98-29644. Florida Power Corporation et al. (Crystal River Unit 3); Exemption  

  • [Federal Register Volume 63, Number 214 (Thursday, November 5, 1998)]
    [Notices]
    [Pages 59811-59813]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-29644]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-302]
    
    
    Florida Power Corporation et al. (Crystal River Unit 3); 
    Exemption
    
    I
    
        The Florida Power Corporation et al. (FPC or the licensee) is the 
    holder of Facility Operating License No. DPR-72, which authorizes the 
    operation of Crystal River Unit 3. The license states that the licensee 
    is subject to all rules, regulations, and orders of the Nuclear 
    Regulatory Commission (NRC or the Commission) now or hereafter in 
    effect.
        The facility consists of a pressurized-water reactor at the 
    licensee's site located in Citrus County, Florida.
    
    II
    
        The Code of Federal Regulations at 10 CFR Part 50, Appendix K, 
    Section I.D.1, ``Single Failure Criterion,'' requires that accident 
    evaluations use the combination of emergency core cooling system (ECCS) 
    subsystems assumed to be operative ``after the most damaging single-
    failure of ECCS equipment has taken place.'' The proposed action would 
    exempt the licensee from the single-failure requirement for very-low-
    probability scenarios under certain circumstances. The exemption is 
    limited to the systems required for preventing boron precipitation 
    during the long-term cooling phase of a loss-of-coolant accident 
    (LOCA). 10 CFR 50.46(b)(5) requires that the ECCS be capable of 
    providing long-term core cooling. Post-accident boron precipitation is 
    a potential, but unlikely, challenge to maintaining long-term core 
    cooling.
        By letter dated October 31, 1997, as supplemented by letters dated 
    December 13, 1997, February 27, 1998, and April 24, 1998, FPC requested 
    an amendment to its operating license for Crystal River Unit 3. The FPC 
    amendment request addressed prevention of boron precipitation following 
    a LOCA that involved the following:
        (1) Reactor vessel vent valves (RVVVs) that are effective when 
    needed for all LOCA conditions except for (a) some LOCAs between the 
    reactor coolant pumps and the reactor vessel (RV) at an elevation below 
    the cold-leg mid-pipe at the junction with the RV and (b) decay heat 
    generation rate comparable to approximately a month following extended 
    operation at full power for some LOCAs.
        (2) If the RVVVs are not effective, then, according to the 
    licensee's
    
    [[Page 59812]]
    
    calculations, Motor Control Center (MCC) 3AB is needed to provide power 
    to open valves within 8 hours for the worst-case LOCA to (a) initiate 
    water injection via auxiliary pressurizer spray (APS) or (b) initiate 
    the dump-to-sump (DTS) method of moving water from a hot leg to the 
    reactor building sump.
        Should MCC 3AB fail before the APS or DTS initiates, both of these 
    systems will fail to initiate in these licensing scenarios. In a June 
    4, 1998, submittal, FPC requested an exemption from the single-failure 
    requirement with respect to this failure. FPC justified its request by 
    stating that the proposed exemption meets the underlying purpose of the 
    rule in that there are conservatisms in the calculations that cause 
    underprediction of available repair time, so that, using realistic 
    assumptions, sufficient time would be available to perform repairs to 
    restore MCC 3AB if needed. As a result, the licensee stated that there 
    was reasonable assurance of the availability of an active boron 
    precipitation method (APS or DTS) if one were needed. FPC states that 
    timely recognition of boron precipitation is assured by compliance with 
    plant procedures and further states that prompt operator actions will 
    be taken to restore an active method in the event of MCC 3AB failure.
        One element of the licensee's justification was to credit flow 
    through the hot-leg nozzle gaps. According to FPC's calculations, APS 
    is not fully effective until 21 hours after LOCA initiation, but it may 
    be needed within 8 hours if a single failure other than the failure of 
    MCC 3AB makes DTS unavailable. FPC addressed this problem by crediting 
    flow through hot-leg nozzle gaps to provide a boron dilution means for 
    the first 21 hours. However, the NRC does not accept credit for hot-leg 
    nozzle gap flow because FPC has not established that the nozzle gaps 
    will remain functional after a LOCA. Therefore, during this time 
    period, a failure to meet the Appendix K Item I.D.1 single-failure 
    criterion remains. However, the NRC has determined that the licensee 
    has given adequate justification in its submittal to extend the 
    exemption to this scenario.
    
