E7-21777. Duke Power Company, LLC; Oconee Nuclear Station, Units 1, 2, and 3 Environmental Assessment and Finding of No Significant Impact
-
Start Preamble
The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of amendments to Renewed Facility Operating Licenses Nos. DPR-38, DPR-47, and DPR-55, issued to Duke Power Company, LLC (the licensee), for operation of the Oconee Nuclear Station, Units 1, 2, and 3, located in Seneca, South Carolina. Therefore, as required by Title 10 of the Code of Federal Regulations, Part 51, Section 51.21, the NRC is issuing this environmental assessment and finding of no significant impact.
Environmental Assessment
Identification of the Proposed Action
The proposed action is administrative in nature and would revise the Technical Specifications (TSs) to remove requirements that are no longer applicable due to the completion of the control room intake/booster fan modifications.
The proposed action is in accordance with the licensee's application dated January 31, 2007.
The Need for the Proposed Action
The proposed action removes requirements from the TSs that are no longer applicable.
Environmental Impacts of the Proposed Action
The NRC has completed its safety evaluation of the proposed action and concludes that there are no environmental impacts.
The details of the staff's safety evaluation will be provided in the license amendments that will be issued as part of the letter to the licensee approving the license amendments.
The proposed action will not significantly increase the probability or consequences of accidents. No changes are being made in the types of effluents that may be released off site. There is no significant increase in the amount of any effluent released off site. There is no significant increase in occupational or public radiation exposure. Therefore, there are no significant radiological environmental impacts associated with the proposed action.
With regard to potential non-radiological impacts, the proposed action does not have a potential to affect any historic sites. It does not affect nonradiological plant effluents and has no other environmental impact. Therefore, there are no significant nonradiological environmental impacts associated with the proposed action.
Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action.
Environmental Impacts of the Alternatives to the Proposed Action
As an alternative to the proposed action, the staff considered denial of the proposed action (i.e., the “no-action” alternative). Denial of the application would result in no change in current environmental impacts. The environmental impacts of the proposed action and the alternative action are similar.
Alternative Use of Resources
The action does not involve the use of any different resources than those previously considered in the Final Environmental Statement for the Oconee Nuclear Station, Units 1, 2, and 3, dated March 1972 and Final Supplemental Environmental Impact Statement (NUREG-1437, Supplement 2) dated December 9, 1999.
Agencies and Persons Consulted
In accordance with its stated policy, on October 18, 2007, the staff consulted with the South Carolina State official, Mr. R. Mike Gandy of the Department of Health and Environmental Control, regarding the environmental impact of the proposed action. The State official had no comments.
Finding of No Significant Impact
On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.
For further details with respect to the proposed action, see the licensee's letter dated January 31, 2007. Documents may be examined and/or copied for a fee, at the NRC's Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or send an e-mail to pdr@nrc.gov.
Start SignatureDated at Rockville, Maryland, this 31st day of October 2007.
For the Nuclear Regulatory Commission.
Leonard N. Olshan,
Project Manager, Plant Licensing Branch II-1, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. E7-21777 Filed 11-5-07; 8:45 am]
BILLING CODE 7590-01-P
Document Information
- Published:
- 11/06/2007
- Department:
- Nuclear Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- E7-21777
- Pages:
- 62684-62684 (1 pages)
- Docket Numbers:
- Docket Nos. 50-269, 50-270, and 50-287
- PDF File:
- e7-21777.pdf