94-27306. Salt Lake City Area/Integrated Projects Notice of Rate Order No. WAPA-63  

  • [Federal Register Volume 59, Number 212 (Thursday, November 3, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-27306]
    
    
    [[Page Unknown]]
    
    [Federal Register: November 3, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    Western Area Power Administration
    
     
    
    Salt Lake City Area/Integrated Projects Notice of Rate Order No. 
    WAPA-63
    
    AGENCY: Western Area Power Administration, DOE.
    
    ACTION: Notice of Rate Order''Salt Lake City Area/Integrated Projects 
    (Integrated Projects) Firm Electric Service Rate Adjustment.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Notice is given of the confirmation and approval by the Deputy 
    Secretary of the Department of Energy (DOE) of Rate Order No. WAPA-63 
    and Rate Schedule SLIP-F5 placing firm power rates for capacity and 
    energy from the Integrated Projects of the Western Area Power 
    Administration (Western) into effect on an interim basis. The 
    provisional rates will remain in effect on an interim basis until the 
    Federal Energy Regulatory Commission (FERC) confirms, approves, and 
    places them into effect on a final basis or until they are replaced by 
    other rates.
        The provisional firm power rates to be effective from December 1, 
    1994, through November 30, 1999, consist of an energy charge of 8.90 
    mills per kilowatthour (mills/kWh) and a capacity charge of $3.83 per 
    kilowatt month (kW-month), which result in a composite rate of 20.17 
    mills/kWh. This is a 7.9-percent increase over the current energy 
    charge of 8.40 mills/kWh and the current capacity charge of $3.54/kW-
    month which results in a composite rate of 18.70 mills/kWh. A 
    comparison of existing and provisional rates follows: 
    
       Salt Lake City Area/Integrated Projects Comparison of Existing and   
                          Provisional Firm Power Rates                      
    ------------------------------------------------------------------------
                                                   Existing     Provisional 
                                                    rates          rates    
                                                (effective 10/ (effective 12/
                                                     92)            94)     
    ------------------------------------------------------------------------
    Firm Power Service Rate Schedule..........  SLIP-F4        SLIP-F5      
    Firm Capacity Charge ($/kW/month).........  $3.54          $3.83        
    Firm Energy Charge (mills/kWh)............  8.40           8.90         
    Composite Rate (mills/kWh)................  \1\18.70       20.17        
    ------------------------------------------------------------------------
    \1\The rates calculated at a 58.2-percent load factor can be expressed  
      as a Combined Rate of 16.72 mills/kWh.                                
    
    DATES: Rate Schedule SLIP-F5 will be placed into effect on an interim 
    basis on the first day of the first full billing period beginning on/or 
    after December 1, 1994, and will be in effect until FERC confirms, 
    approves, and places the rate schedule in effect on a final basis 
    through November 30, 1999, or until the rate schedule is superseded.
    
    FOR FURTHER INFORMATION CONTACT:
    
    Mr. Kenneth G. Maxey, Area Manager, Salt Lake City Area Office, Western 
    Area Power Administration, 275 East 200 South, Suite 475, Salt Lake 
    City, UT 84111, (801) 524-6372
    Ms. Deborah M. Linke, Chief, Rates and Statistics Branch, Western Area 
    Power Administration, P.O. Box 3402, Golden, CO 80401-0098, (303) 275-
    1618
    Mr. Joel Bladow, Assistant Administrator for Washington Liaison, 
    Western Area Power Administration, Room 8G-027, Forrestal Building, 
    1000 Independence Avenue SW., Washington, DC 20585-0001, (202) 586-5581
    
    SUPPLEMENTARY INFORMATION: By Amendment No. 3 to Delegation Order No. 
    0204-108, published November 10, 1993 (58 FR 59716), the Secretary of 
    Energy (Secretary) delegated (1) the authority to develop long-term 
    power and transmission rates on a nonexclusive basis to the 
    Administrator of Western; (2) the authority to confirm, approve, and 
    place such rates into effect on an interim basis to the Deputy 
    Secretary; and (3) the authority to confirm, approve, and place into 
    effect on a final basis, to remand, or to disapprove such rates to 
    FERC. Existing DOE procedures for public participation in power rate 
    adjustments (10 CFR Part 903) became effective on September 18, 1985 
    (50 FR 37835).
        These power rates are established pursuant to section 302(a) of the 
    DOE Organization Act, 42 U.S.C. 7152(a), through which the power 
    marketing functions of the Secretary of the Interior and the Bureau of 
    Reclamation (Reclamation) under the Reclamation Act of 1902, 43 U.S.C. 
    371 et seq., as amended and supplemented by subsequent enactments; 
    particularly section 9(c) of the Reclamation Project Act of 1939, 43 
    U.S.C. 485h(c); and other acts specifically applicable to the project 
    system involved, were transferred to and vested in the Secretary.
        The main issues raised at public meetings and in written comments 
    included (1) cost projections used in the Power Repayment Study (PRS), 
    (2) water depletion schedules assumed for future power projections, and 
    (3) estimated future prices for purchased power. Western has considered 
    all comments in preparation of the provisional rates.
        Rate Order No. WAPA-63, confirming, approving, and placing the 
    proposed Integrated Projects rate adjustment into effect on an interim 
    basis, is issued, and the new Rate Schedule SLIP-F5 will be promptly 
    submitted to FERC for confirmation and approval on a final basis.
    
        Issued in Washington, D.C. October 24, 1994.
    William H. White,
    Deputy Secretary.
    
    Order Confirming, Approving, and Placing the Salt Lake City Area/
    Integrated Projects Firm Power Service Rates Into Effect on an Interim 
    Basis
    
        In the Matter of Western Area Power Administration Rate 
    Adjustment for Salt Lake City Area/Integrated Projects
    October 24, 1994.
    [Rate Order No. WAPA-63]
        These power rates are established pursuant to section 302(a) of the 
    Department of Energy (DOE) Organization Act, 42 U.S.C. 7152(a), through 
    which the power marketing functions of the Secretary of the Interior 
    and the Bureau of Reclamation (Reclamation) under the Reclamation Act 
    of 1902, 43 U.S.C. 371 et seq., as amended and supplemented by 
    subsequent enactments, particularly section 9(c) of the Reclamation 
    Project Act of 1939, 43 U.S.C. 485h(c), and other acts specifically 
    applicable to the project system involved, were transferred to and 
    vested in the Secretary of Energy (Secretary).
        By Amendment No. 3 to Delegation Order No. 0204-108, published 
    November 10, 1993 (58 FR 59716), the Secretary delegated (1) the 
    authority to develop long-term power and transmission rates on a 
    nonexclusive basis to the Administrator of Western Area Power 
    Administration (Western); (2) the authority to confirm, approve, and 
    place such rates into effect on an interim basis to the Deputy 
    Secretary; and (3) the authority to confirm, approve, and place into 
    effect on a final basis, to remand, or to disapprove such rates to the 
    Federal Energy Regulatory Commission (FERC). Existing DOE procedures 
    for public participation in power rate adjustments (10 CFR Part 903) 
    became effective on September 18, 1985 (50 FR 37835).
    
    Acronyms and Definitions
    
        As used in this rate order, the following acronyms and definitions 
    apply:
        $/kW/month: Monthly charge for capacity (i.e., $ per kilowatt (kW) 
    per month).
        AF: Acre-foot. The amount of water necessary to cover 1 acre of 
    land to a depth of 1 foot.
        Basin Fund: That account in the U.S. Department of the Treasury, 
    established by the Colorado River Storage Project (CRSP) Act.
        Billing Demand: The greater of (1) the highest 30-minute demand 
    measured during the month up to, but not in excess of, the delivery 
    obligation under the power sales contract or (2) the contract rate of 
    delivery.
        Capacity Component: Part of a firm power rate; shown in the power 
    repayment study (PRS) as a dollar per kW per year charge. Billed on a 
    dollar per kW per month basis. Applied each billing period to each kW 
    which each contractor is entitled by contract.
        Categorical Exclusion: Characterizes an action which does not 
    individually or cumulatively have a significant effect on the human 
    environment and which has been found to have no such effect in 
    procedures adopted by a Federal agency and for which, therefore, 
    neither an environmental assessment nor an environmental impact 
    statement is required.
        CME: Capitalized movable equipment.
        Collbran: Collbran Project.
        CREDA: Colorado River Energy Distributors Association.
        CROD: Contract rate of delivery. Capacity the supplier of electric 
    service agrees to have available for delivery. It may or may not be 
    accompanied by energy.
        CRSM: Colorado River Simulation Model.
        CRSP: Colorado River Storage Project.
        CRSP Act: Act of April 11, 1956, ch. 203, 70 Stat. 105, as amended, 
    43 U.S.C. 620-620o.
        CWIP: Construction work in progress.
        Customer Brochure: A document prepared for public distribution 
    explaining the background of the rate proposal.
        Demand: The rate at which electric capacity is delivered to or by a 
    system over any designated period of time.
        DOE: U.S. Department of Energy.
        DOE Order RA 6120.2: An order dealing with power marketing 
    administration financial reporting.
        EA: Environmental assessment.
        EIS: Environmental impact statement.
        Energy Component: Part of a firm power rate; expressed in mills per 
    kilowatthour (kWh). Applied to each kWh made available to each 
    customer.
        Exception Criteria: An agreement between Reclamation and Western 
    setting forth conditions for operating the Glen Canyon Dam outside of 
    test flows and subsequent interim operating criteria, including system 
    regulation, emergency situations, and for the specific purpose of 
    avoiding high-cost replacement power purchases.
        FERC: Federal Energy Regulatory Commission.
        FPOD: Federal point of delivery.
        FY: Fiscal year.
        Glen Canyon Dam: The dam on the Colorado River which forms Lake 
    Powell.
        Glen Canyon Dam EIS: Glen Canyon Dam Environmental Impact 
    Statement.
        GCPA: Grand Canyon Protection Act of 1992.
        IDC: Interest during construction.
        Integrated Projects: The Salt Lake City Area/Integrated Projects, 
    which encompass the combined sales and resources of the CRSP, Collbran, 
    and Rio Grande Projects.
        Interior: U.S. Department of the Interior.
        kW: Kilowatt; 1,000 watts.
        kWh: Kilowatthour; the common unit of electric energy, equal to one 
    kW taken for a period of 1 hour.
        Load: The amount of capacity or energy delivered or required at any 
    specified point or points on a system. Load originates primarily with a 
    customer's energy-consuming equipment.
        M&I: Municipal and industrial.
        Mill: Unit of monetary value equal to .001 of a U.S. dollar; i.e., 
    1/10th of a cent. Used to express wholesale energy and composite 
    electric rates.
        Mills/kWh: Mills per kilowatthour.
        MW: Megawatt; 1,000 kW; 1,000,000 watts.
        NEPA: National Environmental Policy Act of 1969.
        OMB: Office of Management and Budget.
        O&M: Operation and maintenance. Pinch-Point: The FY in which the 
    level of the rate is set as dictated by a revenue requirement in some 
    future year to meet relatively large annual costs or to repay 
    investments which come due.
        PMA: Power marketing administration.
        PRS: Power repayment study.
        Reclamation: Bureau of Reclamation, U.S. Department of the 
    Interior.
        Regional Office: Bureau of Reclamation's Regional Office.
        RGP: Rio Grande Project.
        SLCA: Salt Lake City Area.
        SLCAO: Salt Lake City Area Office.
        Upper Basin States: Colorado, New Mexico, Utah, and Wyoming.
        UCRC: Upper Colorado River Commission.
        Watt: The electrical unit of power or rate of doing work. It is 
    analogous to horsepower or foot-pounds per minute of mechanical power. 
    One horsepower is equivalent to approximately 746 watts.
        Western: Western Area Power Administration, U.S. Department of 
    Energy.
        WSCC: Western Systems Coordinating Council.
    
