2018-24372. Approval and Promulgation of Air Quality Implementation Plans; Wyoming; Revisions to Regional Haze State Implementation Plan  

  • Start Preamble

    AGENCY:

    Environmental Protection Agency (EPA).

    ACTION:

    Proposed rule.

    SUMMARY:

    The Environmental Protection Agency (EPA) is proposing to approve a source-specific revision to the Wyoming State Implementation Plan (SIP) that provides an alternative to Best Available Retrofit Technology (BART) for Unit 3 at the Naughton Power Plant (“the SIP revision”) that is owned and operated by PacifiCorp. The EPA proposes to find that the BART alternative for Naughton Unit 3 would provide greater reasonable progress toward natural visibility Start Printed Page 55657conditions than BART in accordance with the requirements of section 110 of the Clean Air Act (CAA) and the EPA's Regional Haze Rule (RHR). The SIP revision was submitted by the State of Wyoming on November 28, 2017.

    The SIP revision for Naughton Unit 3 was submitted along with Wyoming's 5-year progress report, which is required under the Regional Haze Rule. However, the EPA is not proposing to act on the 5-year progress report in this rulemaking.

    DATES:

    Written comments must be received on or before December 7, 2018.

    ADDRESSES:

    Submit your comments, identified by Docket ID No. EPA-R08-OAR-2018-0607, to the Federal Rulemaking Portal: https://www.regulations.gov. Follow the online instructions for submitting comments. Once submitted, comments cannot be edited or removed from www.regulations.gov. The EPA may publish any comment received to its public docket. Do not submit electronically any information you consider to be Confidential Business Information (CBI) or other information whose disclosure is restricted by statute. Multimedia submissions (audio, video, etc.) must be accompanied by a written comment. The written comment is considered the official comment and should include discussion of all points you wish to make. The EPA will generally not consider comments or comment contents located outside of the primary submission (i.e., on the web, cloud, or other file sharing system). For additional submission methods, the full EPA public comment policy, information about CBI or multimedia submissions, and general guidance on making effective comments, please visit http://www2.epa.gov/​dockets/​commenting-epa-dockets.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Aaron Worstell, Air Program, EPA, Region 8, Mailcode 8P-AR, 1595 Wynkoop Street, Denver, Colorado 80202-1129, (303) 312-6073, worstell.aaron@epa.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Throughout this document wherever “we,” “us,” or “our” is used, we mean the EPA.

    Table of Contents

    I. General Information

    II. Background

    III. The SIP Revision for Naughton Unit 3

    IV. Clean Air Action Section 110(l)

    V. Consultation With FLMs

    VI. The EPA's Proposed Action

    VII. Incorporation by Reference

    VIII. Statutory and Executive Order Reviews

    I. General Information

    A. Definitions

    For the purpose of this document, we are giving meaning to certain words or acronyms as follows:

    • The words Wyoming and State mean the State of Wyoming.
    • The word Naughton refers to the Naughton Plant.
    • The initials BART mean or refer to Best Available Retrofit Technology.
    • The term Class I area refers to a mandatory Class I federal area.[1]
    • The initials CAA mean or refer to the Clean Air Act.
    • The initials CBI mean or refer to Confidential Business Information.
    • The initials EGU mean or refer to Electric Generating Unit.
    • The words EPA, we, us, or our mean or refer to the United States Environmental Protection Agency.
    • The initials FGR mean flue gas recirculation.
    • The initials FIP mean or refer to Federal Implementation Plan.
    • The initials LNB mean or refer to low-NOX burners.
    • The initials MMBtu mean or refer to million British thermal units.
    • The initials NAAQS mean or refer to National Ambient Air Quality Standards.
    • The initials NOX mean or refer to nitrogen oxides.
    • The initials OFA mean or refer to over fire air.
    • The initials PM mean or refer to Particulate Matter, which is inclusive of PM10 (particulate matter less than or equal to 10 micrometers) and PM2.5 (particulate matter less than or equal to 2.5 micrometers).
    • The initials SCR mean or refer to Selective Catalytic Reduction.
    • The initials SIP mean or refer to State Implementation Plan.
    • The initials SO2 mean or refer to Sulfur Dioxide.

    B. Docket

    All documents in the docket are listed in the www.regulations.gov index. Although listed in the index, some information is not publicly available, e.g., CBI or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, will be publicly available only in hard copy. Publicly available docket materials are available either electronically in www.regulations.gov or in hard copy at the Air Program, Environmental Protection Agency (EPA), Region 8, 1595 Wynkoop Street, Denver, Colorado 80202-1129. The EPA requests that if at all possible, you contact the individual listed in the FOR FURTHER INFORMATION CONTACT section to view the hard copy of the docket. You may view the hard copy of the docket Monday through Friday, 8:00 a.m. to 4:00 p.m., excluding federal holidays.

    II. Background

    A. Requirements of the Clean Air Act and the EPA's Regional Haze Rule

    In section 169A of the 1977 Amendments to the CAA, Congress created a program for protecting visibility in the nation's national parks and wilderness areas. This section of the CAA establishes “as a national goal the prevention of any future, and the remedying of any existing, impairment of visibility in mandatory Class I Federal areas which impairment results from manmade air pollution.” [2]

    The EPA promulgated a rule to address regional haze on July 1, 1999.[3] The RHR revised the existing visibility regulations [4] to integrate provisions addressing regional haze and established a comprehensive visibility protection program for Class I areas. The requirements for regional haze, found at 40 CFR 51.308 and 40 CFR 51.309, are included in the EPA's visibility protection regulations at 40 CFR 51.300 through 40 CFR 51.309. The EPA revised the RHR on January 10, 2017.[5]

    The CAA requires each state to develop a SIP to meet various air quality Start Printed Page 55658requirements, including protection of visibility.[6] Regional haze SIPs must assure reasonable progress toward the national goal of achieving natural visibility conditions in Class I areas. A state must submit its SIP and SIP revisions to the EPA for approval. Once approved, a SIP is enforceable by the EPA and citizens under the CAA; that is, the SIP is federally enforceable. If a state elects not to make a required SIP submittal, fails to make a required SIP submittal or if we find that a state's required submittal is incomplete or not approvable, then we must promulgate a Federal Implementation Plan (FIP) to fill this regulatory gap.[7]

    B. Best Available Retrofit Technology (BART)

    Section 169A of the CAA directs states as part of their SIPs to evaluate the use of retrofit controls at certain larger, often uncontrolled, older stationary sources in order to address visibility impacts from these sources. Specifically, section 169A(b)(2)(A) of the CAA requires states' implementation plans to contain such measures as may be necessary to make reasonable progress toward the natural visibility goal, including a requirement that certain categories of existing major stationary sources built between 1962 and 1977 procure, install, and operate the “Best Available Retrofit Technology” as determined by the states through their SIPs. Under the RHR, states (or the EPA) are directed to conduct BART determinations for such “BART-eligible” sources that may reasonably be anticipated to cause or contribute to any visibility impairment in a Class I area.[8] Rather than requiring source-specific BART controls, states also have the flexibility to adopt an emissions trading program or other alternative program as long as the alternative provides greater reasonable progress towards improving visibility than BART.[9]

    C. BART Alternatives

    An alternative program to BART must meet requirements under 40 CFR 51.308(e)(2) and (e)(3). These requirements for alternative programs relate to the “better-than-BART” test and fundamental elements of any alternative program.

