98-29766. Idaho Power Company; Notice of Authorization for Continued Project Operation  

  • [Federal Register Volume 63, Number 215 (Friday, November 6, 1998)]
    [Notices]
    [Pages 59961-59962]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-29766]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Project No. 2777]
    
    
    Idaho Power Company; Notice of Authorization for Continued 
    Project Operation
    
    November 2, 1998.
        On December 20, 1995, Idaho Power Company, licensee for the Upper 
    Salmon Falls Project No. 2777, filed an application for a new or 
    subsequent license pursuant to the Federal Power Act (FPA) and the 
    Commission's regulations thereunder. Project No. 2777 is located on the 
    Snake River in Gooding and Twin Falls Counties, Idaho.
        The license for Project No. 2777 was issued for a period ending 
    October 31, 1998. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
    requires the Commission, at the expiration of a license term, to issue 
    from year to year an annual license to the then licensee under the 
    terms and conditions of the
    
    [[Page 59962]]
    
    prior license until a new license is issued, or the project is 
    otherwise disposed of as provided in Section 15 or any other applicable 
    section of the FPA. If the project's prior license waived the 
    applicability of Section 15 of the FPA, then, based on Section 9(b) of 
    the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 
    CFR 16.21(a); if the licensee of such project has filed an application 
    of a subsequent license, the licensee may continue to operate the 
    project in accordance with the terms and conditions of the license 
    after the minor or minor part license expires, until the Commission 
    acts on its application. If the licensee of such a project has not 
    filed an application for a subsequent license, then it may be required, 
    pursuant to the 18 CFR 16.21(b), to continue project operations until 
    the Commission issues someone else a license for the project or 
    otherwise orders disposition of the project.
        If the project is subject to Section 15 of the FPA, notice is 
    hereby given that an annual license for Project No. 2777 is issued to 
    Idaho Power Company for a period effective November 1, 1998, through 
    October 31, 1999, or until the issuance of a new license for the 
    project or other disposition under the FPA, whichever comes first. If 
    issuance of a new license (or other disposition) does not take place on 
    or before October 31, 1999, notice is hereby given that, pursuant to 18 
    CFR 16.18(c), an annual license under Section 15(a)(1) of the FPA is 
    renewed automatically without further order or notice by the 
    Commission, unless the Commission orders otherwise.
         If the project is not subject to Section 15 of the FPA, notice is 
    hereby given that Idaho Power Company is authorized to continue 
    operation of the Upper Salmon Falls Project No. 2777 until such time as 
    the Commission acts on its application for subsequent license.
    David P. Boergers,
    Secretary.
    [FR Doc. 98-29766 Filed 11-5-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
11/06/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-29766
Pages:
59961-59962 (2 pages)
Docket Numbers:
Project No. 2777
PDF File:
98-29766.pdf