95-28978. In the Matter of: Commonwealth Edison Company (Zion Nuclear Power Station, Unit Nos. 1 and 2); Exemption  

  • [Federal Register Volume 60, Number 228 (Tuesday, November 28, 1995)]
    [Notices]
    [Pages 58686-58688]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-28978]
    
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket Nos. 50-295 and 50-304]
    
    
    In the Matter of: Commonwealth Edison Company (Zion Nuclear Power 
    Station, Unit Nos. 1 and 2); Exemption
    
    I.
    
        Commonwealth Edison Company (ComEd or the licensee) is the holder 
    of Facility Operating License Nos. DPR-39 and DPR-48, which authorize 
    operation of the Zion Nuclear Power Station, Unit Nos. 1 and 2, at a 
    steady-state reactor power level not in excess of 3250 megawatts 
    thermal. The facilities are pressurized water reactors located at the 
    licensee's site in Lake County, Illinois. The licenses provide, among 
    other things, that the Zion Nuclear Power Station is subject to all 
    rules, regulations, and Orders of the U.S. Nuclear Regulatory 
    Commission (the Commission or NRC) now or hereafter in effect.
    
    II.
    
        Sections III.B and III.D.2.(a) of 10 CFR Part 50, Appendix J, 
    Option A, require that Type B local leakage rate periodic tests shall 
    be performed during reactor shutdown for refueling, or other convenient 
    intervals, but in no case at intervals greater than 2 years. In 
    addition, Sections III.C and III.D.3 of 10 CFR Part 50, Appendix J, 
    Option A, require that Type C local leakage rate periodic tests shall 
    be performed during each reactor shutdown for refueling, but in no case 
    at intervals greater than 2 years. These requirements are reflected in 
    the Zion Technical Specifications (TS) as requirements to perform Type 
    B and C containment leakage rate testing in accordance with 10 CFR Part 
    50, Appendix J and approved exemptions.
    
    III.
    
        The licensee has determined that certain containment isolation 
    pathways have not been locally leakage rate tested (Type B and C tests) 
    as required by 10 CFR Part 50, Appendix J, Option A. There were 23 
    untested pathways in Unit 1 and 18 in Unit 2. In a letter dated August 
    16, 1995, the licensee requested relief from the requirement to perform 
    the Type B and C containment leakage rate tests of certain penetrations 
    and valves in these pathways in accordance with the requirements of 
    Sections III.B, III.C and III.D of 10 CFR Part 50, Appendix J, Option 
    A. Continued operation of the Zion units was authorized by a Notice of 
    Enforcement Discretion (NOED) orally granted on August 15, 1995, until 
    such time as the staff acted on the exemption requests. The NOED was 
    granted in writing on August 16, 1995.
        If the exemptions the licensee requested in its letter dated August 
    16, 1995, are granted, the tests, except those for which permanent 
    exemptions were requested, would be performed: (1) during the fall 1995 
    Unit 1 refueling outage, or (2) during power operation on Unit 2 prior 
    to September 15, 1995, or (3) during the Unit 2 refueling outage in the 
    fall of 1996.
        Attachment 1A of the licensee's letter contained one-time schedular 
    exemption requests and justifications for pathways that can be tested 
    at power. Although the tests can be performed with the units at power, 
    time was needed to properly develop and perform the necessary test 
    procedures. Accordingly, the licensee requested that the Type B and C 
    testing of the pathways associated with Zion, Unit 2, be deferred, with 
    final test completion of the affected pathways (as listed in Attachment 
    1A) prior to September 15, 1995. The tests have been completed on Unit 
    2. In addition, the licensee requested that the affected penetrations 
    associated with Zion, Unit 1, be deferred until the completion of its 
    current refueling outage, which began on September 9, 1995.
        Attachment 1B of the licensee's letter also contains one-time 
    schedular exemption requests and justifications for pathways that can 
    only be tested with the unit shutdown. The tests of the penetrations 
    listed in Attachment 1B would be performed during the next cold 
    shutdown of sufficient duration. In all cases, the testing would be 
    performed prior to the end of the next refueling outage on each unit. 
    The refueling outage is currently in progress for Unit 1 and is planned 
    for the fall of 1996 for Unit 2.
        Attachment 2 of the licensee's letter contains permanent exemption 
    requests and justifications for pathways that cannot satisfy the 
    requirements of 10 CFR Part 50, Appendix J, Option A, due to system/
    penetration design; that is, a test is not feasible, without making 
    physical plant modifications.
    