    Effective Date
    
        The new rates will become effective on an interim basis on the 
    first day of the first full billing period beginning on or after 
    December 1, 1994, and will be in effect pending FERC's approval of them 
    or substitute rates on a final basis through November 30, 1999, or 
    until superseded.
    
    Public Notice and Comment
    
        The Procedures for Public Participation in Power and Transmission 
    Rate Adjustments and Extensions, 10 CFR Part 903, have been followed by 
    Western in the development of this firm power rate. The provisional 
    firm power rate represents an increase of more than 1 percent in total 
    Integrated Projects revenues; therefore, it is a major rate adjustment 
    as defined at 10 CFR Secs. 903.2(e) and 903.2(f)(1). The distinction 
    between a minor and a major rate adjustment is used only to determine 
    the public procedures for the rate adjustment.
        The following summarizes the steps Western took to ensure 
    involvement of interested parties in the rate process:
        1. A preliminary Federal Register notice (FRN), published July 1, 
    1993 (58 FR 35449), invited interested parties to participate in the 
    determination of whether an Integrated Projects' firm power rate 
    increase was necessary. Western also invited participation in deciding 
    the issues that should be addressed in the process.
        2. Several informal meetings were held between the publication of 
    the July 1, 1993, FRN and the beginning of the public rate adjustment 
    process. These meetings, involving personnel from Western, Reclamation, 
    and represen- tatives from organizations of interested parties, 
    produced many issue papers that identified and discussed the items 
    which should be considered in a firm power rate adjustment. Agreement 
    as to how to approach many of the issues was reached during this time, 
    considerably reducing the number of unresolved issues and easing the 
    later formal public process.
        3. On December 27, 1993, letters were mailed from Western's 
    Loveland, Phoenix, and Salt Lake City Area Offices to all Integrated 
    Projects customers and other interested parties announcing an informal 
    public meeting to be held on January 31, 1994.
        4. At the informal meeting held on January 31, 1994, Western and 
    Reclamation representatives explained the need for a rate increase and 
    answered questions.
        5. An FRN was published on April 21, 1994 (59 FR 19008), officially 
    announc- ing the proposed firm-power rate adjustment, initiating the 
    public consultation and comment period, announcing the public 
    information and public comment forums, and presenting procedures for 
    public participation.
        6. On April 22, 1994, a rate announcement package was mailed from 
    Western's Salt Lake City Area Office to all Integrated Projects 
    customers and other interested parties announcing the publication of 
    the FRN of April 21, 1994, and the beginning of the formal public 
    process to adjust firm power rates. The package contained (1) a letter 
    announcing the upcoming public information and comment forums, (2) a 
    copy of the April 21 FRN, and (3) a copy of the April 1994 Integrated 
    Projects Firm Power Rate Adjustment brochure. Rate announcement 
    packages were mailed to customers served by Western's Loveland and 
    Phoenix Area Offices on April 25, 1994.
        7. At the public information forum held on May 24, 1994, Western 
    and Reclamation representatives explained the need for the rate 
    increase in greater detail and answered questions.
        8. The comment forum was held on June 30, 1994, to give the public 
    an opportunity to comment for the record. Four persons representing 
    customers and customer groups made oral comments.
        9. Nine comment letters were received during the 97-day 
    consultation and comment period. The consultation and comment period 
    was originally scheduled to end on July 20, 1994. A letter was sent to 
    all interested parties from the SLCAO on July 19, 1994, stating that 
    Western would continue to accept written comments through July 27, 
    1994. Letters were mailed from the Loveland and Phoenix Area Offices on 
    July 20, 1994. All comments submitted by the end of the comment period 
    have been considered in the preparation of this rate order.
    
    Project History
    
        The Integrated Projects consist of the CRSP and the Rio Grande and 
    Collbran Projects. The projects were integrated for marketing and 
    ratemaking purposes on October 1, 1987. The goals of integration were 
    to increase marketable resources, simplify contract and rate 
    development and project administration, assure repayment of Collbran 
    and Rio Grande Projects' costs, and create a common rate. The projects 
    maintain their individual identities for financial accounting and 
    repayment purposes, but their revenue requirements are integrated into 
    one PRS for ratemaking.
    
    Power Repayment Studies
    
        PRSs are prepared each FY to determine if power revenues will be 
    sufficient to pay, within the prescribed time periods, all costs 
    assigned to power. Repayment criteria are based on law, policies, 
    authorizing legislation, and DOE Order RA 6120.2.
    
    Existing and Provisional Rates
    
        A comparison of the existing and provisional rates follows:
    
       Salt Lake City Area Integrated Projects Comparison of Existing and   
                          Provisional Firm Power Rates                      
    ------------------------------------------------------------------------
                                                   Existing     Provisional 
                                                    rates          rates    
                                                (effective 10/ (effective 12/
                                                     92)            94)     
    ------------------------------------------------------------------------
    Firm power service rate schedule..........  SLIP-F4        SLIP-F5      
    Firm capacity charge ($/kW/month).........  $3.54          $3.83        
    Firm energy charge (mills/kWh)............  8.40           8.90         
    Composite rate (mills/kWh)................  18.70\1\       20.17        
    ------------------------------------------------------------------------
    \1\The rates calculated at a 58.2-percent load factor can be expressed  
      as a combined rate of 16.72 mills/kWh.                                
    
    Certification of Rate
    
        Western's Administrator has certified that the Integrated Projects 
    firm power rate placed into effect on an interim basis herein is the 
    lowest possible consistent with sound business principles. The rate has 
    been developed in accordance with agency administrative policies and 
    applicable laws.
    
    Discussion
    
        Many factors influenced this rate adjustment. The items having an 
    impact upon the proposed Integrated Projects firm power rates are 
    summarized in the table below. Because rates must earn sufficient 
    revenues to pay for estimated future costs, the table compares the 
    change in the average annual projections used in the FY 1991 Rate Order 
    PRS (which set the rate effective October 1, 1992) and the ratesetting 
    PRS prepared for this rate adjustment. 
    
        Major Factors Affecting the Integrated Projects' Firm Power Rate    
    ------------------------------------------------------------------------
                                                    Change in               
                                                     average                
                                                     annual       Estimated 
                       Event                         revenue     rate effect
                                                   requirement   (mills/kWh)
                                                   ($000,000)               
    ------------------------------------------------------------------------
    Increase in Colorado River Storage Project                              
     (CRSP) Transmission and Other Miscellaneous                            
     Revenues: primarily, compensation for new                              
     Phase-Shifter services (for Western System                             
     Coordinating Council loop-flow mitigation).         $-2.6         -0.33
    Increase in CRSP Operation & Maintenance                                
     (O&M) Expense: $2.8 million per year due to                            
     inclusion of CME interest (inadvertently                               
     omitted from current rate); Remainder due                              
     to shifting of field crews from                                        
     construction to maintenance work...........           8.2          1.05
    Increase in Small Project O&M Expense: Rio                              
     Grande Project is one of Western's oldest                              
     projects, and O&M increases with age;                                  
     Collbran has many small irrigation dams                                
     needing repair.............................           1.1          0.14
    Increase in Purchased Power and Transmission                            
     Expense: The environmentally-related flow                              
     restrictions already in place at CRSP                                  
     powerplants require Western to purchase                                
     additional power to meet contractual                                   
     delivery obligations.......................           1.6          0.20
    $51.2 million in historical environmental                               
     expenses made nonreimbursable by Grand                                 
     Canyon Protection Act (plus $9.1 million                               
     associated with deferred interest expense);                            
     Applied to outstanding deficits............          -0.5         -0.06
    Passage of Grand Canyon Protection Act made                             
     certain future environmental costs                                     
     nonreimbursable............................          -1.0         -0.13
    Increase in Interest on Project Investment:                             
     The increase in power investment and unpaid                            
     deficits since the October 1992 rate                                   
     adjustment resulted in an increase in                                  
     annual interest due........................           2.1          0.27
    Increase in Project Additions and                                       
     Replacements: As noted on page 13 of Rate                              
     Brochure, $80.5 million was omitted from                               
     CWIP in the October 1992 rate adjustment...           1.2          0.15
    Increase in aid to CRSP irrigation and                                  
     participating projects: Investment is very                             
     similar to October 1992 rate adjustment;                               
     however, there are 63 total years to pay                               
     for the investment, rather than the 65                                 
     years used previously since both studies                               
     have the pinch-point year of 2057. The                                 
     change in the divisor results in the annual                            
     increase...................................           1.4          0.18
                                                 ---------------------------
        Totals..................................         $11.5          1.47
    ------------------------------------------------------------------------
    
        The existing and proposed revenue requirements for the Integrated 
    Projects are as follows: 
    
       Integrated Projects Average Annual Firm-Power Revenue Requirements   
    ------------------------------------------------------------------------
                                                         Estimated average  
                                                      annual FY 1995-99 firm
                                                       power revenue ($000) 
                                                     -----------------------
                                                        SLIP-F4     SLIP-F5 
    ------------------------------------------------------------------------
    Firm power revenue..............................  \1\$109,26            
                                                               5  \2\$122,41
                                                                           3
    ------------------------------------------------------------------------
    \1\From FY 1991 Rate Order PRS.                                         
    \2\From Ratesetting PRS.                                                
    
        The rate increase is necessary to satisfy the cost-recovery 
    criteria set forth in DOE Order No. RA 6120.2. This rate schedule, 
    which will be effective on an interim basis beginning December 1, 1994, 
    replaces Rate Schedule SLIP/F4 which FERC approved through September 
    30, 1996 at 62 FERC 61,159 (February 18, 1993).
    
