2018-26005. Midship Pipeline Company, LLC; Notice of Intent To Prepare an Environmental Assessment for a Proposed Amendment of the Midcontinent Supply Header Interstate Pipeline Project and Request for Comments on Environmental Issues
-
Start Preamble
The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of a proposed amendment (0.8-mile reroute) of Midship Pipeline Company, LLC's (Midship Pipeline) Midcontinent Supply Header Interstate Pipeline Project (MIDSHIP Project) in Bryan County, Oklahoma.[1] The Commission will use this EA in its decision-making process to determine whether the amendment is in the public convenience and necessity.
This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies about issues regarding the amendment/reroute. The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from its action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires the Commission to discover concerns the public may have about proposals. This process is referred to as “scoping.” The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC on or before 5:00 p.m. Eastern Time on December 24, 2018.
You can make a difference by submitting your specific comments or concerns about the reroute. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Commission staff will consider all filed comments during the preparation of the EA.
If you sent comments on this project to the Commission before the opening of this docket on November 14, 2018, you will need to file those comments in Docket No. CP19-17-000 to ensure they are considered as part of this proceeding.
This notice is being sent to the Commission's current environmental mailing list for this amendment. State and local government representatives should notify their constituents of this proposed amendment and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable easement agreement. You are not required to enter into an agreement. However, if the Commission approves the amendment, that approval conveys with it the right of eminent domain. Therefore, if you and the company do not reach an easement agreement, the pipeline company could initiate condemnation proceedings in court. In such instances, compensation would be determined by a judge in accordance with state law.
Midship Pipeline provided landowners with a fact sheet prepared by FERC entitled “An Interstate Natural Gas Facility On My Land? What Do I Need To Know?” This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission's proceedings. It is also available for viewing on the FERC website (www.ferc.gov) at https://www.ferc.gov/resources/guides/gas/gas.pdf.
Public Participation
The Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances and submittals regarding the dockets/projects to which you subscribe. These instant email notifications are the fastest Start Printed Page 61627way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. To sign up go to www.ferc.gov/docs-filing/esubscription.asp.
For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208-3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded.
(1) You can file your comments electronically using the eComment feature, which is located on the Commission's website (www.ferc.gov) under the link to Documents and Filings. Using eComment is an easy method for submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling feature, which is located on the Commission's website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; a comment on a particular project is considered a “Comment on a Filing”; or
(3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP19-17-000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426.
Summary of the Proposed Project
Midship Pipeline proposes a 0.8-mile reroute between mileposts 195.2 to 195.9 of the MIDSHIP Project in Bryan County, Oklahoma. This reroute would shift the pipeline about 400 feet west and south of the certificated pipeline route. The general location of the reroute is shown in appendix 1.[2]
Land Requirements for Construction
Construction of the proposed reroute would disturb about 12.5 acres of land. Following construction, Midship Pipeline would maintain about 5.3 acres for permanent operation of the project; the remaining acreage would be restored and revert to former uses. This represents an increase from the certificated route of about 1.2 acres during construction and 0.5 acre during operation.
The EA Process
The EA will discuss impacts that could occur as a result of the proposed amendment under these general headings:
- Geology and soils;
- water resources and wetlands;
- vegetation and wildlife;
- threatened and endangered species;
- cultural resources;
- land use;
- air quality and noise;
- public safety; and
- cumulative impacts.
Commission staff will also evaluate reasonable alternatives to the proposed amendment, and make recommendations on how to lessen or avoid impacts on the various resource areas as applicable.
The EA will present Commission staffs' independent analysis of the issues. The EA will be available in electronic format in the public record through eLibrary [3] and the Commission's website (https://www.ferc.gov/industries/gas/enviro/eis.asp). If eSubscribed, you will receive instant email notification when the EA is issued. The EA may be issued for an allotted public comment period. Commission staff will consider all comments on the EA before making recommendations to the Commission. To ensure Commission staff have the opportunity to address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2.
With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the EA.[4] Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice.
Consultation Under Section 106 of the National Historic Preservation Act
In accordance with the Advisory Council on Historic Preservation's implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the applicable State Historic Preservation Office (SHPO), and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project's potential effects on historic properties.[5] Commission staff will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project develops. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, contractor/pipe storage yards, compressor stations, and access roads). The EA for this project will document findings on the impacts on historic properties and summarize the status of consultations under section 106.
Environmental Mailing List
The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission's regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, and anyone who submits comments on the project. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed amendment.
If the Commission issues the EA for an allotted public comment period, a Notice of Availability of the EA will be sent to the environmental mailing list and will provide instructions to access the electronic document on the FERC's website (www.ferc.gov). If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please return the attached “Mailing List Update Form” (appendix 2).Start Printed Page 61628
Additional Information
Additional information about the amendment/reroute is available from the Commission's Office of External Affairs, at (866) 208-FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on “General Search” and enter the docket number in the “Docket Number” field, excluding the last three digits (i.e., CP19-17). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.
Start SignatureDated: November 23, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
Footnotes
1. On August 13, 2018, the Commission issued a Certificate of Public Convenience and Necessity for the 234.1-mile-long MIDSHIP Project under Docket No. CP17-458-000.
Back to Citation2. The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called “eLibrary” or from the Commission's Public Reference Room, 888 First Street NE, Washington, DC 20426, or call (202) 502-8371. For instructions on connecting to eLibrary, refer to the last page of this notice.
Back to Citation3. For instructions on connecting to eLibrary, refer to page 5 of this notice.
Back to Citation4. The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6.
Back to Citation5. The Advisory Council on Historic Preservation's regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places.
Back to Citation[FR Doc. 2018-26005 Filed 11-29-18; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 11/30/2018
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 2018-26005
- Pages:
- 61626-61628 (3 pages)
- Docket Numbers:
- Docket No. CP19-17-000
- PDF File:
- 2018-26005.pdf