  • Milestone Target date
    Issue draft EIS April 2025.
    Draft EIS Public Meeting May 2025.
    Comments on draft EIS due June 2025.
    Commission issues final EIS December 2025.

Document Information

Published:
11/29/2024
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2024-27970
Pages:
94719-94720 (2 pages)
Docket Numbers:
Project No. 1889-085, Project No. 2485-071