2023-24317. WBI Energy Transmission, Inc.; Notice of Request for Extension of Time  

  • Start Preamble

    Take notice that on October 25, 2023, WBI Energy Transmission, Inc. (WBI Energy) requested that the Federal Energy Regulatory Commission (Commission) grant an extension of time (2023 Extension of Time Request), until June 1, 2024, to construct to construct and operate a new compressor station, tie-in facilities including pipeline, and associated measurement facilities on its Line Section 27 Expansion Project (Project) to provide incremental natural gas firm transportation service in McKenzie County, North Dakota authorized by the Commission in Docket Nos. CP82–487–000, et al.[1]

    In its 2023 Extension of Time Request, WBI Energy states that it will not complete all work associated with the project by the November 21, 2023, deadline. Accordingly, WBI Energy requests an extension of time until June 1, 2024, to complete construction of project facilities.

    This notice establishes a 15-calendar day intervention and comment period deadline. Any person wishing to comment on WBI Energy's request for an extension of time may do so. No reply comments or answers will be considered. If you wish to obtain legal status by becoming a party to the proceedings for this request, you should, on or before the comment date stated below, file a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10).

    As a matter of practice, the Commission itself generally acts on requests for extensions of time to complete construction for Natural Gas Act facilities when such requests are contested before order issuance. For those extension requests that are contested,[2] the Commission will aim to issue an order acting on the request within 45 days.[3] The Commission will address all arguments relating to whether the applicant has demonstrated there is good cause to grant the extension.[4] The Commission will not consider arguments that re-litigate the issuance of the certificate order, including whether the Commission properly found the project to be in the public convenience and necessity and whether the Commission's environmental analysis for the certificate complied with the National Environmental Policy Act.[5] At the time a pipeline requests an extension of time, orders on certificates of public convenience and necessity are final and the Commission will not re-litigate their issuance.[6] The OEP Director, or his or her designee, will act on all of those extension requests that are uncontested.

    In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( http://www.ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number Start Printed Page 75585 field to access the document. At this time, the Commission has suspended access to the Commission's Public Reference Room. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TTY, (202) 502–8659.

    The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the “eFiling” link at http://www.ferc.gov. Persons unable to file electronically should submit an original and three copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.

    Comment Date: 5:00 p.m. Eastern Time on, November 14, 2023.

    Start Signature

    Dated: October 30, 2023.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.   WBI Energy Transmission et al., 30 FERC ¶ 61,143, (1985).

    Back to Citation

    2.  Contested proceedings are those where an intervenor disputes any material issue of the filing. 18 CFR 385.2201(c)(1) (2022).

    Back to Citation

    3.   Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).

    Back to Citation

    4.   Id. at P 40.

    Back to Citation

    5.  Similarly, the Commission will not re-litigate the issuance of an NGA section 3 authorization, including whether a proposed project is not inconsistent with the public interest and whether the Commission's environmental analysis for the permit order complied with NEPA.

    Back to Citation

    6.   Algonquin Gas Transmission, LLC, 170 FERC ¶ 61,144, at P 40 (2020).

    Back to Citation

    [FR Doc. 2023–24317 Filed 11–2–23; 8:45 am]

    BILLING CODE 6717–01–P

Document Information

Published:
11/03/2023
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2023-24317
Dates:
5:00 p.m. Eastern Time on, November 14, 2023.
Pages:
75584-75585 (2 pages)
Docket Numbers:
Docket No. CP22-512-001
PDF File:
2023-24317.pdf