    Statement of Revenue and Related Expenses
    
        The following table provides a summary of revenue and expense data 
    through the 5-year proposed rate approval period. 
    
    Salt Lake City Area/Integrated Projects Comparison of 5-Year Rate Period
                         Revenues and Expenses ($1,000)                     
    ------------------------------------------------------------------------
                                     Ratesetting  FY 1991 rate              
               Revenues               PRS 1995-     order PRS    Difference 
                                        1999       1995-1999                
    ------------------------------------------------------------------------
    Revenue Distribution:                                                   
      O&M.........................      $237,483      $218,540       $18,943
      Environmental...............        19,295        37,223       -17,928
      Net purchased power\2\......           972        -1,953         2,925
      Transmission................        35,785        31,695         4,090
      Interest....................       229,029       188,103        40,926
      Miscellaneous expenses\3\...        45,976        20,430        25,546
      Investment repayment........       102,255        99,189         3,066
                                   -----------------------------------------
        Total\4\..................    \1\670,795    \5\593,227    \6\77,568 
    ------------------------------------------------------------------------
    \1\To be comparable with the FY 1991 Rate order PRS, the ratesetting    
      PRS' ``Other Miscellaneous Revenues'' (from sales of surplus off-peak 
      energy) were deducted from the total revenues and were combined with  
      total purchased power expense.                                        
    \2\Net Purchased Power Expenses (Ibid.). Negative net purchase power    
      expense figures imply surplus sales in excess of total purchase power 
      expenses. Likewise, positive net purchase power expense figures imply 
      total purchase power expenses in excess of total power sales.         
    \3\Interest on undepreciated CME, annual liability for the Civil Service
      Retirement System, and annual gross power-related requirements for the
      Collbran, Provo River, Rio Grande, and Seedskadee Projects.           
    \4\Includes repayment of capitalized deficits.                          
    \5\Does not equal Total Revenues due to rounding.                       
    \6\Ibid.                                                                
    
    Basis for Rate Development
    
        The provisional Integrated Projects rate was designed to continue 
    to maintain an approximate 50/50 split between revenue earned from 
    demand charges and that earned from energy charges. The cost to 
    individual customers will vary because of differences in the amounts of 
    capacity and energy they purchase from the Integrated Projects.
        The provisional rate contains a $3.83/kW/month firm-capacity charge 
    and an 8.90 mills/kWh firm-energy charge in FY 1995. The necessary 
    composite rate is 20.17 mills/kWh, which is an increase of 7.9 percent 
    above the existing rate. The rate terminates on November 30, 1999.
    
    Comments
    
        During the 97-day comment period, Western received nine letters 
    commenting on the rate adjustment. One letter was received after the 
    close of the comment period. Additionally, four persons commented 
    during the June 30, 1994, public comment forum. All comments received 
    by the end of the comment period were reviewed and considered in the 
    preparation of this rate order. Written comments were received before 
    the comment deadline from the following sources:
    
    Bountiful City Light and Power (Utah)
    Bridger Valley Electric Association (Wyoming)
    Colorado River Energy Distributors Association (Arizona, Colorado, 
    Nevada, New Mexico, Utah, and Wyoming)
    Energy Strategies, Inc. (Utah)
    Garkane Power Association, Inc. (Arizona and Utah)
    Intermountain Consumer Power Association (Nevada and Utah)
    Irrigation and Electrical Districts Association of Arizona (Arizona)
    Upper Colorado River Commission (Colorado, New Mexico, Utah, and 
    Wyoming)
    Utah Municipal Power Agency (Utah)
    
        Representatives of the following organizations made oral comments:
    
        Colorado River Energy Distributors Association (Arizona, 
    Colorado, Nevada, New Mexico, Utah, and Wyoming)
        Intermountain Consumer Power Association (Nevada and Utah)
        Irrigation and Electrical Districts Association of Arizona 
    (Arizona)
        Platte River Power Authority (Colorado)
    