    In order to demonstrate that the alternative program achieves greater reasonable progress than source-specific BART, a state must demonstrate that its SIP meets the requirements in 40 CFR 51.308(e)(2)(i) through (v). The state or the EPA must conduct an analysis of the best system of continuous emission control technology available and the associated reductions for each source subject to BART covered by the alternative program, termed a “BART benchmark.” Where the alternative program has been designed to meet requirements other than BART, simplifying assumptions may be used to establish a BART benchmark.

    Pursuant to 40 CFR 51.308(e)(2)(i)(E), the state or the EPA, must also provide a determination that the alternative program achieves greater reasonable progress than BART under 40 CFR 51.308(e)(3) or otherwise based on the clear weight of evidence. 40 CFR 51.308(e)(3), in turn, provides specific tests applicable under specific circumstances for determining whether the alternative achieves greater reasonable progress than BART. If the distribution of emissions for the alternative program is not substantially different than for BART, and the alternative program results in greater emissions reductions, then the alternative program may be deemed to achieve greater reasonable progress. If the distribution of emissions is significantly different, the differences in visibility between BART and the alternative program, must be determined by conducting dispersion modeling for each impacted Class I area for the best and worst 20 percent of days. This modeling demonstrates “greater reasonable progress” if both of the two following criteria are met: (1) Visibility does not decline in any Class I area; and (2) there is overall improvement in visibility when comparing the average differences between BART and the alternative program across all the affected Class I areas. Alternatively, pursuant to 40 CFR 51.308(e)(2), states may show that the alternative achieves greater reasonable progress than the BART benchmark “based on the clear weight of evidence” determinations. Specific RHR requirements for alternative programs are discussed in more detail in Section III.[10]

    Generally, a SIP addressing regional haze must include emission limits and compliance schedules for each source subject to BART. In addition to the RHR's requirements, general SIP requirements mandate that the SIP include all regulatory requirements related to monitoring, recordkeeping, and reporting for the alternative's enforceable requirements. See CAA section 110(a); 40 CFR part 51, subpart K.

    D. Reasonable Progress Requirements

    In addition to BART requirements, as mentioned previously, each regional haze SIP must contain measures as necessary to make reasonable progress towards the national visibility goal. Finally, the SIP must establish reasonable progress goals (RPGs) for each Class I area within the state for the plan implementation period (or “planning period”), based on the measures included in the long-term strategy.[11] If an RPG provides for a slower rate of improvement in visibility than the rate under which the national goal of no anthropogenic visibility impact would be attained by 2064, the SIP must demonstrate, based on the four reasonable progress factors, why that faster rate is not reasonable and the slower rate provided for by the SIP's state-specific RPG is reasonable.[12]

    E. Consultation With Federal Land Managers (FLMs)

    The RHR requires that a state consult with FLMs before adopting and submitting a required SIP or SIP revision.[13] Further, the EPA, or state when considering a SIP revision, must include in its proposal a description of how it addressed any comments provided by the FLMs.

    F. Requirements for Regional Haze SIPs Submitted Under 40 CFR 51.309

    The EPA's RHR provides two paths to address regional haze. One is 40 CFR 51.308, requiring states to perform individual point source BART determinations and evaluate the need for other control strategies. The other method for addressing regional haze is through 40 CFR 51.309, and is an option for nine states termed the “Transport Region States,” which include: Arizona, California, Colorado, Idaho, Nevada, New Mexico, Oregon, Utah and Wyoming. By meeting the requirements under 40 CFR 51.309, a Transport Region State can be deemed to be making reasonable progress toward the Start Printed Page 55659national goal of achieving natural visibility conditions for the 16 Class I areas on the Colorado Plateau.[14]

    Section 309 requires those Transport Region States that choose to participate to adopt regional haze strategies that are based on recommendations from the Grand Canyon Visibility Transport Commission (GCVTC) for protecting the 16 Class I areas on the Colorado Plateau. The purpose of the GCVTC was to assess information about the adverse impacts on visibility in and around the 16 Class I areas on the Colorado Plateau and to provide policy recommendations to the EPA to address such impacts. The GCVTC determined that all Transport Region States could potentially impact the Class I areas on the Colorado Plateau. The GCVTC submitted a report to the EPA in 1996 for protecting visibility for the Class I areas on the Colorado Plateau, and the EPA codified these recommendations as an option available to states as part of the RHR.[15]

    The EPA determined that the GCVTC strategies would provide for reasonable progress in mitigating regional haze if supplemented by an annex containing quantitative emission reduction milestones and provisions for a trading program or other alternative measure.[16] In September 2000, the Western Regional Air Partnership (WRAP), which is the successor organization to the GCVTC, submitted an annex to the EPA. The annex contained SO2 emissions reduction milestones and detailed provisions of a backstop trading program to be implemented automatically if voluntary measures failed to achieve the SO2 milestones. The EPA codified the annex on June 5, 2003 at 40 CFR 51.309(h).[17]

    Five western states, including Wyoming, submitted implementation plans under section 309 in 2003.[18] The EPA was challenged by the Center for Energy and Economic Development (CEED) on the validity of the annex provisions. In CEED v. EPA, the D.C. Circuit Court of Appeals vacated the EPA approval of the WRAP annex.[19] In response to the court's decision, the EPA vacated the annex requirements adopted under 40 CFR 51.309(h), but left in place the stationary source requirements in 40 CFR 51.309(d)(4).[20] The requirements under 40 CFR 51.309(d)(4) contain general requirements pertaining to stationary sources and market trading, and allow states to adopt alternatives to the point source application of BART.