    III
    
        Pursuant to 10 CFR 50.12, the Commission may, upon application by 
    any interested person or upon its own initiative, grant exemptions from 
    the requirements of 10 CFR Part 50 (1) when the exemptions are 
    authorized by law, will not present an undue risk to public health or 
    safety, and are consistent with the common defense and security and (2) 
    when special circumstances are present. Special circumstances are 
    present whenever, according to 10 CFR 50.12(a)(2)(ii), ``Application of 
    the regulation in the particular circumstances would not serve the 
    underlying purpose of the rule or is not necessary to achieve the 
    underlying purpose of the rule. . . .''
        The underlying purpose of the single-failure criterion requirement 
    is to assure long-term cooling performance of the ECCS in the event of 
    the most damaging single-failure of ECCS equipment. As a licensing 
    review tool, the single-failure criterion helps assure reliable systems 
    as an element of defense in depth. As a design and analysis tool, it 
    promotes reliability through enforced redundancy. Since only those 
    systems or components that are judged to have a credible chance of 
    failure are assumed to fail, the criterion is applied to such responses 
    as valve movement on demand, emergency diesel generator start, short 
    circuit in an electrical bus, and fluid leakage caused by gross failure 
    of a pump or valve seal during long-term cooling. Reactor vessels or 
    certain types of structural elements within systems, when combined with 
    other unlikely events, are not assumed to fail because the 
    probabilities of the resulting scenarios have been deemed sufficiently 
    small that they need not be considered. Certain passive failures 24 
    hours or more after initiation of a LOCA, such as pipe breaks, are not 
    addressed as single failures because the compounded probabilities were 
    judged sufficiently small that they could be discounted without 
    affecting overall systems reliability.
        The single-failure criterion was developed without the benefit of 
    numerical failure assessments. Regulatory requirements and guidance 
    consequently were based upon categories of equipment and examples that 
    must be covered or that are exempt, and do not allow a probabilistic 
    consideration during routine implementation. Hence, a single failure, 
    whether or not there is a substantial impact upon overall system 
    reliability, would not meet the regulatory requirements. A non-
    beneficial result is inconsistent with the objective of the single-
    failure criterion, which was not intended to force changes if 
    essentially no benefit would accrue. This is the case with the 
    potential MCC 3AB failure.
        FPC estimated that the combined probability of the LOCA of concern 
    and failure of MCC 3AB is 10-10/reactor-year. (The 
    probability of the LOCA of concern is 10-7/reactor-year and 
    the failure probability of MCC 3AB given the LOCA of concern is 
    10-3/reactor-year.) If MCC 3AB were to fail, FPC would 
    initiate its Emergency Plan Implementing Procedure to re-power MCC 3AB 
    from an alternate electric power source. FPC stated that sufficient 
    time will be available and that radiological conditions should permit 
    such activities.
        In addition, there are other conservatisms in the licensee's 
    analyses. These include:
         Presence of buffer compounds may increase solubility limit 
    margins. FPC concluded that solutes in the sump water will increase 
    boron solubility, but did not credit the effect in its calculations. 
    This is a conservatism when considering MCC 3AB repair and APS 
    unavailability time.
         Decay heat was calculated using Appendix K methods. FPC's 
    calculations, in accordance with its licensing basis, use a decay heat 
    generation rate that is roughly 25 percent too high. A realistic decay 
    heat would increase the time available before boron precipitation 
    became a concern. This is a significant conservatism when considering 
    MCC 3AB repair and APS unavailability time.
         Boron solubility. FPC used a boron solubility decreased by 
    4 weight percent from the published values, consistent with previously 
    accepted evaluation models. This is a conservatism when considering MCC 
    3AB repair and APS unavailability time.
         Boron precipitation. The approved evaluation models are 
    based upon preventing precipitation. Should precipitation occur, 
    significant boron would have to precipitate to prevent core cooling. 
    This unquantified conservatism is significant when considering MCC 3AB 
    repair and APS unavailability time.
        Despite the licensee's determination that there is no safety-
    significant vulnerability associated with the two particular instances 
    of failing to meet the single-failure criterion, FPC has developed and 
    implemented procedures to address the conditions should they occur. It 
    has shown that there is essentially no benefit to be achieved by 
    investing in additional equipment to eliminate the single-failure 
    aspects since the combined probability of the LOCA of concern with the 
    failure is very low. With regard to the availability of APS during the 
    first 21 hours following a LOCA should DTS be unavailable, realistic 
    calculations without the conservative assumptions discussed above 
    predict that APS would be available.
        These calculations, along with the low estimate of core damage 
    probability resulting from this scenario, result in a
    