        Most of the comments received at the public meetings and in 
    correspondence dealt with cost, purchased power, and water depletion 
    projections.
        The comments and responses, paraphrased for brevity when it does 
    not affect the meaning of the statement(s), are discussed below. Direct 
    quotes from comment letters are used for clarification where necessary.
        The issues discussed are: (1) Depletion-related issues, (2) 
    purchased power expense, (3) future flow restrictions at Glen Canyon 
    Dam, (4) O&M-related issues, (5) construction-related projections, (6) 
    environmentally-related expenses, (7) miscellaneous comments, and (8) 
    issue paper resolution.
    1. Depletion-Related Issues
        Extensive comments were made regarding the deferred recognition of 
    water depletions for water projects in the Colorado River Basin after 
    FY 2010. Western's responses are listed sequentially:
        a. Comment: Western is being guided solely by RA 6120.2 in the 
    rate-setting process without paying sufficient attention to the CRSP 
    Act of 1956 and other relevant legislation. The rate does not 
    accurately reflect the intent of the CRSP Act, which is to produce 
    rates that result in full repayment of the power system costs.
        Response: Western disagrees. Western complies with requirements of 
    the CRSP Act of 1956, other relevant legislation, and DOE Order RA 
    6120.2 in assuring repayment of all CRSP costs assigned to power. 
    Legislation takes precedence when there is conflict with DOE Order RA 
    6120.2.
        Treatment of depletions in the same manner has been approved by 
    FERC twice prior to the present rate adjustment. Two of FERC's criteria 
    for rate approval are whether the proposed rate will repay all 
    obligations assigned to power in full and on time consistent with 
    requirements of the CRSP Act and whether the methodology which achieves 
    this result is in compliance with DOE Order RA 6120.2. The requested FY 
    1995 rate adjustment meets these criteria and satisfies all repayment 
    requirements.
        b. Comment: If power rates are set without providing for future 
    depletions, it will affect Upper Basin development under the (Colorado 
    River and Upper Colorado River Basin) compacts. Every time someone 
    wants to build a project or open a business that will deplete water, 
    the power rates will have to go up if those increased depletions have 
    not already been factored into the rates.
        Can full repayment be truly represented by rates derived assuming 
    water is available for release through powerplants when that water will 
    not be available because of depletions by the Upper Division States 
    above the powerplants?
        Response: Total depletions forecasted by the Basin States for the 
    use of Colorado River water have been included in the proposed rate. 
    The water has been allocated by compacts for use by the Upper Basin 
    States. Furthermore, Western is obligated to assure that funds are 
    available on schedule to meet repayment requirements regardless of 
    depletion schedules.
        In its proposed treatment (deferral) of uncertain depletions, 
    Western assumes that greater amounts of Colorado River water will be 
    available for release through CRSP powerplants than would be suggested 
    by current rapid-growth forecasts of water development projects and 
    their associated depletions.
        Western's experience has been that out-year depletion estimates are 
    subject to frequent revision. It is reasonable, therefore, to give more 
    weight to near-term projections. Western prepares an annual PRS for 
    every project to assure that repayment is proceeding satisfacto- rily. 
    Thus, there will be many future opportunities to revise the Integrated 
    Projects rate appropriately as the near-term projections are changed 
    and more accurate long-term estimates are made available.
        Western has determined that depletions affect the firm power rate, 
    at most, by 0.32 mills/kWh (composite). The impact is small enough so 
    that power rates could (and would) be adjusted to assure full 
    repayment, if more rapid depletions take place in the Upper Basin 
    States. It is not likely that this small impact on power rates would 
    constrain water depletions.
        c. Comment: By its own terms the 1983 Agreement between Reclamation 
    and Western does not apply to State and private projects or 
    developments and that the agreement reveals the parties' intent to use 
    full depletion levels in setting rates under the terms of the 
    Agreement.
        Response: Western disagrees that the intent of the 1983 Agreement 
    was for Western to use ``full'' (or ultimate) depletion levels in 
    setting rates. Rather, a provision of the agreement that addresses 
    depletions only requires that water depletion schedules used for power 
    repayment studies ``. . . be consistent with construction schedules for 
    participating projects.''
        Western agrees that provisions of the 1983 Agreement between 
    Western and Reclamation did not explicitly address State and private 
    projects or developments. In defining a ``reasonable expectation 
    standard,'' the 1983 Agreement establishes necessary steps by 
    Reclamation to demonstrate the potential for construction of future 
    Federal participating projects before the costs of these projects would 
    be included in the ratesetting years. This reasonable expectation 
    standard has been applied to the future development of all water 
    development projects for ratesetting purposes by Western in setting the 
    lowest possible rates consistent with sound business principles.
        Therefore, Western has included total depletions forecasted by the 
    Upper Basin States for the use of Colorado River water for all 
    projects, with deferral of less-certain water developments (depletions) 
    beyond the ratesetting period in the proposed rate. Future rate 
    adjustments will allow for movement of depletions into the rate- 
    setting years.
        d. Comment: Western arbitrarily suppressed depletions from 2010 
    through 2090 only justified by the fact that such a method of 
    suppression (capping) was utilized in the 1990 study and did so without 
    adequate consultation with Reclamation.
        Response: The decision by Western to defer uncertain depletions 
    beyond the ratesetting period is not arbitrary. In the 1990 rate 
    process, Western gave considerable attention to the reasonableness of 
    the then-proposed depletion deferral and to the associated rate effect 
    when applied. Further, Western has given renewed and height- ened 
    attention to the treatment of depletions in the proposed rate through 
    preparation of numerous issue papers, informal discussions with both 
    customer and water user representatives, and in Western's April 1994 
    rate brochure.
        Figure 1, on page 12-5 of the rate brochure, shows that Western 
    presently assumes full development (full depletions) of all Upper Basin 
    water projects by FY 2090.
        Projects with uncertain schedules have been placed in the PRS so 
    that they do not impact the rate at this time, in accordance with 
    Western's practice to set the lowest possible rate consistent with 
    sound business principles.
        Western also disagrees with the claim that inadequate consultation 
    occurred with Reclamation in the past on this deferral treatment. 
    Reclamation, along with other interested parties, has either 
    participated in or has attended many of the public forums scheduled in 
    the development of all Integrated Projects rate proposals. In these 
    public forums, Western has detailed the components of the rate 
    adjustment, including the treatment of depletions. Reclamation and 
    interested parties have been and will continue to be afforded ample 
    notice and opportunity to comment on future rate proposals.
        e. Comment: Five comments said: DOE RA 6120.2 seems to require the 
    use of operation studies based on historical streamflows including 
    hydrologic data current to within 5 years.
        Response: Western believes that it is in compliance with DOE RA 
    6120.2. This requirement is valid for most projects. However, 
    exceptions, as discussed in DOE RA 6120.2, Section 10.e.(4), are 
    provided for those projects which are anticipated to have extensive 
    water development in the future. CRSP operation studies are based on 
    historic streamflows, which are then reduced by projected water 
    depletions supplied by the Upper Basin States and modified by 
    Reclamation.
        f. Comment: Western suggests that its departure from the 1990 
    depletion schedule represents better data than utilized by Reclamation 
    in its energy and capacity studies.
        Response: Both Reclamation and UCRC staff have told Western infor- 
    mally that the depletion schedule used in this process is a more 
    accurate reflection of the current situation than the earlier ``Energy 
    and Capacity Studies'' which was available when the ratesetting PRS was 
    prepared.
        g. Comment: The 1990 cap at 2010 resulted in an approximate 11-
    percent reduction of Basin States' depletions and an artificially low 
    power rate. The proposed super-imposition of a 1990 mentality beginning 
    in 2010 to a substantially revised 1992 unofficial depletion schedule 
    results in excess of 20-percent reduction of depletions and does not 
    even fully recognize the future depletions of projects currently under 
    construction.
        Response: Western agrees that the deferral of some estimated deple- 
    tion effects until 2060 suggests a significant (20-percent) reduction 
    from the 1992 depletion schedule contained in the CRSM demand data. 
    Western believes there should be greater certainty of development 
    regarding this 20-percent prior to including the associated reduction 
    in hydrogeneration in the PRS in a way that affects the firm power 
    rates. Also, Western agrees that its deferral postpones future 
    depletions of projects currently under construction, based on the 
    principles of the 1983 agreement. Again, because the timing of the 
    development of the associated consumptive use is uncertain, Western 
    chooses to not include future depletions within the ratesetting years. 
    As more current information is supplied by the UCRC to Reclamation, 
    Western will apply the ``reasonable expectation'' standard to these 
    updated depletions.
        h. Comment: Western did not use the depletion schedule dated July 
    1994 which was received in draft form in April 1994.
        Response: Western was provided a draft work-in-progress depletion 
    schedule by UCRC representatives in April 1994. This latest unofficial 
    schedule demonstrated a reduced and delayed schedule for development of 
    Upper Basin projects. However, the schedule had yet to be approved by 
    the Basin States and, once received by Reclamation, would still have 
    required considerable work by Reclamation staff to modify depletion 
    (demand) data used by the CRSM. In addition, subsequent analysis by 
    Western's power resources and rates staff would have taken considerable 
    time and effort before new information could be verified and supported 
    for inclusion in any revised PRS for this proposed rate process. For 
    example, the final PRS used for the April 1994 rate brochure was 
    created in March of 1994. Its power projections were the end result of 
    several months of work by Western and Reclamation resources staff. An 
    official depletion schedule ready for use in July of 1994 would have 
    delayed the public process for the current rate adjustment by several 
    additional months.
        Western is responsible for seeing that the Integrated Projects earn 
    sufficient revenues to pay all of their obligations on time. Such a 
    lengthy delay in implementing the rate adjustment would have resulted 
    in increased interest cost to customers, lost revenues, and, as a 
    result, higher firm power rates.
        Western has assured UCRC that when official depletion information 
    is available, has been incorporated into Reclamation's CRSM data files, 
    and there is a common understanding of the reasonable certainty of 
    future water projects, the associated generation effects will be 
    weighed and a decision made by Western regarding their inclusion in any 
    future PRS.
        i. Comment: The attorney for a customer stated:
        . . . the treatment of depletions in this rate case has nothing to 
    do with the water rights of the Upper Basin States. Nor does it have 
    anything to do with how those rights will be exercised in the future. 
    Western has no power over the water rights of the Upper Basin States. 
    Conversely, the power users should not be punished because of delays in 
    Upper Basin water use development and fears of Upper Basin water users 
    that such development may ultimately not occur.
        Response: Western agrees with this comment.
    2. Purchased Power Expense
        Four large customer organizations all commented extensively on 
    purchased power expense:
        a. Comment: A customer organization stated:
        The assumed lower prices for surplus energy sales are, in fact, at 
    odds with recent experience for the SLCA/IP.
        It is clear that experience does not support Western's pricing 
    assumptions, which were based on combining various pricing and cost 
    data in an inconsistent and somewhat arbitrary fashion. (The commentor) 
    recommends that Western modify its pricing assumptions by setting 
    prices for surplus sales at the same levels as those used for 
    purchases.
        Response: Western agrees, in part, with comments that assumed 
    nonfirm surplus sales pricing in the estimation of future-year net 
    purchased power expenses does not reflect an extension of historic 
    pricing trends. This fact is supported in documentation prepared by 
    Western on the methodology and assumptions developed in previous rate 
    proceedings and consistently applied again in this proposed rate 
    adjustment. The imposed restrictions at Glen Canyon Dam have caused 
    Western to sell off-peak surplus energy. The impact of these sales is 
    based upon the market conditions. Western has explained that the basis 
    for assumptions of future surplus sales pricing is based upon 
    consideration of the potential market conditions. Western assumes that 
    there will be a need to dispose of limited onpeak surpluses in southern 
    markets, which will mean competing against low-cost sales from the 
    Navajo Generating Station. Western will also try to sell significant 
    surpluses in northern markets, competing against low-cost sales from 
    regional northern utilities. Certain general conclusions may be drawn: 
    (1) average nonfirm surplus energy prices, both offpeak and onpeak, 
    will be less than historic conditions, this also implies that period 
    pricing (onpeak or offpeak) will be less than recent experience, (2) 
    historic pricing differentials, onpeak versus offpeak, winter versus 
    summer season, will continue, and (3) Western's hourly modeling of 
    constrained operations at Glen Canyon is reasonable.
        Though the method developed is believed to be a reasonable tool for 
    forecasting future surplus sales pricing, Western acknowledges that 
    some merit exists in comments that suggest a closer link to recent 
    historic trends is reasonable. Western will continue to refine the 
    methods for forecasting future market conditions, both purchases and 
    surplus sales, and will continue to give greater weight to recent 
    historic pricing trends in future pricing projections.
        Western disagrees with the comment which suggests that surplus 
    sales and purchase pricing should be identical, without consideration 
    of the nature of the constraint condition at Glen Canyon. The methods 
    developed by Western for assessment of conditions with and without 
    interim release constraints at Glen Canyon currently predict (a) that 
    higher, but acceptable, average purchase prices will result in the near 
    future from deliveries under several long-term purchase agreements and 
    (b) lower average surplus sale prices will occur due to significant 
    ``forced sales'' during offpeak and shoulder onpeak hours. However, 
    should additional operation experience suggest modification to this 
    base assumption, Western will consider future improvements in the 
    methods used.
        b. Comment: Western applied the hourly modeling of net purchased 
    power expense to only 3 years. The other years between and beyond the 3 
    years modeled were estimated based on a regression analysis of the 3 
    years' results . . . regression analysis using three data points to 
    interpolate and extrapolate results may be unreliable and is certainly 
    less than ideal. (The commentor) recommends that the hourly model be 
    used to calculate annual net expense at least through the year 2002, 
    when the recovery of the hydrosystem and increases in firm load . . . 
    have stabilized.
        Response: Western disagrees with the suggestion that additional 
    years of hourly modeling in its current form would significantly 
    improve the reliability of forecasted net purchase power expenses.
        The methodology developed by Western to forecast the net purchase 
    power expense considers several significant variables such as hourly 
    firm load and available hourly hydrogeneration in determination of 
    hourly deficits or surpluses. The method then considers seasonal 
    variation in purchase and surplus sales pricing structures in 
    estimation of the net purchase power expense. Given the simplifying 
    assumptions made in the methods, Western recognizes a significant 
    correlation between deficit (or surplus) hydrogeneration and the 
    associated net purchase power expense.
        In balancing the limited time required to complete the analysis and 
    the precision required for the net expense estimate, Western determined 
    that modeling all hours within each month for 3 years (i.e., 36 months) 
    would be adequate and that hourly modeling for additional years would 
    not significantly improve the reliability of the forecasted net 
    purchase power expense.
        Western continues to support the general application of these 
    methods to express the causal relationship between deficit (or surplus) 
    hydrogeneration and annual net purchase power expenses. However, 
    Western acknowledges that some future modifications may be beneficial, 
    such as (1) additional refinements of the model, (2) validation of key 
    assumptions, and (3) application of refined methods and assumptions to 
    additional future periods (i.e., months, years) to increase the sample 
    size. Such changes will be considered in future net purchase power 
    expense forecasts.
        c. Comment: A large customer organization says that it has been 
    unable to understand or replicate Western's results.
        Response: Western has made a conscientious effort to provide all of 
    the information needed to develop the purchased power expense analysis 
    in a timely manner. Western's staff has provided explanations to 
    customers and their consultants and are available and willing to 
    provide additional clarification as needed.
    3. Future Flow Restrictions at Glen Canyon Dam
        a. Comment: A large customer organization expressed concern that 
    Western has overstated revenues of $3 to $8 million per year from 
    short-term capacity sales through 2004.
        Response: It is improbable that flows restricted for environmental 
    reasons will ever again provide enough firm power from the Glen Canyon 
    Unit to reach levels used in past power projections. Western does not 
    know which of many possible flow regimes will finally be imposed at the 
    Glen Canyon Unit. The treatment of short-term sales has been consistent 
    with the firm power assumptions. Therefore, it is impossible to modify 
    power projections for the proposed rate adjustment to recognize the 
    reduced power output. The only course of action Western is able to 
    follow is to stay with historic power projection figures, using the 
    methodology already used in previous processes, until the Glen Canyon 
    regime is finally determined.
        Western will evaluate the firm power rate then in place when the 
    new flow regimes from the Glen Canyon Dam are decided. If it is needed, 
    a firm power rate adjustment will be proposed then.
        b. Comment: An organization of several customers stated: While it 
    is understood that a degree of uncertainty surrounds the exact level of 
    flows at Glen Canyon, Western should conduct a sensitivity analysis 
    predicated on the alternative flow assumptions identified in the 
    Operation of Glen Canyon Dam Environmental Impact Statement. Such 
    sensitivity analysis (sic) would give customers a range of possible 
    replacement power costs.
        Response: Western has done extensive analyses of the power and rate 
    impact of every flow regime identified for study in the GCD-EIS. 
    Detailed descriptions of the studies and their results are reported in 
    the draft GCD-EIS, and will be contained in the final GCD-EIS when it 
    is published.
        In the meantime, Western is specifically required, by law and by 
    regulation, to use known or statistically probable estimates of future 
    activity in creating rates. The level of uncertainty still existing 
    with the GCD-EIS prevents the use of any of its data at this time. As 
    is noted above, when a decision about environmentally related flows 
    through Glen Canyon Dam is made, a revised PRS will be prepared, and a 
    new rate will be proposed, if needed.
    4. O&M-Related Issues
        a. Western O&M: CREDA signed an agreement with Western and 
    Reclamation dated September 24, 1992, which states:
        Western shall utilize the Work Program Information made available 
    to its Customers by Western and Reclamation (including adjustments 
    thereof which may result from reviews, from internal corrections or the 
    dispute resolution process provided for in these Joint Procedures but 
    excluding the costs of future transmission system additions in a 
    Planning Year or Out Year which are conceptual in nature), to prepare 
    the power repayment studies upon which it relies to promulgate any 
    interim or final rates proposed or adopted for SLCAIP firm power or 
    transmission services.
        Several customers and their member organizations are concerned 
    about the implementation of the 1992 Agreement.
        (1) Comment: (One commentor) continues to be concerned with 
    Western's inconsistent use of budgeted information in the preparation 
    of the PRS . . . (the commentor) has been some-what frustrated in its 
    attempts in this rate adjustment process to reconcile certain 
    information used in the 1994 Rate Brochure PRS with the information 
    previously provided in the Work Program review process.
        Response: The FY 1995 Work Program is merely a copy of the proposed 
    FY 1994 Congressional Budget Submission. It was used as the starting 
    point in planning expenditures for the FY 1995 congressional budget.
        CREDA's September 1992 agreement with Western and Reclamation 
    allows power customers to have meaningful input to the new 
    congressional budget. However, this work program document is prepared 
    too early in the planning process for either customers or Western to 
    say that no further changes will be made. Western feels that the timing 
    and use of documents stated in the agreement should be revisited. 
    Western is willing to continue to work with the customers in improving 
    the budget and work plan review process in the future.
        To illustrate the process, the transformation of the FY 1995 Work 
    Program into the final FY 1995 Budget is outlined below:
        (a) (The commentor) reviewed the FY 1995 Work Program and had 
    opportunity to make suggested changes.
        (b) The revised FY 1995 Work Program became the FY 1995 Internal 
    Review Budget. At this point, more changes were made. Those changes 
    then were reviewed by Western. Further changes, usually a lowering of 
    spending projections, are common in this stage of budget preparation.
        (c) The FY 1995 Internal Review Budget was then sent to Washington 
    to be approved by DOE. There are usually reductions in spending 
    estimates at this stage, as well, dictated by DOE's spending 
    priorities. The DOE-approved budget was called the FY 1995 OMB Budget 
    Request and was sent to that agency for review and approval. Any 
    changes were then incorporated into a document called the FY 1995 
    Congressional Budget Submission.
        (d) Finally, the FY 1995 Congressional Budget Submission went 
    before Congress, where any final changes desired by the legislative 
    branch of Government were made. Only after it was approved by Congress 
    after public debate was the final FY 1995 Budget determined.
        The FY 1994 Congressional Budget Submission was officially sent to 
    Congress in January 1993. When the April 1994 rate brochure PRSs were 
    being prepared, the data in the FY 1994 Congressional Budget 
    Submission/1995 Work Program was already more than 2 years old (having 
    begun as the FY 1994 Work Program in early 1992). Because of this 
    timing, most of the information was outdated.
        Western had completed turning the FY 1995 Work Program into the FY 
    1995 Congressional Budget Submission by that time. As is usually the 
    case, some of the planned expenditures had been deleted in the process. 
    Further, because of extra impetus to keep costs down, a Western-wide 
    decision was made in which O&M costs would be allowed to rise only 2-
    percent per year between FYs 1994 and 1996.
        In keeping with Western's policy to set rates at the lowest 
    possible level consistent with sound business principles, Western used 
    data from the lower-cost (and more current) FY 1995 Congressional 
    Budget Submission rather than that in the customer-reviewed FY 1995 
    Work Program in the Rate Brochure PRS.
        When Reclamation, Western, and CREDA entered into the September 
    1992 agreement, the parties did not anticipate that expenditure plans 
    would change significantly between the Work Program review and the 
    congressional budget submission. Events have proved otherwise.
    
