of the reactor, and upgrade the 
    reactor (e.g., add scientific instruments) to enhance the reactor's 
    scientific research capabilities and increase the number of potential 
    reactor users. Because of budget limitations, the Department regards 
    this as a non-preferred alternative.
    
    Permanent Shutdown Alternative
    
        Under this alternative, the HFBR would be permanently shut down for 
    eventual decontamination and decommissioning. Additional NEPA review 
    would be necessary in the future for a proposal to decontaminate and 
    decommission the reactor. This alternative would involve terminating 
    the scientific research mission of the HFBR at BNL and placing the 
    reactor in an industrially and radiologically safe condition for an 
    extended period of time until a proposal were made to decontaminate and 
    decommission the reactor. While an analysis of the full and complete 
    decontamination and decommissioning is beyond the scope of this EIS, 
    the potential environmental impacts associated with decontamination and 
    decommissioning will be analyzed to the extent possible.
        At this time, the Department of Energy has no preferred 
    alternative. As noted above, the Secretary of Energy will designate a 
    preferred alternative based on the results of the scoping process and 
    other information in early 1998.
    
    Preliminary Environmental Analysis
    
        The following issues have been tentatively identified for analysis 
    in the EIS. This list is neither intended to be all-inclusive nor is it 
    a predetermination of potential environmental impacts. The list is 
    presented to facilitate comment on the scope of the EIS. Additions to 
    or deletions from this list may occur as a result of the public scoping 
    process.
        Health and Safety: potential public and occupational consequences 
    from routine operation and credible accident scenarios.
        Waste Generation/Pollution Prevention: types of wastes expected to 
    be generated and stored, pollution prevention opportunities, and the 
    potential consequences to public safety and the environment.
        Hazardous Materials: handling, storage, and use; waste management 
    both present and future.
        Background Radiation: cosmic, rock, soil, water, and air, and the 
    potential addition of radiation.
        Water Resources: surface and groundwater hydrology, use, and 
    quality, and the potential for degradation.
        Air Quality: meteorological conditions, ambient background, 
    pollutant sources, and potential for degradation.
        Earth Resources: physiography, topography, geology, and soil 
    characteristics.
        Land Use: plans, policies and controls.
        Noise: ambient, sources, and sensitive receptors.
        Ecological Resources: wetlands, aquatic, terrestrial, economically/
    recreationally important species, threatened and endangered species.
        Socioeconomic: demography, economic base, labor pool, housing, 
    transportation, utilities, public services/facilities, education, 
    recreation, and cultural resources.
        Natural Disasters: floods, hurricanes, tornadoes, and seismic 
    events. Unavoidable Adverse Impacts.
        Natural and Depletable Resources: requirements and conservation 
    potential.
        Environmental Justice: any potential disproportionately high and 
    adverse impacts to minority and low income populations.
        Alternatives other than those presented in this document may 
    warrant examination, and new issues may be identified for evaluation.
    
    Scoping Meetings
    
        The purpose of this NOI is to encourage public involvement in the 
    EIS process and to solicit public comments on the proposed scope and 
    content of the EIS. DOE will hold public scoping meetings in the BNL 
    area to solicit both oral and written comments from interested parties.
        DOE will designate a facilitator for the scoping meetings. The 
    facilitator may ask for clarification of statements to ensure that 
    representatives of the DOE fully understand the comments and 
    suggestions. The scoping meetings will not be conducted as evidentiary 
    hearings nor will there be questioning of the commentors. At the 
    opening of each meeting the facilitator will establish the order of 
    speakers and will announce any additional procedures necessary for 
    conducting the meetings. To ensure that all persons wishing to make a 
    presentation are given the opportunity, a five-minute limit may be 
    enforced for each speaker, with the exception of public officials and 
    representatives of groups, who will be allotted ten minutes each. DOE 
    encourages those providing oral comments to also submit them in 
    writing. Comment cards will also be available for those who prefer to 
    submit their comments in written form.
        DOE will make transcripts of the scoping meetings and project-
    related materials available for public review in the following reading 
    rooms:
        1. U.S. Department of Energy, Freedom of Information Public Reading 
    Room, Forrestal Building, Room 1E-190, 1000 Independence Avenue, S.W., 
    Washington, D.C. 20585, Telephone: (202) 586-3142.
        2. Brookhaven National Laboratory Research Library, Bldg. 477A 
    Brookhaven Ave., Upton, NY 11973, Telephone: (516) 344-3483.
        3. Longwood Public Library, 800 Middle Country Rd., Middle Island, 
    NY 11953, Telephone: (516) 924-6400.
        4. Mastics-Moriches-Shirley Community Library, 301 William Floyd 
    Parkway, Shirley, NY 11967, Telephone: (516) 399-1511.
        Other environmental materials available at these locations or 
    through the Suffolk County Interlibrary Loan System include BNL's 1977 
    Site-wide EIS, Annual Site Environmental Reports, and the CERCLA 
    Administrative record for cleanup activities.
    
    NEPA Process
    
        The EIS for the HFBR will be prepared according to the National 
    Environmental Policy Act of 1969, the Council on Environmental 
    Quality's Regulations for Implementing the Procedural Provisions of 
    NEPA (40 CFR Parts 1500-1508), and DOE's NEPA Regulations (10 CFR Part 
    1021).
        The draft EIS is scheduled to be published in the summer of 1998. A 
    45-day comment period on the draft EIS is planned, and public hearings 
    to receive comments will be held approximately three weeks after 
    distribution of the draft EIS. Availability of the draft EIS, the dates 
    of the public comment period, and information about the public meetings 
    will be announced in the Federal Register and in the local news media 
    when the draft EIS is distributed.
        The final EIS, which will incorporate public comments received on 
    the draft EIS, is expected in November 1998. No sooner than 30 days 
    after a notice of availability of the final EIS is published
    
    [[Page 62576]]
    
    in the Federal Register, DOE will issue its Record of Decision and 
    publish it in the Federal Register. The Record of Decision is expected 
    to be issued in December 1998.
    
        Signed in Washington, D.C., this 19th day of November, 1997.
    Peter N. Brush,
    Acting Assistant Secretary, Environment, Safety and Health
    [FR Doc. 97-30821 Filed 11-21-97; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Published:
11/24/1997
Department:
Energy Department
Entry Type:
Notice
Action:
Notice of intent (NOI).
Document Number:
97-30821
Dates:
The public scoping begins with publication of this NOI in the Federal Register and continues until January 23, 1998. Written comments submitted by mail should be postmarked by that date to ensure consideration. Comments mailed after that date will be considered to the extent practicable.
Pages:
62572-62576 (5 pages)
PDF File:
97-30821.pdf