    [[Page 59813]]
    
    conclusion that essentially no benefit would be achieved by requiring 
    modifications to meet the single-failure criteria for the specific 
    scenario during this time period.
    
    IV
    
        For these foregoing reasons, the NRC staff has concluded that it is 
    not necessary to meet the single-failure requirement of Appendix K, 
    Section I.D.1, with respect to (1) failure of Motor Control Center 3AB 
    and the resulting inability to initiate an active means of controlling 
    core boron concentration and (2) the active methods not meeting the 
    single-failure criterion for the period when approved licensing methods 
    predict that APS is not effective following certain LOCAs to adequately 
    ensure that boron precipitation does not interfere with long-term 
    cooling. The NRC staff has determined that there are special 
    circumstances present, as specified in 10 CFR 50.12.(a)(2)(ii), in that 
    application of 10 CFR Part 50, Appendix K, Section I.D.1, is not 
    necessary in order to achieve the underlying purpose of this 
    regulation, which is to provide adequate assurance that boron 
    precipitation will not interfere with the capability of the ECCS to 
    provide long-term core cooling.
        Accordingly, the Commission has determined that, pursuant to 10 CFR 
    50.12(a), this exemption is authorized by law, will not endanger life 
    or property or the common defense and security, and is otherwise in the 
    public interest. Therefore, the Commission hereby grants the following 
    exemption:
    
        The Florida Power Corporation, et al., is exempt from the 
    single-failure criterion requirement of 10 CFR Part 50, Appendix K, 
    Section I.D.1, with respect to (1) failure of Motor Control Center 
    3AB and the resulting inability to initiate an active means of 
    controlling core boron concentration and (2) failure of the active 
    means to meet the single-failure criterion for the period when 
    approved licensing methods predict that APS is not effective 
    following reactor coolant pump discharge breaks provided that: 
    procedural guidance shall be maintained that describes the actions 
    necessary to restore an active method of boron precipitation 
    mitigation in the event of a failure of Motor Control Center 3AB.
    
        Pursuant to 10 CFR 51.32, the Commission has determined that the 
    granting of this exemption will have no significant impact on the 
    quality of the human environment (63 FR 54162).
        This exemption is effective upon issuance.
    
        Dated at Rockville, Maryland, this 29th day of October, 1998.
    
        For the Nuclear Regulatory Commission.
    
    Frank J. Miraglia,
    Acting Director, Office of Nuclear Reactor Regulation.
    
    [FR Doc. 98-29644 Filed 11-4-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
11/05/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-29644
Pages:
59811-59813 (3 pages)
Docket Numbers:
Docket No. 50-302
PDF File:
98-29644.pdf