    Thus, rather than requiring source-specific BART controls as explained previously in Section II.B., states have the flexibility to adopt an emissions trading program or other alternative program if the alternative provides greater reasonable progress than would be achieved by the application of BART pursuant to 40 CFR 51.308(e)(2). Under 40 CFR 51.309, states can satisfy the SO2 BART requirements by adopting SO2 emissions milestones and a backstop trading program. Under this approach, states must establish declining SO2 emissions milestones for each year of the program through 2018. The milestones must be consistent with the GCVTC's goal of 50 to 70 percent reduction in SO2 emissions by 2040. The backstop trading program would be implemented if a milestone is exceeded and the program is triggered.[21]

    G. History of NO X and PM BART Determinations for Naughton Unit 3

    1. PacifiCorp Naughton Unit 3

    The PacifiCorp Naughton Power Plant, located in Lincoln County, Wyoming, is comprised of three pulverized coal-fired units with a total net generating capacity of 700 megawatts (MW). All three boilers are tangentially fired and burn subbituminous coal. Naughton Unit 3 generates a nominal 330 MW and commenced operation in 1971. Naughton Unit 3 is currently equipped with low-NOX burners (LNB) and overfire air (OFA) to control NOX, sodium-based wet flue gas desulfurization to control SO2, and an electrostatic precipitator and flue gas conditioning to control PM.[22] All three units are within the statutory definition of BART-eligible units, and were determined to be subject to BART by Wyoming in its 2011 Regional Haze SIP (discussed below).

    2. 2011 Wyoming Regional Haze SIP

    Wyoming submitted its SIP revision to the EPA on January 12, 2011, to address the requirements of section 309(g) of the RHR. On June 10, 2013, the EPA proposed to approve portions of the Wyoming Regional Haze SIP, including the State's NOX and PM BART determinations for Naughton Unit 3.[23] Specifically, we proposed to approve: (1) Wyoming's NOX BART emission limit of 0.07 lb/MMBtu (30-day rolling average), reflecting the existing LNBs plus OFA and the installation of selective catalytic reduction (SCR), and (2) Wyoming's PM BART emission limit of 0.015 lb/MMBtu, reflecting installation of a new full-scale fabric filter.[24 25] We also proposed to approve the associated compliance dates that required that PacifiCorp comply with the NOX and PM BART emission limits within 5 years from the effective date of our final rule (that is, by March 4, 2019).

    During the public comment period for the EPA's proposed rule, PacifiCorp submitted comments indicating that, in place of installing SCR on Naughton Unit 3 to meet the NOX BART emission limit of 0.07 lb/MMbtu (30-day rolling average), it planned to convert the unit to natural gas firing by the end of 2018. On July 5, 2013, at the request of PacifiCorp, Wyoming issued air quality permit MD-14506 [26] to modify the Naughton Power Plant by converting Unit 3 to fire natural gas. In a meeting with PacifiCorp held on October 31, 2013, the company clarified to the EPA that its comments were a request that the EPA establish emission limits reflecting conversion to natural gas through a FIP. In response to PacifiCorp's request, in our final rule the EPA indicated that while we tentatively supported PacifiCorp's planned conversion of Naughton Unit 3 to burn natural gas, we were unable to impose the associated emission limits Start Printed Page 55660through a FIP.[27] We found no basis to disapprove Wyoming's SIP requirement for Naughton Unit 3 and were therefore obligated to approve them. Accordingly, in a final rule dated January 30, 2014, the EPA approved Wyoming's NOX and PM emission limits for Naughton Unit 3 that reflected the installation of SCR and a new full-scale fabric filter baghouse.[28] At the time, we acknowledged that Wyoming intended to submit a revision to its regional haze SIP for Naughton Unit 3 that would reflect conversion to natural gas. We indicated that we would act on the SIP revision in an expedited timeframe.

    Though we approved Wyoming's NOX and PM BART [29] emission limits for Naughton Unit 3, we disapproved the monitoring, record-keeping, and reporting requirements in the SIP for all BART sources, and promulgated federal requirements in their place for the reasons stated in our January 30, 2014 final rule and June 10, 2013 proposed rule.[30]

    3. Wyoming Regional Haze SIP Revision for Naughton Unit 3

    On November 28, 2017, Wyoming submitted a revision to the Wyoming Regional Haze SIP (“SIP revision”) that provides an alternative to NOX and PM BART for Naughton Unit 3 (“Naughton Unit 3 BART Alternative”). This SIP revision is in Appendix B to Wyoming's 5-year progress report, titled Alternative to BART for NOXand PM for PacifiCorp Naughton Unit 3, and includes five air quality permits for the Naughton Power Plant.[31] The SIP revision is the subject of this proposal.

    III. The SIP Revision for Naughton Unit 3

    A. Summary of the SIP Revision

    The November 28, 2017 SIP revision requires that PacifiCorp cease firing coal at Naughton Unit 3 no later than January 30, 2019.[32] The SIP revision establishes NOX and PM emission limits that reflect firing natural gas, installation of new low-NOX gas burners along with a boiler flue gas recirculation system (FGR) for NOX control, and a limit on annual heat input of 12,964,800 MMBtu/year (based on 12-month rolling average of hourly heat input values [33] ) equal to 40 percent of the maximum design heat input when firing coal.[34] Collectively, these control measures will significantly reduce NOX and PM emissions. The SIP revision includes the associated compliance deadlines, monitoring, recordkeeping and reporting requirements. Finally, the SIP revision includes a determination that the Naughton Unit 3 BART alternative is “better than BART” based on a demonstration that it fulfills the requirements of 40 CFR 51.308(e)(2) for a BART alternative. More information regarding Wyoming's analysis of the BART alternative is set forth below, along with the EPA's evaluation of the analysis.

    B. The EPA's Evaluation of the SIP Revision

    The RHR establishes the requirements for BART alternatives. Three of the requirements are of relevance to our evaluation of the Naughton Unit 3 BART alternative. We evaluate the proposed alternative to the NOX and PM BART requirements in the SIP revision with respect to each of these following elements:

    • A demonstration that the emissions trading program or other alternative measure will achieve greater reasonable progress than would have resulted from the installation and operation of BART at all sources subject to BART in the state and covered by the alternative program.[35]
    • A requirement that all necessary emissions reductions take place during the period of the first long-term strategy for regional haze.[36]
    • A demonstration that the emissions reductions resulting from the alternative measure will be surplus to those reductions resulting from the measures adopted to meet requirements of the CAA as of the baseline date of the SIP.[37]

    Our evaluation draws from Appendix B of the SIP submittal: Alternative to BART for NOXand PM for PacifiCorp Naughton Unit 3.