             Comparison of FY 1995 Work Plan With FY 1995 Congressional Budget Submission O&M Expenses $000         
    ----------------------------------------------------------------------------------------------------------------
                                                     FY 1994    FY 1995    FY 1996    FY 1997    FY 1998    Totals  
    ----------------------------------------------------------------------------------------------------------------
    1995 Work Plan:                                                                                                 
      Reclamation.................................    $17,898    $18,408    $17,403    $17,884    $16,739    $88,332
      Western.....................................     30,894     30,379     30,743     31,481     33,905   157,402 
                                                   -----------------------------------------------------------------
      Total.......................................     48,792     48,787     48,146     49,365     50,644    245,734
    1995 Budget:                                                                                                    
      Reclamation.................................    $15,856    $15,925    $16,041    $16,262    $16,631    $80,715
      Western.....................................     29,307     27,635     27,971     28,724     28,984   142,621 
                                                   -----------------------------------------------------------------
        Total.....................................     45,163     43,560     44,012     44,986     45,615   223,336 
                                                   -----------------------------------------------------------------
          Decreased Cost to Customers.............     -3,629     -5,227     -4,134     -4,379     -5,029   -22,398 
    ----------------------------------------------------------------------------------------------------------------
    
        (2) Comment: Two comments expressed concern that: Western's 
    projected O&M expenses for 1994 are more than 25-percent higher than 
    actual O&M expenses in 1993 and more than 20-percent higher than the 
    1994 O&M expenses included in the 1995 Work Program documents.
        Response: Western has been unable to duplicate the analysis in this 
    comment. Some of the figures in the commentor's table are incorrect. 
    This gives the impression of a problem where Western believes none 
    exists. Most significantly, Western's actual FY 1993 CRSP O&M expense 
    of $17.964 million shown in the commentor's tables is incorrect. The 
    proper amount, from the Results of Operations (financial statements) as 
    shown below, is $21.418 million. This should be the basis for the 
    commentor's percentage calculations.
        Below is a table comparing the table submitted by the commentors, 
    the FY 1995 Work Program, and the amounts used in the PRS. 
    