    Pathways Listed in Licensee's Attachment 1A
    
        Attachment 1A of the licensee's letter requested temporary, 
    schedular exemptions for components in the following containment 
    penetrations:
    
    Units 1 and 2:
        P-14, Valve 1(2) RC8045, Nitrogen to the Pressurizer Relief Tank.
    Unit 2 only:
        P-30, Valve 2AOV-DT9159A, Reactor Coolant Drain Tank to Gas 
    Analyzer.
    
        For Unit 2, the required tests were completed prior to September 
    15, 1995.
        For Unit 1, the required tests will be performed before startup 
    from the current refueling outage. The Zion TSs do not require 
    compliance with containment leakage rate limits during refueling 
    outages, because there is little risk of an accident occurring which 
    would release significant amounts of radioactivity. Therefore, the 
    staff finds acceptable the schedular exemption request to delay the 
    local leakage rate testing of valve 1 RC8045 until no later than 
    startup from the current Unit 1 refueling outage.
    
    Pathways Listed in Licensee's Attachment 1B
    
        Attachment 1B of the licensee's letter requested temporary, 
    schedular exemptions for components in the following containment 
    penetrations:
    
    Units 1 and 2:
        P-60, Valve 1(2)AOV-RV0005, Containment Vent Isolation
        P-70, Valve 1(2)SF8767, Refuel Cavity to Purification Pump
        P-80, ECCS Relief Valve Header to Pressurizer Relief Tank
        P-99, Valve 1(2)SF8787, Purification Pump to Refuel Cavity
    Unit 1 only:
        P-30, Valve 1AOV-DT9159A, Reactor Coolant Drain Tank to Gas 
    Analyzer
    
        For Unit 1, the required tests will be performed before startup 
    from the current refueling outage. The Zion TSs do not require 
    compliance with containment leakage rate limits during refueling 
    outages, because there is little risk of an accident occurring which 
    would release significant amounts of radioactivity. Therefore, the 
    staff finds acceptable the schedular exemption request to delay the 
    local leakage rate testing of the Unit 1 components listed above until 
    startup from the current Unit 1 refueling outage.
        For Unit 2, the leakage pathways do not consist of through-valve 
    leakage paths, but rather leakage paths out of 
    
    [[Page 58687]]
    containment isolation valves or barriers through or past valve packing, 
    diaphragms, flanges, or other resilient seals. The potential leakage 
    paths are small or restrictive and are at mechanical joints of flange 
    and compression fittings, through valve packing, or through cracks or 
    tears in valve diaphragms. Although none of the penetrations in 
    question were tested in accordance with the requirements, most of them 
    were tested during the most recent Type A containment leakage rate test 
    or by process flow, with either no or minimal leakage. For those 
    penetrations that were not tested, the leakage path for a significant 
    leak to occur requires a sequence of events for which the probability 
    of occurrence during the limited time period of the exemption is low 
    enough to provide reasonable assurance of no significant increase in 
    risk to the health and safety of the public. In addition, seismic 
    qualification of some of the systems, missile protection, and the 
    isolation valve seal water system all provide additional assurance that 
    the risk of a significant leak is minimal. For these reasons, the staff 
    finds that the requested schedular exemption is justified and that it 
    is acceptable to delay the local leakage rate testing of the Unit 2 
    components listed above until the next cold shutdown of sufficient 
    duration for testing, but no later than startup from the next Unit 2 
    refueling outage, currently scheduled for September 1996.
    