    1. Demonstration That the Alternative Measure Will Achieve Greater Reasonable Progress

    Pursuant to 40 CFR 51.308(e)(2)(i), a state must demonstrate that the alternative measure will achieve greater reasonable progress than would have resulted from the installation and operation of BART at all sources subject to BART in the state and covered by the alternative program. For a source-specific BART alternative, the critical elements of this demonstration are:

    • A list of all BART-eligible sources within the state;
    • A list of all BART-eligible sources and all BART source categories covered by the alternative program;
    • An analysis of BART and associated emission reductions;
    • An analysis of projected emissions reductions achievable through the BART alternative; and
    • A determination that the alternative achieves greater reasonable progress than would be achieved through the installation and operation of BART.

    We summarize the SIP revision with respect to each of these elements and provide our evaluation in the proceeding sections.

    • A List of All BART-Eligible Sources Within the State

    Table 1 shows a list of all BART-eligible sources in the State of Wyoming.

    Table 1—Wyoming BART-Eligible Sources

    CompanyFacility
    PacifiCorpJim Bridger.
    Basin ElectricLaramie River.
    PacifiCorpDave Johnston.
    PacifiCorpNaughton.
    PacifiCorpWyodak.
    FMCWestvaco.
    General ChemicalGreen River.
    Black HillsNeil Simpson 1.
    SinclairSinclair Refinery.
    SinclairCasper Refinery.
    FMCGranger.
    Dyno NobelDyno Nobel.
    OCI WyomingOCI Wyoming.
    P4 ProductionP4 Production.

    • A List of All BART-Eligible Sources and All BART Source Categories Covered by the BART Alternative Program

    Table 2 shows a list of all the BART-eligible sources covered by the BART Start Printed Page 55661alternative program along with the BART source category.

    Table 2—Wyoming Subject-to-BART Sources Covered by the Alternative

    CompanyFacilitySubject-to-BART unitsSource category
    PacifiCorpNaughton Power PlantUnit 3Electrical generating units.

    • Analysis of BART and Associated Emission Reductions

    Pursuant to 40 CFR 51.308(e)(2)(i)(C), the SIP must include an analysis of BART and associated emission reductions at Naughton Unit 3. As noted above, Wyoming's BART analyses and determinations for Naughton Unit 3 were included in the 2011 Wyoming Regional Haze SIP. The EPA approved Wyoming's NOX BART emission limit of 0.07 lb/MMBtu (30-day rolling average) for Naughton Unit 3 that reflected existing LNBs plus OFA with the installation of SCR.[38] In addition to the NOX BART emission limit of 0.07 lb/MMBtu approved by the EPA, the 2011 SIP included NOX emission limits of 259 lb/hr (30-day rolling average) and 1,134 tons/year. We also approved Wyoming's PM BART emission limit of 0.015 lb/that reflected installation of a new full-scale fabric filter.[39] In addition to the PM BART emission limit of 0.015 lb/MMBtu approved by the EPA, the 2011 SIP included PM emission limits of 56 lb/hr and 243 tons/year. These BART determinations are shown in the SIP revision, and are summarized in Table 3 below.

    Table 3—Summary of Wyoming's NOX and PM BART Determinations for Naughton Unit 3

    Permitted controlsNOXPM
    SCR, New Fabric Filter Baghouse0.07 lb/MMBtu (30-day rolling) 259 lb/hr (30-day rolling) 1,134 tons/yr0.015 lb/MMBtu. 56 lb/hr. 243 tons/yr.

    We propose to find that Wyoming has met the requirement for an analysis of BART and associated emission reductions achievable at Naughton Unit 3 under 40 CFR 51.308(e)(2)(i)(C). Note that the emission reductions associated with BART, when expressed in tons reduced per year, are shown in the section that follows.

    • Analysis of Projected Emissions Reductions Achievable Through the BART Alternative

    Pursuant to 40 CFR 51.308(e)(2)(i)(D), the SIP must include an analysis of projected emissions reductions achievable through the BART alternative. The BART alternative achieves emission reductions through the following control measures: conversion of the unit to natural gas firing, installation of new low-NOX gas burners and FGR for NOX control, and a limit on annual heat input equal to 40 percent of the maximum design heat input (when burning coal), or 12,964,800 MMBtu/year. The SIP revision includes an analysis of the projection emissions and emissions reductions associated with these alternative control measures as reproduced in Tables 4 and 5 below.

    Table 4—Naughton Unit 3 Emission Limits When Converted to Natural Gas

    Permitted controlsNOXPM
    New LNB, FGR0.12 lb/MMBtu (30-day rolling) 250 lb/hr (30-day rolling) 519 tons/yr0.008 lb/MMBtu. 30 lb/hr. 52 tons/yr.

    Table 5—Naughton Unit 3 Emission Comparison When Converted to Natural Gas

    FuelPermitted controlsNOXPM
    lb/MMbtulb/hrtons/yrlb/MMbtulb/hrtons/yr
    CoalSCR, Fabric Filter0.072591,1340.01556243
    Natural GasNew LNB, FGR, heat input limit0.122505190.0083052
    Additional Reduction96150.00726191