                                               Western's CRSP O&M ($000)                                            
    ----------------------------------------------------------------------------------------------------------------
                                                                 1993     1994     1995     1996     1997      1998 
    ----------------------------------------------------------------------------------------------------------------
    Commentor's Table \1\.....................................   17,964   18,628   20,888   21,070   21,437   21,923
    Annual Change (%).........................................        0        4       12        1        2        2
    FY 1995 Work Program\2\...................................   26,449   24,555   23,898   24,202   24,882   27,245
    Annual Change (%).........................................        0       -7       -3        1        3       10
    Rate Brochure PRS \3\.....................................   21,418   22,530   20,888   21,070   21,437   21,993
    Annual Change (%).........................................        0        5       -7        1        2       3 
    ----------------------------------------------------------------------------------------------------------------
    \1\ From comment letter dated July 27, 1994; source of data identified as FY 1995 Work Program.                 
    \2\ From FY 1995 Work Program (i.e., FY Congressional Budget submission), according to CRSP records.            
    \3\ Using the FY 1995 Congressional Budget submission.                                                          
    
        The average annual growth rate in the rate brochure PRS from 1993 
    through 1996 is a negative 0.33 percent. This is considerably below the 
    2-percent maximum annual growth rate which is Western's goal.
    5. Reclamation O&M
        a. Comment: Reclamation explained the increase in Regional Office 
    expense in 1995 O&M expenses over the level shown in the 1995 Work 
    Program (which was $564,000) as the inclusion of the Dolores Project 
    O&M expense. The O&M expenses for the Dolores Project are shown in the 
    1995 Work Program as $301,000 for 1995, leaving $263,000 of the 
    increase in this account category unexplained.
        Response: The statement that the Regional Office expense in 1995 
    included the Dolores Project is incorrect. The Regional Office expense 
    category applies only to the initial CRSP units (i.e., Aspinall, 
    Flaming Gorge, Glen Canyon, and Navajo), and not to the Dolores 
    Project. Dolores Project costs are shown in their own, separate PF-3 
    budget document.
        Regional Office expenses shown in the initial units (CRSP) work 
    plan differ from those included in the PRS because Western 
    inadvertently used an unofficial version of Reclamation's PF-3. This 
    document did not differ from the official budget in total costs for the 
    CRSP initial units. An adjustment within the program was made, which 
    increased the Regional Office expense by $564,000. This was made to 
    balance to the FY 1995 Budget Submission funding amount.
        b. Comment. The O&M figures (for the Rio Grande Project) in the PRS 
    appear to double count capitalized moveable equipment (CME) expenses 
    for the years 1995, 1997, and 1998 . . . .
        Response: Western agrees with the comment and has rerun the RGP 
    study to eliminate this error.
        c. Comment: For 1994, the difference in expenses between the Work 
    Program and the PRS appears to be comprised of the $35,000 for CME less 
    a $20,500 expense reduction, which is unex- plained.
        Response: Western's numbers were correct and have been used in the 
    PRS. The commentor's table shows a difference of $28,885. There are 
    four reasons for the difference: (1) O&M expenditures planned for FY 
    1993 on the Elephant Butte Dam of $67,548 (portion assigned to power = 
    $67,548 X 20.8% = $14,050) were not spent in FY 1993, but were 
    obligated and actually spent in 1994; (2) expenditures planned on the 
    Elephant Butte Powerplant ($30,854, of which 100-percent is repayable 
    by power revenues) were not spent in FY 1993, but were obligated and 
    actually spent in FY 1994; (3) the $35,000 referred to as CME for FY 
    1994 is not CME, but miscellaneous tools which is charged off to O&M 
    and is properly includable in the total O&M for the year; and (4) item 
    number (2) was further complicated by the fact that both the Work 
    Program and the FY 1995 Budget Congressional Submission are based on an 
    incorrect version of the summarized report. A line item (which should 
    be included in the Other Expense line) which appears on the detailed 
    report was coded incorrectly so that it does not appear on the 
    summarized reports, but is included in the totals of both reports. 
    Thus, the totals are $40,000 higher in the Work Program than the total 
    of the numbers shown and $23,921 higher than the total of the numbers 
    shown in the FY 1995 Congressional Budget Submission. The $40,000 
    budgeted Other Expense item was later reduced to $23,921, which matches 
    the $1,141,775 figure shown in the FY 1995 Congressional Budget 
    Submission. Following is a table which recaps the above information 
    starting with the figures shown in the commentor's table:
    
                            Elephant Butte Powerplant                       
    ------------------------------------------------------------------------
                                                                    1995    
                                                   1995 Work   congressional
                                                    Program        budget   
                                                                submission  
    ------------------------------------------------------------------------
    Salaries....................................     $532,000      $532,000 
    Office General Expense......................      262,000       262,000 
    CPA.........................................      173,000      173,000  
                                                 ---------------------------
    Other Expense\1\............................      120,000    150,854\2\ 
        Subtotal\3\.............................    1,087,000     1,117,854 
    Missing Line Item\4\ (other expenses).......       40,000       23,921  
                                                 --------------             
        Total\5\................................    1,127,000    1,141,775  
    ------------------------------------------------------------------------
    \1\Other expenses should have been higher by $40,000 in both the FY 1995
      Work Program and the FY 1995 Congressional Budget Submission.         
    \2\When summed, includes $30,850 carryover from FY 1993.                
    \3\Actual summation of figure shown.                                    
    \4\This amount should have been included in the ``other expense'' line  
      of both the FY 1995 work program and the FY 1995 Budget               
      Justifications.                                                       
    \5\As displayed in the FY 1995 Work Program and the FY 1995             
      Congressional Budget Submission.                                      
    
    
    Subtotal--Elephant Butte Powerplant O&M....................   $1,141,775
    Less amount shown on commentor's table.....................   1,127,000 
                                                                ------------
        Subtotal...............................................       14,775
    Add allocated carry-over amount from item (1) above........      14,050 
                                                                ------------
        Total difference shown on commentor's table............      28,825 
                                                                ------------
    The average annual increase in projected O&M expenses which             
     results in a $8.2 million annual revenue requirement is                
     troublesome. How this figure was obtained in the modeling              
     effort undertaken at Western is not explained in detail in             
     the brochure. If the projected figure is based upon an                 
     extrapolation of historical data adjusted for inflation,               
     the cost figure may not reflect all of the possible areas              
     of cost reduction available to both Western and the Bureau             
     of Reclamation.                                                        
    Response. Only two projections used in the Integrated                   
     Projects and/or CRSP PRS are based on computer modeling:               
     the water available for power production and the ultimate              
     power-related revenue requirements for the participating               
     projects. Estimates for future O&M expenses are taken                  
     directly from official budgets; the budgets include modest             
     approximations of labor cost increases. All equipment                  
     spending in the 5-year budget window is made up of actual              
     projections received from workers in the field, reporting              
     which equipment is likely to need replacement and when.                
     Miscellaneous revenue and expense projections are based on             
     historical averages and known future commitments.                      
    b. Comment. A customer organization said:                               
    The Energy Policy Act of 1992 (EPACT) has served as the                 
     catalyst for increasing competition in wholesale                       
     generation. They would anticipate that Western begin to                
     streamline its operations in order that it position itself             
     competitively in the new electricity market.                           
    Response. Western's management is presently looking for                 
     ways to improve customer service while cutting costs                   
     through Western's Strategic Planning initiative. Some of               
     the decisions made to date include:                                    
    (1) Delayering. This is a reduction in the number of                    
     supervisory employees, to reduce red tape and inertia                  
     while increasing customer service. The emphasis will be on             
     empowering the employees. The initiative is already under              
     way.4703                                                               
    (2) Western will limit increases in annual operating                    
     expenses to less than 2-percent per project per year                   
     through FY 1996. Thereafter, increases in annual operating             
     expenses will not exceed the annual rate of inflation.                 
    (3) As the marketing agent for Federal power, Western will              
     participate in the decision making process with other                  
     resource agencies whose operating decisions significantly              
     affect Federal power rate and repayment obligations                    
     whenever possible.                                                     
    (4) Proposals for construction of new facilities will be                
     assessed using integrated resource planning principles and             
     must meet at least one of three criteria before                        
     construction may begin:                                                
    (a) Increased revenues from new facilities must exceed                  
     their annual cost over the cost-evaluation period.                     
    (b) Customers must benefit sufficiently to support new                  
     facilities in spite of a possible rate increase.                       
    (c) The new facilities will be funded by non-Western                    
     sources.                                                               
    A customer organization has a series of questions about                 
     construction-related cost projections.                                 
    a. Comment: Some of the commentators said: ... they have                
     been unable to find support in the 1995 Work Program for a             
     majority of the significant (>$100,000) additions and                  
     replacements included in the 1994 rate brochure and rate               
     brochure PRS....                                                       
    Response: For a detailed outline of the budget process,                 
     Western refers the reader to earlier replies to questions              
     about O&M. To reiterate, the FY 1995 Work Program had, in              
     many instances, higher cost projections than the FY 1995               
     Congressional Budget Submission. Western has used the                  
     lower figures in the ratesetting PRS.                                  
    In the case of CRSP construction, this change dramatically              
     reduced the cost projections. Table VI on pages 12 and 13              
     of the April 1994 Rate Brochure shows a $276 million                   
     decrease in budgeted power-related construction costs                  
     through FY 1998 between the FY 1995 Work Program (referred             
     to in the brochure as the FY 1994 Congressional Budget                 
     Submission) and the FY 1995 Congressional Budget                       
     Submission. Western has used the lower figure where it is              
     considered reliable.                                                   
    b. Comment: (The commentor) has been unable to find support             
     for the investments included in the Collbran/Rate Brochure             
     PRS.                                                                   
    Response: It is not possible to find the correlation                    
     between the investments in a budget document or work                   
     program and those in a PRS without some intermediate                   
     steps.                                                                 
    The annual figures in the 1995 Work Program are only                    
     planned cash expenditures. Investments are large items,                
     often taking more than 1 year to complete. The total spent             
     on any one investment, then, is the sum of the annual                  
     expenditures shown in the work programs, plus any                      
     applicable IDC.                                                        
    Western is required to record an investment in a PRS in the             
     year that it becomes operational. This permits the                     
     establishment of the proper repayment period and begins                
     the annual payment of interest on investment (due until                
     the investment's cost is completely repaid). Future                    
     investments appear in a PRS in the year they are planned               
     to be in-service, if that is within the 5-year budget                  
     window. Future investments (excluding future replacements)             
     planned for completion at some time after the 5-year                   
     window are normally excluded from a PRS, unless                        
     legislation directs otherwise (as is the case with the                 
     CRSP's participating projects). Annual cash outlays for an             
     investment that takes more than 1 year to complete have no             
     counterpart in a PRS. Indeed, there may be several years               
     of investment costs shown in work programs and budgets                 
     which do not appear in PRSs. However, the total sum, plus              
     IDC, will appear in the PRS in the year when the item is               
     anticipated to be operational.                                         
    It is not unusual for the first future year in a budget                 
     document to show projections higher than those shown in                
     the previous budget document for that same year. It is                 
     common to have obligated amounts at the end of the year                
     just closed that do not get paid in that year. They are                
     then carried over and added to the next year. Also, CWIP               
     that has been completed, but that did not get moved to                 
     plant-in-service in the financial records, is carried over             
     to the next year (with the assumption that it will be                  
     moved to plant-in-service at that time). This also adds to             
     the total amount shown in the subsequent year.                         
    c. Comment: (The commentor's) Table 7 below uses                        
     information provided in response to WAPA/CREDA-76 to                   
     illustrate the differences between the 1995 Work Program               
     and the PRS.4703                                                       
    (The commentor) believes that some or all of the decrease               
     may result from elimination or reduction of dam repair                 
     work described in Reclamation's response to (the                       
     commentor's) comments on the 1995 Work Program review. The             
     increases (i.e., increases over and above the amounts                  
     shown in the 1995 Work Program) are unexplained, however,              
     by changes presented in the 1995 Work Program. Therefore,              
     (the commentor) recommends use of the investments shown in             
     line 31 of table 7 in the Collbran/Rate PRS.                           
    Response: Table 7 in the commentor's July 27 comment letter             
     displays Collbran investment as shown in the FY 1995 Work              
     Program. Western agrees with the commentor's figures for               
     FY 1994 through FY 1998, except that carry-over from FY                
     1993 must also be added to FY 1994's total number.                     
     Western's brochure study also contained some figures from              
     the FY 1995 Congressional Budget Submission. There have                
     since been changes to that budget that have reduced some               
     of those costs by approximately $450,000. Western has                  
     rerun the Collbran ratesetting PRS using these changes.                
    The following table illustrates how incremental investment              
     in budget figures is transformed into a PRS entry. Figures             
     from Reclamation's FY 1995 Work Program are used. The                  
     Collbran Project was used for this example because it                  
     contains no IDC or multipurpose investment, thereby                    
     simplifying the                                                        
     illustration.47038,L2,i1,s100,4,4,4,4,4,5,5                            
    Per FY 1995 Work Plan:                                                  
      Big Meadows Dam..........................................          200
      Cottonwood Dam #2........................................           72
      Atkinson Dam.............................................  ...........
      Big Creek Dam............................................           69
      Lambert Dam..............................................  ...........
                                                                ------------
        Total..................................................          341
    Per PRS/Financial Statement Entries                                     
      Big Meadows Dam..........................................  ...........
      Cottonwood Dam #2........................................  ...........
      Atkinson Dam.............................................  ...........
      Big Creek Dam............................................  ...........
      Lambert Dam..............................................  ...........
                                                                ------------
        Total..................................................            0
                                                                            