    Pathways Listed in Licensee's Attachment 2
    
        Attachment 2 of the licensee's letter requested permanent 
    exemptions for components in the following containment penetrations:
    
    Units 1 and 2:
        P-14, Valve 1(2) FCV-SA01A, Service Air Supply to Containment
        P-19, Valve 1(2) MOV-CC9413A, Component Cooling Water Supply to the 
    Reactor Coolant Pumps
        P-34, Valve 1(2) DW0030, Demineralized Flushing Water to 
    Containment
        P-43, Valve 1(2) LCV-DT1003, Reactor Coolant Drain Tank Pump 
    Discharge
        P-75, Valves 1(2) VC8402A, 1920HCV-VC182, 1(2) VC8402B, 1(2) 
    VC8403, Chemical and Volume Control to Regenerative Heat Exchanger
        P-76, Valve 1(2) VC8480A, Reactor Coolant Loop Fill Header
        P-77, Valves 1(2) PP0101, 1(2) PP0102, 1(2) PP0103, 1(2) PP0104, 
    Penetration Pressurization to Containment Valve Stations
        P-88, Valve 1(2) FCV-RV112, Containment Hot Water Supply
        P-102, Valve 1(2) AOV-RC8029, Primary Water to the Pressurizer 
    Relief Tank
    Unit 1 only:
        P-16, Compression Fittings on Five Reactor Vessel Leak Detection 
    System Lines
    
        To provide time for additional staff review before granting 
    permanent exemptions, the staff will consider only schedular exemptions 
    for these components. Final staff action on these exemption requests 
    will be taken by December 31, 1995.
        The leakage pathways listed above do not consist of through-valve 
    leakage paths, but rather leakage paths out of containment isolation 
    valves or barriers through or past valve packing, diaphragms, flanges, 
    or other resilient seals, except for Penetration P-77, which is 
    reviewed separately below. The potential leakage paths are small or 
    restrictive and are at mechanical joints of flange and compression 
    fittings, through valve packing, or through cracks or tears in valve 
    diaphragms. Although none of the penetrations in question were tested 
    in accordance with the requirements, most of them were tested during 
    the most recent Type A containment leakage rate test or by process 
    flow, with either no or minimal leakage. For those penetrations that 
    were not tested, the leakage path for a significant leak to occur 
    requires a sequence of events for which the probability of occurrence 
    during the limited time period of the schedular exemption is low enough 
    to provide reasonable assurance of no significant increase in risk to 
    health and safety of the public. In addition, seismic qualification of 
    some of the systems, missile protection, and the isolation valve seal 
    water system all provide additional assurance that the risk of a 
    significant leak is minimal. For these reasons, the staff finds that a 
    schedular exemption is justified and that it is acceptable to delay the 
    local leakage rate testing of the components listed above (except 
    Penetration P-77) until final staff action on these exemptions, which 
    will be taken prior to December 31, 1995.
    