    Here we note that Wyoming calculated the annual emission reductions achievable through BART based on a potential-to-emit (i.e., allowable) emissions basis. For example, Wyoming calculated the annual emissions for NOX under the BART scenario by multiplying the unit's maximum hourly heat input when Start Printed Page 55662combusting coal of 3,700 MMbtu/hr by the emission limit of 0.07 lb/MMBtu (30-day rolling average). Wyoming then converted the resulting value of 259 lb/hr to a tons/yr basis (3700 MMBtu/hr × 0.07 lb/MMBtu × 8760 hr/yr × 1 ton/2000 lb = 1,134 tons/yr). Wyoming's calculation for BART assumes that the unit would be operated at the maximum design heat input of 3,700 MMBtu/hr for the entire year (8,760 hours), yielding an annual heat input of 32,412,000 MMBtu. We disagree with the calculation methodology Wyoming used to calculate the annual emission reductions achievable with BART because they were based on a potential-to-emit basis. By contrast, in our analysis of NOX BART associated with the 2011 SIP, consistent with the BART Guidelines,[40] we calculated the projected emissions with SCR based on past actual practice rather than the potential-to-emit. Our calculations reflected the actual operation of Naughton Unit 3 during the baseline period of 2001-2003 during which the heat input of the unit was 24,856,366 MMBtu.[41] In addition, as opposed to using the 30-day rolling average emission limit of 0.07 lb/MMBtu, the EPA used the anticipated annual emission rate with SCR of 0.05 lb/MMbtu.[42] Since that time, the 0.05 lb/MMBtu annual emission rate has been demonstrated at other PacifiCorp EGUs in Wyoming that have been retrofitted with SCR and that burn similar coal to Naughton Unit 3.[43] The result is that the EPA calculated that the projected actual annual NOX emissions with SCR would be 621 tons/year [44] (as opposed to 1,134 tons/year calculated by Wyoming). Because the value of 621 tons/year was calculated consistent with the procedures outlined in the BART Guidelines, and reflects the projected actual emissions that would have been achieved with SCR, it sets the appropriate benchmark for making the better-than-BART comparison. To ensure an apples-to-apples comparison, it is also appropriate to calculate the projected annual emissions anticipated with the BART alternative in a commensurate manner to that for BART (i.e., based on projected actual rather than allowable emissions). Nonetheless, even if annual emissions for the BART alternative are calculated based on an allowable emissions basis as Wyoming has done, the allowed annual emissions for the BART alternative of 519 tons/year is lower than the EPA's estimate for BART (SCR) of 621 tons/year. Therefore, regardless of whether the emission reductions achievable with the BART alternative are assessed on a projected actual or allowable emissions basis, the anticipated NOX emissions are lower under the BART alternative than they are under BART. The same conclusion holds true for PM. Therefore, while we disagree with the State's potential-to-emit (allowable) methodology, we propose to agree with the State's conclusion that the emissions reductions achievable through the alternative measure are better-than-BART. 40 CFR 51.308(e)(2)(i)(D).

    • Determination That the Alternative Achieves Greater Reasonable Progress Than Would Be Achieved Through the Installation and Operation of BART

    Pursuant to 40 CFR 51.308(e)(2)(i)(E), the SIP revision must provide a determination under 40 CFR 51.308(e)(3) or otherwise based on the clear weight of evidence that the alternative achieves greater reasonable progress than BART. Two different tests for determining whether the alternative achieves greater reasonable progress than BART are outlined in 40 CFR 51.308(e)(3). Under the first test, if the distribution of emissions is not substantially different than under BART, and the alternative measure results in greater emission reductions, then the alternative measure may be deemed to achieve greater reasonable progress. Under the second test, if the distribution of emissions is significantly different, then dispersion modeling must be conducted to determine differences between BART and the BART alternative for each impacted Class I area for the worst and best 20 percent days. The modeling would demonstrate “greater reasonable progress” if both of the following criteria are met: (1) Visibility does not decline in any Class I area; and (2) there is an overall improvement in visibility, determined by comparing the average differences between BART and the alternative over all affected Class I areas. This modeling test is sometimes referred to as the “two-prong test.”

    As stated in the SIP revision, the emissions reductions under PacifiCorp's BART alternative will occur at the same unit, and therefore the distribution of emissions under BART and the better-than-BART alternative are not substantially different. Accordantly, if the BART alternative results in greater emission reductions, then it may be deemed to achieve greater reasonable progress. The SIP revision includes an analysis of the emission reductions achievable with the BART alternative as compared to BART which indicates that the BART alternative achieves greater emission reductions. As indicated in section E. above, the BART alternative will achieve additional NOX reductions and additional PM reductions that are greater than achieved by BART.[45] Therefore, we propose to find that Wyoming's conclusion that the BART alternative achieves greater reasonable progress than would be achieved through the installation and operation of BART is appropriate. 40 CFR 51.308((e)(2)(i)(E).

    2. A Requirement That All Necessary Emissions Reductions Take Place During the Period of the First Long-Term Strategy for Regional Haze

    Pursuant to 40 CFR 51.308(e)(2)(iii), all necessary emission reductions must take place during the period of the first long-term strategy for regional haze. The RHR further provides that, to meet this requirement, a detailed description of the alternative measure, including schedules for implementation, the emission reductions required by the program, all necessary administrative and technical procedures for implementing the program, rules for accounting and monitoring emissions, and procedures for enforcement.

    The SIP revision requires PacifiCorp to cease firing coal at Naughton Unit 3 no later than January 30, 2019.[46] Because no emissions will occur between the date that PacifiCorp must cease firing coal, and when the unit is converted to fire natural gas, the SIP revision achieves emission reductions before the original BART compliance date of March 4, 2019. As a result, we do not find that it is appropriate to disapprove this aspect of the BART alternative.

    In addition, Wyoming has included the relevant implementation schedules, monitoring, reporting and record keeping requirements in the SIP revision as presented in section VI of this action. Accordingly, we propose to Start Printed Page 55663find that the BART alternative meets the requirements of 40 CFR 51.308(e)(2)(iii).

    3. Demonstration That Emissions Reductions From the Alternative Measure Will Be Surplus

    Pursuant to 40 CFR 51.308(e)(2)(iv), the SIP must demonstrate that the emissions reductions resulting from the BART alternative measure will be surplus to those reductions resulting from measures adopted to meet requirements of the CAA as of the baseline date of the SIP. The baseline date for regional haze SIPs is 2002. All the NOX and PM emission reductions required by the BART alternative will occur in the future and are surplus to reductions resulting from SIP measures applicable to Naughton Unit 3 as of 2002. Therefore, we propose to find that the BART alternative complies with 40 CFR 51.308(e)(2)(iv).

    In sum, we propose to find that the BART alternative meets all the applicable requirements of 40 CFR 51.308(e)(2).

    IV. Clean Air Act Section 110(l)

    Under CAA section 110(l), the EPA cannot approve a plan revision “if the revision would interfere with any applicable requirement concerning attainment and reasonable further progress (as defined in section 7501 of this title), or any other applicable requirement of this chapter.” [47] The previous sections of the action explain how the SIP revision will comply with applicable regional haze requirements and general implementation plan requirements such as enforceability. With respect to requirements concerning attainment and reasonable further progress, the Wyoming Regional Haze SIP, as revised by this action, will result in a significant reduction in emissions compared to current levels. Moreover, the SIP revision will result in decreased future NOX and PM emissions as compared to the prior SIP, and will therefore achieve greater reasonable progress than the prior SIP. In addition, the area where the Naughton Unit 3 is located has not been designated nonattainment for any National Ambient Air Quality Standards (NAAQS). Thus, the revisions will ensure a significant reduction in NOX and PM emissions compared to current levels in an area that has not been designated nonattainment for the relevant NAAQS at those current levels. Accordingly, we propose to find that these revisions satisfy section 110(l).