    
        d. Comment: All years in the (Rio Grande) PRS except 1994 match the 
    values from the 1995 Work Program. In 1994, the difference is $619,806. 
    (The values shown in line 14 of Table 9 should be used in the PRS.)
        Response:  The commentor is correct. An additional $619,806 has 
    been added to the work program amount shown in FY 1994. Not all of the 
    work in the Work Program for FY 1993 was completed or posted in that 
    year. The amounts not completed, including those obligated but not 
    spent in 1993, were carried over into FY 1994. This was the case with 
    the $619,806 noted by the commentor. This is necessitated because of 
    Western and Reclamation's accounting procedures (as explained in the 
    previous section on the Collbran Project), which require the total 
    investment (including IDC) to be moved to the plant-in-service account 
    in the year it becomes operational, rather than recording incremental 
    amounts of annual spending.
        Western has used the figures recommended by the commentor. The 
    figures are the basis for the projected investment through the cost 
    evaluation period (FY 1994-98). However, these amounts do not appear in 
    the PRS in those years. As previously explained (see the example of the 
    Collbran Project above), these amounts (plus IDC, where applicable) are 
    shown in the PRS in the year the particular investment is scheduled to 
    go into service.
        e. Comment: Commentor stated that:
        The intent of the work program review was to provide a less formal 
    process through which customers could receive information and provide 
    input regarding Western's and Reclamation's programs, allowing for this 
    same information to then be used in determining the adequacy of rates. 
    In departing in the rate process from data developed in the FY 1995 
    Work Program, the principal benefit of the process is effectively 
    undone. Moreover, the departures were not trivial. For Western's O&M 
    expenses, the 1994 figure used in the Rate Brochure PRS exceeds that 
    contained in the FY 1995 Work Program by almost $4 million, or 20 
    percent.
        In new construction projects, the commentor identified over $45 
    million in additional investment included in the PRS that was not 
    identified or had been excluded in the work program review.
        Response: Western has given a detailed explanation of the changes 
    in the 1994 O&M figures between the FY 1995 Work Program and the 1993 
    ratesetting PRS earlier in this Rate Order. Construction cost 
    modifications are also listed in detail.
        Western disagrees with the thrust of the commentor's statement. As 
    Western follows its policy to develop the lowest rate to consumers 
    consistent with sound business principles, all power customers, 
    including the commentor's members benefit.
        For example, the FY 1995 Work Program includes over $527 million in 
    construction costs for the SLCAO alone. Deducting what would normally 
    be excluded from the PRS because it is not planned for completion by FY 
    1998 leaves $284 million. This figure ($284 million) is still more than 
    double what Western finally included in the Rate Brochure PRS as new 
    investment $131 million. The difference between these two figures (the 
    $284 million in the FY 1995 Work Program and the $131 million in the 
    Rate Brochure PRS) equals approximately 0.75 mills/kWh in the composite 
    rate. In other words, following the commentor's instructions would have 
    resulted in a \3/4\ mills/kWh higher firm power rate than Western is 
    proposing. Finally, Western will continue to work with its customers to 
    identify and correct problems with the work program review process.
    8. Environmentally Related Expenses
        a. Comment: The sum of environmental costs in the 1994 Rate 
    Brochure is more than $0.5 million greater in 1993 and 1994 than 
    contained in the FY 1995 Work Program. Western's response to CREDA's 
    information request (WAPA/CREDA 67) indicated that the additional costs 
    in 1994 were explained by about $6.0 million in ``unliquidated 
    obligation'' in 1993. While actual costs were indeed lower than planned 
    in 1993, the reduction does not explain the still greater increase 
    indicated in the 1994 rate brochures. Environmental study costs should 
    be limited to the amounts (with some allowance for carryover from prior 
    years) developed in the work program process.
        Response: To compare environmental costs spent and budgeted for FYs 
    1993 and 1994 in the 1995 budget and work plan, the unliquidated 
    obligations must be taken into consideration, as shown below: 
    
                         Environmental Expenses ($000)                      
    ------------------------------------------------------------------------
                                                                       New  
                                      FY 1993   FY 1994    Total     Total  
    ------------------------------------------------------------------------
    1994 Rate Brochure Appendix.....   $11,885   $20,935   $32,820   $32,820
    Adjustment......................         0       490       490    33,310
    FY 93 Unliquidated Obligations..    -2,391         0    -2,391    30,919
    FY 94 Unliquidated Obligations..     6,005    -6,005         0    30,919
                                     ---------------------------------------
        Total Obligations...........    15,499    15,420    30,919    30,919
    FY 1995 Work Program............    16,788    15,463    32,251    32,251
    FY 93 Unliquidated Obligations..    -2,391         0    -2,391   29,860 
                                     ---------------------------------------
        Total Obligations...........    14,397    15,463    29,860   29,860 
                                     ---------------------------------------
          Difference................     1,102       -43     1,059    1,059 
    ------------------------------------------------------------------------
    
        b. Comment: A customer organization says:
        It is clear that environmental expenses associated with Glen Canyon 
    Dam have gotten out of hand, are not under control, and are not being 
    subjected to any sort of cost-control analysis or audit. They urge 
    Western to do what it can to urge the Bureau of Reclamation to limit 
    environmental study expenditures to those that are calculated to 
    produce necessary, credible information.
        Response: As a part of Western's Strategic Planning initiative: 
    Western will, as the marketing agent for Federal power, participate in 
    the decision making process whenever possible with other resource 
    agencies whose operating decisions significantly affect Federal power 
    rate and repayment obligations. Western will do so to sustain the 
    marketability of the Federal hydroelectric resource.
    9. Miscellaneous Comments
        Long-term Capacity Sales:
        (1) Comment: (The commentor) notes that there is a discrepancy 
    between the projection of capacity sales shown in Western's ``1993 
    Power Projections'' and the values in the PRS. Upon inspection of the 
    two set of values, it appears that the values used in the PRS may have 
    been misentered 1 year below the proper year. This causes the amount of 
    capacity sales to be slightly understated in several years.
        Response: Western agrees. Western has checked these data and has 
    found a disconnect between the kW of capacity sales estimate found in 
    the work papers and that in the PRS. It appears that the data from FYs 
    1993 through 2003 in the work papers were put into the PRS in FYs 1994 
    through 2004. The error has been corrected.
        (2) Comment: Western calculates the PRS for Integrated Projects 
    such that replacements are repaid up to the rate-setting year. In part, 
    this is due to the assignment of a lower repayment priority (to 
    irrigation) in the PRS. Assigning the lower priority (to irrigation) 
    causes a less than optimal rate calculation, since the rate could be 
    lowered by allowing for some replacements to remain unpaid beginning 9-
    10 years prior to the ratesetting year.
        Response: Western recognizes that some replacements have been paid 
    earlier in the PRS than required. Western conducted a test to determine 
    if forcing payments to irrigation obligations would postpone early 
    payment of replacements, thus lowering the rate. Forcing payments 
    reduces the composite rate 0.13 mills/kWh. This change has been made in 
    the ratesetting PRS.
    10. Untimely Responses to Data Requests
        a. Comment: Three commentors stated that their consultant did not 
    receive all the information needed to reconcile certain key portions of 
    the proposed rate and did not have adequate time to verify all the data 
    underlying the rate adjustment.
        Response: The consultant submitted five official data requests. 
    Responses were as follows: 
    
    ------------------------------------------------------------------------
                                          Items of                          
     Data request received by western's     data      Information mailed by 
                   SLCAO                 requested       western's SLCAO    
    ------------------------------------------------------------------------
    May 13, 1994.......................          18  May 20, 1994.          
    June 3, 1994.......................           9  June 23, 1994.         
    June 24, 1994......................           9  June 30, 1994.         
    July 1, 1994.......................          38  July 19, 1994.         
    July 8, 1994.......................           8  July 14, 1994.         
      Total............................         82                          
    ------------------------------------------------------------------------
    