    Penetration P-77
    
        Manual containment isolation valves 1(2) PP0101, 1(2) PP0102, 1(2) 
    PP0103, 1(2) PP0104, are in four lines that are part of the Penetration 
    Pressurization (PP) system. There is one valve in each line and it is 
    open during power operation. The piping associated with the PP system 
    is seismically supported and missile protected. The valves' primary 
    post-accident design function is to remain open so that the PP system 
    can continue to pressurize containment penetrations, such as electrical 
    penetrations, preventing containment leakage out through those 
    penetrations. These valves have not been locally leakage rate (Type C) 
    tested for through-valve leakage. Local leakage rate testing is 
    conducted with the valves open, with the packing of the four valves 
    part of the test boundary. The leakage rate from this test is added 
    into the sum of all local leakage rate tests for comparison to the 0.6 
    La acceptance criterion. This test was completed with satisfactory 
    results during refueling outage Z1R13 which ended March 1994 for Unit 1 
    and during refueling outage Z2R13 which ended April 1995 for Unit 2. 
    The portion of the PP system that includes these valves is continuously 
    monitored for leakage, with a high flow condition annunciated in the 
    control room. Additionally, these valves are tested for seat leakage 
    during the Type A (integrated leak rate) test.
        The post-accident design function of the PP system is to pressurize 
    components to a pressure greater than Pa, the calculated peak accident 
    pressure of the containment atmosphere during a design-basis accident, 
    thereby preventing containment out-leakage. The licensee asserts that 
    Penetration P-77 and its associated valves are provided with a suitable 
    alternative to Type C testing due to the leak detection and mitigation 
    capability of the system. The PP system features which provide that 
    capability are summarized as follows:
        (1) Supply characteristics:
        (a) Normal supply: 100 psig air receivers
    --passive components
    --pressurized greater than or equal to 1.10 Pa (Pa=47 psig)
        (b) Backup supplies--high degree of redundancy
    --three PP air compressors: safety-related, seismic, auto start 
    feature, powered from ESF buses
    --passive supply from high pressure Nitrogen bottles: safety-related, 
    seismic
    --non-safety-related Instrument Air system;
        (2) Leak Detection Capabilities: continuously monitored, main 
    control board alarms on low pressure and on high flow;
        (3) Piping system characteristics: seismically designed, missile 
    protected;
        (4) Operational readiness--TSs maintain:
        (a) Required pressure and flow
        (b) Availability of supplies (air compressors and Nitrogen) and 
    emergency power supplies 
    
    [[Page 58688]]
    
        (c) Periodic testing requirements for compressors.
        This system is required to be operable during Operational Modes 1-4 
    per the TSs. In addition, the PP system seal pressure is designed to 
    continuously maintain a nominal pressure of 1.04 Pa during post-
    accident conditions. Since this penetration and associated valves are 
    maintained at a pressure greater than or equal to post-loss-of-coolant 
    accident containment pressure, containment leakage is unlikely through 
    this penetration.
        Based on the above, the staff finds that a schedular exemption is 
    justified and that it is acceptable to delay the local leakage rate 
    testing of the four subject valves in Penetration P-77 until final 
    staff action is taken on these requests. Final staff action will be 
    taken by December 31, 1995.
        In addition, the Commission will not grant an exemption unless at 
    least one of the special circumstances, as defined in 10 CFR 
    50.12(a)(2), are present. One of the special circumstances is that: the 
    exemption would provide only temporary relief from the applicable 
    regulation and the licensee has made good faith efforts to comply with 
    the regulations. The licensee presented the following discussion to 
    show that the requested exemptions provide only temporary relief and 
    that the licensee made good faith efforts to comply.
    
        The Requested Exemptions Proved Only Temporary Relief and the 
    License Made Good Faith Efforts to Comply
        As discussed above, the exemption request is for short duration 
    relative to the discovery of the aforementioned issues (30 days for 
    Unit 2; completion of the upcoming refueling outage for Unit 1). All 
    pathways that can be safely tested during reactor power operation 
    for Unit 2 will be tested within 30 days. Such pathways for Unit 1 
    will be deferred until entry into Hot Shutdown at the completion of 
    the upcoming outage (outage begins September 7, 1995). For pathways 
    that cannot be tested during power operation, testing described in 
    Attachment 1B will be performed during the next opportunity of 
    sufficient duration when Unit 1 and Unit 2 are in Mode 5. The 
    pathways selected for testing will be based upon the expected 
    duration of the shutdown and the time required to prepare the 
    pathways for testing. Pathways not tested during a Cold Shutdown 
    will be tested during subsequent cold shutdowns that may occur prior 
    to the upcoming refueling outages. In all cases, tests will be 
    completed by the end of Unit 1 outage scheduled to commence 
    September 7, 1995 and for Unit 2 prior to the completion of the 
    September 1996 refueling outage. This meets an additional criterion 
    for a special circumstance per item (v) of 10 CFR 50.12(a)(2)(v), 
    i.e., ``The exemption would provide only temporary relief from the 
    applicable regulation and licensee or applicant has made good faith 
    efforts to comply with the regulation.'' ComEd believes that testing 
    to be performed prior to September 15, 1995 for Unit 2 and during 
    the upcoming refueling outage for Unit 1 demonstrates a good faith 
    effort.
    