    V. Consultation With FLMs

    There are seven Class I areas in the State of Wyoming. The United States Forest Service (USFS) manages the Bridger Wilderness, Fitzpatrick Wilderness, North Absaroka Wilderness, Teton Wilderness and Washakie Wilderness. The National Park Service (NPS) manages the Grand Teton National Park and Yellowstone National Park. The RHR grants the FLMs a special role in the review of regional haze implementation plans, summarized in section II.E of this preamble.

    Under 40 CFR 51.308(i)(2), Wyoming was obligated to provide the USFS and the NPS with an opportunity for consultation in development of the State's proposed SIP revision no less than 60 days prior to the associated public hearing or public comment opportunity. The SIP revision does not describe whether this consultation occurred. Nonetheless, Wyoming made the SIP revision for Naughton Unit 3 available to the public on June 5, 2017. The State's SIP submittal does not include any comments from the FLMs on its SIP revision for Naughton Unit 3 during the public comment period. Additionally, the FLMs will have an opportunity to comment during the public comment period for this action. We propose to find that while Wyoming did not state in its proposed SIP revision that it fully met its obligation to provide the FLMs with an opportunity for consultation in development of the SIP revision, the FLMs will have nevertheless been provided with two opportunities to comment.

    VI. The EPA's Proposed Action

    In this action, the EPA is proposing to approve Wyoming's SIP revision for the Alternative to BART for NOX and PM for PacifiCorp Naughton Unit 3, including the associated emission and operational limitations, compliance dates, and monitoring, record keeping, and reporting requirements. Specifically, the EPA is proposing to approve the following federally enforceable elements of the SIP revision for Naughton Unit 3:

    • The NOX and PM emission limits found in Wyoming air quality permits MD-15946 (condition 5, lb/hr and tons/year) and P0021110 (condition 7, lb/MMbtu).
    • The operational limit on annual heat input of 12,964,800 MMBtu (based on 12-month rolling average of hourly heat input values) found in Wyoming air quality permit P0021110 (condition 18).
    • The compliance dates found in Wyoming air quality permit P0021110; specifically including that PacifiCorp shall (1) remove the coal pulverizers from service (cease firing coal) by January 30, 2019 (P0021110, condition 19), (2) comply with the NOX and PM emission limits in lb/MMBtu upon conversion to natural gas firing (P0021110, condition 7), and (3) comply with the heat input limit by January 30, 2019 (P0021110, condition 18).
    • The compliance dates found in Wyoming air quality permit MD-15946 (conditions 5 and 6), requiring that PacifiCorp comply with the NOX and PM emission limits in lb/hr and tons/year upon completion of the initial performance tests.
    • The monitoring, record keeping, and reporting requirements found in air quality permit P0021110 (NOX CEMs, conditions 8 and 9; heat input, condition 18; PM stack testing, condition 10; reporting, conditions 4, 11, 12, 13, 14, 19; record keeping, condition 17; notification, conditions 4 and 6; good practice, condition 21; credible evidence, condition 24).

    VII. Incorporation by Reference

    In this rule, the EPA is proposing to include regulatory text in an EPA final rule that includes incorporation by reference. In accordance with requirements of 1 CFR 51.5, the EPA is proposing to incorporate by reference the SIP amendments described in section VI. of this preamble. The EPA has made, and will continue to make, these materials generally available through www.regulations.gov and at the EPA Region 8 Office (please contact the person identified in the “For Further Information Contact” section of this preamble for more information).

    VIII. Statutory and Executive Order Reviews

    Under the CAA, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, the EPA's role is to approve state choices, provided that they meet the criteria of the CAA. Accordingly, this action merely proposes to approve state law as meeting federal requirements and does not impose additional requirements Start Printed Page 55664beyond those imposed by state law. For that reason, this action:

    • Is not a “significant regulatory action” subject to review by the Office of Management and Budget under Executive Orders 12866 (58 FR 51735, October 4, 1993) and 13563 (76 FR 3821, January 21, 2011);
    • Is not an Executive Order 13771 (82 FR 9339, February 2, 2017) regulatory action because SIP approvals are exempted under Executive Order 12866;
    • Does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
    • Is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.);
    • Does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4);
    • Does not have federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999);
    • Is not an economically significant regulatory action based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997);
    • Is not a significant regulatory action subject to Executive Order 13211 (66 FR 28355, May 22, 2001);
    • Is not subject to requirements of section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA; and
    • Does not provide the EPA with the discretionary authority to address, as appropriate, disproportionate human health or environmental effects, using practicable and legally permissible methods, under Executive Order 12898 (59 FR 7629, February 16, 1994).

    In addition, the SIP is not approved to apply on any Indian reservation land or in any other area where the EPA or an Indian tribe has demonstrated that a tribe has jurisdiction. In those areas of Indian country, the proposed rule does not have tribal implications and will not impose substantial direct costs on tribal governments or preempt tribal law as specified by Executive Order 13175 (65 FR 67249, November 9, 2000).

    Start List of Subjects

    List of Subjects in 40 CFR Part 52

    • Environmental protection
    • Air pollution control
    • Incorporation by reference
    • Intergovernmental relations
    • Nitrogen dioxide
    • Particulate matter
    • Sulfur oxides
    End List of Subjects Start Signature

    Dated: November 2, 2018.

    Douglas Benevento,

    Regional Administrator, EPA Region 8.

    End Signature

    40 CFR part 52 is proposed to be amended as follows:

    Start Part

    PART 52—APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS

    End Part Start Amendment Part

    1. The authority citation for part 52 continues to read as follows:

    End Amendment Part Start Authority

    Authority: 42 U.S.C. 7401 et seq.

    End Authority

    Subpart ZZ—Wyoming

    Start Amendment Part

    2. Section 52.2620 is amended by adding in paragraph (d), the entry “Naughton Unit 3” at the end of the table; and by adding in paragraph (e), in numerical order, the entry “(32) XXXII” to read as follows:

    End Amendment Part
    Identification of plan.
    * * * * *

    (d) * * *

    RegulationRule titleState effective dateEPA effective dateFinal rule citation/dateComments
    *         *         *         *         *         *         *
    Naughton Unit 3Air Quality SIP Permits containing BART Alternative requirements, MD-15946 and P0021110November 28, 2017December 7, 2018[Federal Register citation] November 7, 2018Only the following permit provisions: NOX and PM emission limits (P0021110, condition 7; MD-15946, condition 5); emission limit compliance dates (P0021110, condition 7; MD-15946, conditions 5 and 6); heat input limit and compliance date (P0021110, condition 18); compliance date for coal pulverizers to be removed from service (P0021110, condition 19); and associated monitoring, recordkeeping, and reporting requirements (P0021110, conditions 4, 6, 8, 9, 10, 11, 12, 13, 14, 17, 18, 19, 21, and 24).