        Customers originally had 97 days to submit comments and request 
    information; 56 of those days were after the public information forum. 
    The largest and most detailed request for data was received by Western 
    on July 1, 1994, which was 19 days before the original close of the 
    comment period. The final response to this request was faxed to the 
    consulting firm, on July 19, 1994, 1 day before the original end of the 
    comment period. Western then extended the date it would accept comments 
    to July 27, 1994, to provide commentors extra time to prepare a reply. 
    Western believes that ample time has been allowed for public comment 
    and that information was furnished to requestors in a timely manner. 
    However, Western also recognizes that there could be confusion and 
    misunderstanding regarding the information needed by the commentators 
    and that some of the information received may not be what was needed. 
    Western will continue to work with customers and interested parties to 
    find a more efficient and acceptable process to respond to data 
    requests and meet the commentors' needs.
        b. Comment: A customer organization said:
        Given the backdrop of structural changes in the industry and 
    increasing environmental concerns over hydro power generation, it would 
    seem that Western should develop a pricing policy based upon a firm 
    understanding of price sensitivity. The lack of any such analysis is a 
    major omission.
        Response: One of Western's primary concerns is the impact the 
    prices for its products have on possible sales. Based on knowledge of 
    the electrical power market, Western's proposed combined rates for firm 
    power are below other sources of firm electrical power available to 
    Integrated Projects customers. For this reason, Western has not 
    undertaken a specific study to analyze price effects on the electrical 
    power purchased by Western's Integrated Projects customers.
        There may be reductions of Integrated Projects energy usage in the 
    short-term by Western's customers as a result of the proposed increase 
    in the energy rate. Some of Western's Integrated Projects customers 
    with their own electrical power generating resources may be faced with 
    variable costs that allow them to produce energy more cheaply than 
    purchasing from Western at the proposed new rate. Information on the 
    cost of generation is considered sensitive and is not available to 
    Western. However, published sources of information which relate to coal 
    prices and other components of the variable costs of power generation 
    indicate that the proposed energy rate is less than Western's estimate 
    of their cost of generating thermal energy. Western has received no 
    comments to indicate otherwise.
        c. Comment: To help customers respond more completely to Western's 
    proposals, a customer organization suggests that, in the future, when 
    Western entertains the thought of extending the time for commenting as 
    done here, tie the extension to a period of time following completion 
    of responses to requests for information.
        Response: Western believes that the existing customer review 
    process and the public rate process sufficiently provide for both 
    flexibility for input and measurability of the progress toward the 
    completion of a rate.
        d. Comment: Several customers concur with changing the expression 
    of the firm power rate from a `combined rate' to a `composite rate'.
        Response: Western agrees with the customer comment and believes 
    that the composite rate will make the price of Integrated Projects 
    power more easily comparable with that from other sources.
        e. Issue: A customer states that they believe it is very unfair to 
    continue to increase the burden on the ratepayers to fund 
    (environmental) studies which will result in further increases in costs 
    and/or reductions in the amount of power available.
        Response: As noted earlier, Western is working with Reclamation to 
    more closely monitor these costs.
        11. Issue Papers Resolution: Several issues which Western believes 
    would have caused considerable protracted comment were discussed in 
    detail during the pre-rate-adjustment process of informal meetings 
    between various stakeholders and the exchange of issue papers. The 
    stakeholders liked the process. The issues which were resolved in this 
    process are summarized below:
        a. Identifying historic expenses related to the CRSP's Glen Canyon 
    Unit that became nonreimbursable with the passage of the Grand Canyon 
    Protection Act of 1992 (GCPA).
        b. Agreement about which future Glen Canyon Dam environmental costs 
    have the potential to become nonreimbursable.
        c. General understanding of the functioning of the budget 
    neutrality stipulations in the GCPA, stating that environmentally 
    related expenses will be nonreimbursable for FY 1993 through FY 1997 
    only to the extent that offsetting revenues are received by the 
    Treasury from other GCPA provisions.
        d. The timing of the reallocation of the construction costs of the 
    Glen Canyon Unit.
        e. Identification of those costs of the Central Utah 
    (participating) Project which are properly excluded from influencing 
    the Integrated Projects firm power rate.
        f. Implementation of a procedure to assure that the Basin Fund has 
    sufficient cash on hand to pay all operating costs for the CRSP.
    
    Environmental Evaluation
    
        In compliance with the National Environmental Policy Act of 1969, 
    42 U.S.C. 4321 et seq.; Council on Environmental Quality Regulations 
    (40 CFR Parts 1500-1508); and DOE NEPA Regulations (10 CFR Part 1021), 
    Western has determined that this action is categorically excluded from 
    the preparation of an environmental assessment or an environmental 
    impact statement.
    
    Executive Order 12866
    
        DOE has determined that this is not a significant regulatory action 
    because it does not meet the criteria of Executive Order 12866, 58 FR 
    51735. Western has an exemption from centralized regulatory review 
    under Executive Order 12866; accordingly, no clearance of this notice 
    by OMB is required.
    
    Availability of Information
    
        Information regarding this rate adjustment, including PRSs, 
    comments, letters, memoranda, and other supporting material made or 
    kept by Western for the purpose of developing the power rates, is 
    available for public review in the following locations.
    
    Salt Lake City Area Office, Western Area Power Administration, Office 
    of the Assistant Area Manager for Power Marketing, 257 East 200 South, 
    Suite 475, Salt Lake City, UT 84111
    Western Area Power Administration, Division of Marketing and Rates, 
    1627 Cole Boulevard, Golden, CO 80401
    Western Area Power Administration, Office of the Assistant 
    Administrator for Washington Liaison, Room 8G-027, Forrestal Building, 
    1000 Independence Avenue SW., Washington, DC 20585
    
    Submission to Federal Energy Regulatory Commission
    
        The rate herein confirmed, approved, and placed into effect on an 
    interim basis, together with supporting documents, will be submitted to 
    FERC for confirmation and approval on a final basis.
    
    Order
    
        In view of the foregoing and pursuant to the authority delegated to 
    me by the Secretary of Energy, I confirm and approve on an interim 
    basis, effective December 1, 1994, Rate Schedule SLIP-F5. The rate 
    schedule shall remain in effect on an interim basis, pending FERC 
    confirmation and approval of it or a substitute rate on a final basis, 
    through November 30, 1999.
    
        Issued in Washington, D.C., October 24, 1994.
    William H. White,
    Deputy Secretary.
    
    Salt Lake City Area Integrated Projects; Arizona, Colorado, Nevada, New 
    Mexico, Utah, Wyoming; Schedule of Rates for Firm Power Service
    
    Effective
    
        Beginning December 1, 1994, through November 30, 1999, or until 
    superseded by another rate schedule, whichever occurs earlier.
    
    Available
    
        In the area served by the Salt Lake City Area Integrated Projects.
    
    Applicable
    
        To the wholesale power customers for firm power service supplied 
    through one meter at one point of delivery, or as otherwise established 
    by contract.
    
    Character
    
        Alternating current, 60 hertz, three-phase, delivered and metered 
    at the voltages and points established by contract.
    
    Monthly Rate
    
        Demand Charge: $3.83 per kilowatt of billing demand.
        Energy Charge: 8.90 mills per kilowatthour of use.
    
    Billing Demand
    
        The billing demand will be the greater of:
        1. The highest 30-minute integrated demand measured during the 
    month up to, but not more than, the delivery obligation under the power 
    sales contract, or
        2. The contract rate of delivery.
    
    Adjustment for Transformer Losses
    
        If delivery is made at transmission voltage but metered on the low-
    voltage side of the substation, the meter readings will be increased to 
    compensate for transformer losses as provided for in the contract.
    
    Adjustment for Power Factor
    
        The customer will be required to maintain a power factor at all 
    points of measurement between 95-percent lagging and 95-percent 
    leading.
    
    Adjustment for Purchased Resources
    
    Purpose of Adjustment
        To ensure that Western Area Power Administration (Western) has 
    sufficient revenues to support resource purchases made necessary 
    because of restricted generation from Glen Canyon Dam as the result of 
    restrictions on water releases from the dam.
    Applicability
        To those contractors who are not receiving service under an Interim 
    Purchase Amendment to the firm power sales contract.
    Adjustment
        If Western finds it necessary to purchase resources to replace 
    generation lost at Glen Canyon Dam because of the above-listed 
    restrictions, Western will, beginning on the first month that such 
    purchases are made, include in the contractor's monthly power bill an 
    estimate of that contractor's proportionate share of net capacity 
    purchase costs. The cost of purchasing these resources will be offset 
    by the revenue that Western receives for the sale of energy, if any, 
    associated with the purchased resources.
        In its October bill each year, Western will reconcile the previous 
    fiscal year's actual purchased power expenses and the monthly estimated 
    costs paid by the contractor. If the contractor has paid more than its 
    proportionate share of actual purchased power expenses, the excess 
    amount will be shown as a credit to the contractor's October power 
    bill. If the contractor has paid less than its proportionate share of 
    actual power purchase expenses, Western will add such amount to the 
    contractor's October power bill.
    
    Notification
        If Western finds it necessary to implement this adjustment, it will 
    give a one-time notification to the contractor and the Federal Energy 
    Regulatory Commission at least 10 days before initially adding 
    purchased power cost to the contractor's monthly bill.
    
    [FR Doc. 94-27306 Filed 11-2-94; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Effective Date:
12/1/1994
Published:
11/03/1994
Department:
Western Area Power Administration
Entry Type:
Uncategorized Document
Action:
Notice of Rate Order''Salt Lake City Area/Integrated Projects (Integrated Projects) Firm Electric Service Rate Adjustment.
Document Number:
94-27306
Dates:
Rate Schedule SLIP-F5 will be placed into effect on an interim basis on the first day of the first full billing period beginning on/or after December 1, 1994, and will be in effect until FERC confirms, approves, and places the rate schedule in effect on a final basis through November 30, 1999, or until the rate schedule is superseded.
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: November 3, 1994