        The exemption request is for a short duration relative to the 
    discovery of the above issues. On Unit 2, the pathways that could be 
    safely tested during power operation were tested prior to September 15, 
    1995. On Unit 1, this exemption allows the deferment of the testing of 
    these pathways until Unit 1 enters hot shutdown during the current 
    refueling outage. For pathways that can not be tested during power 
    operation, the testing described in Attachment 1B will be performed on 
    Unit 1 prior to the end of its current refueling outage and on Unit 2, 
    prior to the completion of the refueling outage currently scheduled to 
    commence in September 1996. The staff has decided that a good faith 
    effort on the part of the licensee to comply with the regulations has 
    been demonstrated by the testing that has already been completed on 
    Unit 2, the testing that will be completed on Unit 1 prior to startup 
    from its current refueling outage, and the schedule for completion of 
    the remainder of the testing.
    
    IV.
    
        Sections III.B and III.D.2.(a) of 10 CFR Part 50, Appendix J, 
    Option A, require that Type B local leakage rate periodic tests shall 
    be performed during reactor shutdown for refueling, or other convenient 
    intervals, but in no case at intervals greater than 2 years. In 
    addition, Sections III.C and III.D.3 of 10 CFR Part 50, Appendix J, 
    Option A, require that Type C local leakage rate periodic tests shall 
    be performed during reactor shutdown for refueling, but in no case at 
    intervals greater than 2 years.
        The licensee proposes an exemption to these sections which would 
    provide relief from the requirement to perform the Type B and C 
    containment leakage rate tests of certain penetrations and valves in 
    accordance with the requirements of Sections III.B, III.C, and III.D of 
    10 CFR Part 50, Appendix J, Option A.
        The Commission has determined that, pursuant to 10 CFR 50.12(a)(1), 
    this exemption is authorized by law, will not present an undue risk to 
    the public health and safety, and is consistent with the common defense 
    and security. The Commission further determined, for the reasons 
    discussed above, that special circumstances, as provided in 10 CFR 
    50.12(a)(2)(v), are present justifying the exemption; namely, that the 
    exemption would provide only temporary relief and the licensee made 
    good faith efforts to comply.
        Based on its review of the licensee's justifications, the staff 
    finds the licensee's requests for schedular exemptions for Type B and C 
    tests of 10 CFR Part 50, Appendix J, Option A, that can be performed 
    while at power (Attachment 1A to the licensee's letter) and those that 
    must be performed while shutdown (Attachment 1B to the licensee's 
    letter) to be acceptable. The staff has reviewed the licensee's 
    requests for permanent exemptions for components in certain 
    penetrations. To provide additional time for staff review before 
    granting permanent exemptions, the staff will at this time grant only 
    schedular exemptions until final staff action is taken on these 
    requests for these components. Final staff action on these exemption 
    requests will be taken prior to December 31, 1995.
        Pursuant to 10 CFR 51.32, the Commission has determined that 
    granting these exemptions will not have a significant impact on the 
    human environment (60 FR 45499).
        This exemption is effective upon issuance and shall expire upon 
    completion of the Unit 2 refueling outage, currently scheduled to 
    commence in September 1996.
    
        Dated at Rockville, Maryland, this 20th day of November 1995.
    
        For the Nuclear Regulatory Commission.
    Jack W. Roe,
    Director, Division of Reactor Projects--III/IV, Office of Nuclear 
    Reactor Regulation.
    [FR Doc. 95-28978 Filed 11-27-95; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
11/28/1995
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
95-28978
Pages:
58686-58688 (3 pages)
Docket Numbers:
Docket Nos. 50-295 and 50-304
PDF File:
95-28978.pdf