    (e) * * *Start Printed Page 55665

    Rule No.Rule titleState effective dateEPA effective dateFinal rule citation dateComments
    *         *         *         *         *         *         *
    (32) XXXIIWyoming State Implementation Plan 5-Year Progress Report for Regional Haze, Appendix B: Alternative to BART for NOX and PM for PacifiCorp Naughton Unit 3November 28, 2017December 7, 2018[Federal Register citation], November 7, 2018Only includes Appendix B: Alternative to BART for NOX and PM for PacifiCorp Naughton Unit 3.
    Start Amendment Part

    3. Section 52.2636 is amended by revising paragraph (a)(1)(vii) and amending paragraph(c)(1) by revising Table 1 to § 52.2636 to read as follows:

    End Amendment Part
    Implementation plan for regional haze.

    (a) * * *

    (1) * * *

    (vii) PacifiCorp Naughton Power Plant Units 1 and 2 (PM and NOX); and

    * * * * *

    (c) * * *

    (1) * * *

    Table 1 to § 52.2636

    [Emission limits for BART units for which EPA approved the State's BART and Reasonable Progress determinations]

    Source name/BART unitPM emission limits—lb/MMBtuNOX emission limits—lb/MMBtu (30-day rolling average)
    FMC Westvaco Trona Plant/Unit NS-1A0.050.35
    FMC Westvaco Trona Plant/Unit NS-1B0.050.35
    TATA Chemicals Partners (General Chemical) Green River Trona Plant/Boiler C0.090.28
    TATA Chemicals Partners (General Chemical) Green River Trona Plant/Boiler D0.090.28
    Basin Electric Power Cooperative Laramie River Station/Unit 10.03N/A
    Basin Electric Power Cooperative Laramie River Station/Unit 20.03N/A
    Basin Electric Power Cooperative Laramie River Station/Unit 30.03N/A
    PacifiCorp Dave Johnston Power Plant/Unit 30.015N/A
    PacifiCorp Dave Johnston Power Plant/Unit 40.0150.15
    PacifiCorp Jim Bridger Power Plant/Unit 110.030.26/0.07
    PacifiCorp Jim Bridger Power Plant/Unit 210.030.26/0.07
    PacifiCorp Jim Bridger Power Plant/Unit 310.030.26/0.07
    PacifiCorp Jim Bridger Power Plant/Unit 410.030.26/0.07
    PacifiCorp Naughton Power Plant/Unit 10.040.26
    PacifiCorp Naughton Power Plant/Unit 20.040.26
    PacifiCorp Wyodak Power Plant/Unit 10.015N/A
    1 The owners and operators of PacifiCorp Jim Bridger Units 1, 2, 3, and 4 shall comply with the NOX emission limit for BART of 0.26 lb/MMBtu and PM emission limit for BART of 0.03 lb/MMBtu and other requirements of this section by March 4, 2019. The owners and operators of PacifiCorp Jim Bridger Units 1, 2, 3 and 4 shall comply with the NOX emission limit for reasonable progress of 0.07 lb/MMBtu by: December 31, 2022, for Unit 1, December 31, 2021, for Unit 2, December 31, 2015, for Unit 3, and December 31, 2016, for Unit 4.
    * * * * *
    End Supplemental Information

    Footnotes

    1.  Although states and tribes may designate as Class I additional areas which they consider to have visibility as an important value, the requirements of the visibility program set forth in section 169A of the CAA apply only to “mandatory Class I Federal areas.”

    Back to Citation

    2.  42 U.S.C. 7491(a). Areas designated as mandatory Class I Federal areas consist of national parks exceeding 6,000 acres, wilderness areas and national memorial parks exceeding 5,000 acres, and all international parks that were in existence on August 7, 1977. 42 U.S.C. 7472(a). In accordance with section 169A of the CAA, the EPA, in consultation with the Department of Interior, promulgated a list of 156 areas where visibility is identified as an important value. 44 FR 69122 (November 30, 1979). The extent of a mandatory Class I area includes subsequent changes in boundaries, such as park expansions. 42 U.S.C. 7472(a). Although states and tribes may designate as Class I additional areas whose visibility they consider to be an important value, the requirements of the visibility program set forth in section 169A of the CAA apply only to “mandatory Class I Federal areas.” Each mandatory Class I Federal area is the responsibility of a “Federal Land Manager.” 42 U.S.C. 7602(i). When we use the term “Class I area” in this section, we mean a “mandatory Class I Federal area.”

    Back to Citation

    3.  64 FR 35714, 35714 (July 1, 1999) (codified at 40 CFR part 51, subpart P).

    Back to Citation

    4.  The EPA had previously promulgated regulations to address visibility impairment in Class I areas that is “reasonably attributable” to a single source or small group of sources, i.e., reasonably attributable visibility impairment (RAVI). 45 FR 80084, 80084 (December 2, 1980).

    Back to Citation

    5.  82 FR 3078 (January 10, 2017).

    Back to Citation

    6.  42 U.S.C. 7410(a), 7491, and 7492(a); CAA sections 110(a), 169A, and 169B.

    Back to Citation

    8.  40 CFR 51.308(e). The EPA designed the Guidelines for BART Determinations Under the Regional Haze Rule (Guidelines) 40 CFR Appendix Y to part 51 “to help States and others (1) identify those sources that must comply with the BART requirement, and (2) determine the level of control technology that represents BART for each source.” Guidelines, Section I.A. Section II of the Guidelines describes the four steps to identify BART sources, and Section III explains how to identify BART sources (i.e., sources that are “subject to BART”).

    Back to Citation

    9.  40 CFR 51.308(e)(2). WildEarth Guardians v. EPA, 770 F.3d 919 (10th Cir. 2014).

    Back to Citation

    14.  The Colorado Plateau is a high, semi-arid tableland in southeast Utah, northern Arizona, northwest New Mexico, and western Colorado. The 16 mandatory Class I areas are: Grand Canyon National Park, Mount Baldy Wilderness, Petrified Forest National Park, Sycamore Canyon Wilderness, Black Canyon of the Gunnison National Park Wilderness, Flat Tops Wilderness, Maroon Bells Wilderness, Mesa Verde National Park, Weminuche Wilderness, West Elk Wilderness, San Pedro Park Wilderness, Arches National Park, Bryce Canyon National Park, Canyonlands National Park, Capital Reef National Park and Zion National Park.

    Back to Citation

    15.  64 FR 35714, 35749 (July 1, 1999).

    Back to Citation

    16.  64 FR 35714, 35749, 35756 (July 1, 1999).

    Back to Citation

    17.  68 FR 33764, 33767 (June 5, 2003).

    Back to Citation

    18.  Five states—Arizona, New Mexico, Oregon, Utah and Wyoming—and Albuquerque-Bernalillo County, New Mexico, initially exercised this option by submitting plans to the EPA in December 2003. Oregon elected to cease participation in 2006, and Arizona elected to cease participation in 2010.

    Back to Citation

    19.  Ctr. for Energy & Econ. Dev. v. EPA, 398 F.3d 653, 654 (D.C. Cir. 2005).

    Back to Citation

    20.  71 FR 60612 (October 13, 2006).

    Back to Citation

    22.  PM includes both PM10 and PM2.5. See Definitions.

    Back to Citation

    23.  78 FR 34738 (June 10, 2013); 78 FR 34760 (June 10, 2013).

    Back to Citation

    24.  The BART requirement is met through compliance with the specified emission limit, and may be achieved through measures other than the referenced control technology.

    25.  Wyoming's 2011 SIP also contained NOX emission limits of 259 lb/hr (30-day rolling average) and 1,134 tons/year, and PM emission limits of 56 lb/hr and 243 tons/year. These hourly and annual limits are the product of the respective lb/MMBtu emission limit and the design heat input for an hour or year. However, EPA's SIP approval only included the lb/MMBtu emission limits.

    Back to Citation

    26.  The emission limits and other requirements associated with the BART alternative were superseded by subsequent permits.

    Back to Citation

    27.  79 FR 5045 (January 30, 2014).

    Back to Citation

    28.  79 FR 5220, 5221 (January 30, 2014).

    Back to Citation

    29.  Separately, under 40 CFR 51.309, Wyoming submitted a SIP satisfying BART requirements for SO2 by adopting SO2 emission milestones and a backstop trading program. We finalized approval of Wyoming's 309 program for SO2 on December 12, 2012. 77 FR 73926 (December 12, 2012).

    Back to Citation

    30.  79 FR 5221, 5222 (January 30, 2014).

    Back to Citation

    31.  Appendix B to the SIP contains the State's better than BART demonstration (PDF pp. 184-193) and five air quality permits issued by the State of Wyoming for the Naughton Power Plant. Permit Nos. P0021110 (March 7, 2017), PDF pp. 194-198; P0021918 (November 18, 2016), PDF pp. 199-200; MD-15946 (March 20, 2014), PDF pp. 201-205; MD-14506 (July 5, 2013), PDF pp. 206-215; and MD-6042A2 (March 7, 2012), PDF pp. 216-220.

    Back to Citation

    32.  The coal pulverizers will be removed from service.

    Back to Citation

    33.  The EPA understands the “12-month rolling average heat input of hourly heat input values” to mean that the hourly heat input values are summed for each month, and that these monthly values are then averaged on a rolling 12-month basis.

    Back to Citation

    34.  The State's SIP explains that “. . . PacifiCorp will no longer operate the unit as a base-load Electric Generating Unit (EGU). Instead it will be operated as a peaking unit with a maximum annual heat input factor of 40%, or 12,964,800 MMBtu based on 12-month rolling average of hourly heat input values.” SIP Appendix B at p. 3.

    Back to Citation

    38.  79 FR 5045 (January 30, 2014).

    Back to Citation

    39.  Ibid.

    Back to Citation

    40.  In general, for the existing sources subject-to-BART, you will estimate the anticipated annual emissions based upon actual emissions from a baseline period. 70 FR 39167 (July 5, 2005, emphasis added).

    Back to Citation

    41.  Heat input data was obtained from the EPA Air Markets Program Data.

    Back to Citation

    42.  79 FR 5043, Table 14 (January 30, 2014); 79 FR 5167 (January 30, 2014).

    Back to Citation

    43.  Refer to the EPA Air Markets Program Data for Jim Bridger Power Plant Units 3 and 4 where SCR was installed in 2015 and 2016, respectively.

    Back to Citation

    44.  Andover Technology Partners, “Cost of NOX Controls on Wyoming EGUs”, October 28, 2013; “Wyoming EGU BART and Reasonable Progress Cost,” 10/28/2013. Docket ID EPA-R08-OAR-2012-0026-0241.

    Back to Citation

    45.  These values are based on a comparison of allowable emissions. See discussion regarding allowable versus actual emissions in preceding section.

    Back to Citation

    46.  Appendix B, p. 2 (PDF p. 187). The associated emission and operational limits apply upon conversion of Naughton Unit 3 to fire natural gas.

    Back to Citation

    47.  Note that “reasonable further progress” as used in CAA section 110(l) is a reference to that term as defined in section 301(a) (i.e., 42 U.S.C. 7501(a)), and as such means reductions required to attain the National Ambient Air Quality Standards (NAAQS) set for criteria pollutants under section 109. This term as used in section 110(l) (and defined in section 301(a)) is not synonymous with “reasonable progress” as that term is used in the regional haze program. Instead, section 110(l) provides that the EPA cannot approve plan revisions that interfere with regional haze requirements (including reasonable progress requirements) insofar as they are “other applicable requirement[s]” of the CAA.

    Back to Citation

    [FR Doc. 2018-24372 Filed 11-6-18; 8:45 am]

    BILLING CODE 6560-50-P

Document Information

Published:
11/07/2018
Department:
Environmental Protection Agency
Entry Type:
Proposed Rule
Action:
Proposed rule.
Document Number:
2018-24372
Dates:
Written comments must be received on or before December 7, 2018.
Pages:
55656-55665 (10 pages)
Docket Numbers:
EPA-R08-OAR-2018-0607, FRL-9986-03-Region 8
Topics:
Air pollution control, Environmental protection, Incorporation by reference, Intergovernmental relations, Nitrogen dioxide, Particulate matter, Sulfur oxides
PDF File:
2018-24372.pdf
Supporting Documents:
» PacifiCorp Jim Bridger AMPD with SCR
» Naughton Unit 3 AMPD annual with heat input
» Governor Mead Letter to R8 Adminstrator Benevento Requesting Approval - Signed_11-28-17
» 3 - Wyoming RH 2013 Progress Report 11-17-17
» 2 - Regional Haze Public Comment Material 11-17-17
» 1 - Letter of Legal Authority re RH SIP (11-17-2017)
CFR: (2)
40 CFR 52.2620
40 CFR 52.2636