94-27612. Tennessee Valley Authority Watts Bar Nuclear Plant, Unit 1; Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 59, Number 215 (Tuesday, November 8, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-27612]
    
    
    [[Page Unknown]]
    
    [Federal Register: November 8, 1994]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-390]
    
     
    
    Tennessee Valley Authority Watts Bar Nuclear Plant, Unit 1; 
    Environmental Assessment and Finding of No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an extension of the latest construction 
    completion date specified in Construction Permit No. CPPR-91 issued to 
    Tennessee Valley Authority (permittee) for Watts Bar Nuclear Plant 
    (WBN), Unit 1. The facility is located at the permittee's site on the 
    west bank of the Tennessee River approximately 50 miles northeast of 
    Chattanooga, Tennessee.
    
    Environmental Assessment
    
    Identification of Proposed Action
    
        The proposed action would extend the latest construction completion 
    date of Construction Permit No. CPPR-91 from December 31, 1994, to 
    December 31, 1995. The proposed action is in response to the 
    permittee's request dated September 19, 1994.
    
    The Need for the Proposed Action
    
        The proposed action is needed because the construction and 
    modification of the facility is not yet fully completed. Following 
    completion of hot functional testing, the permittee conducted an 
    extensive review of the remaining scope of work required to complete 
    the unit. The resulting detailed completion plan indicates fuel load 
    for the unit will occur in the spring of 1995. The requested extension 
    period includes contingency in case any adjustments to the schedule are 
    needed.
        The delays associated with the above efforts to ensure that WBN 
    meets regulatory requirements and licensing commitments make it 
    necessary for the permittee to request an extension of the expiration 
    date for Construction Permit No. CPPR-91 until December 31, 1995.
    
    Environmental Impacts of the Proposed Action
    
        The environmental impacts associated with the construction of the 
    facility have been previously discussed and evaluated in the staff's 
    Final Environmental Statement (FES) issued on November 9, 1972 for the 
    construction permit stage which covered construction of both units. The 
    FES issued in December 1978 for the operating license stage addressed 
    the environmental impacts of construction activities not addressed 
    previously. The activities included: (1) construction of the new 
    transmission route for the Watts Bar--Volunteer 500 kV line, (2) 
    construction of the settling pond for siltation control for 
    construction runoff at a different location from that originally 
    proposed in the Final Environmental Statement--Construction Permit 
    (FES-CP), (3) the relocation of the blowdown diffuser from the 
    originally proposed site indicated in the FES-CP. The staff addressed 
    the terrestrial and aquatic environmental impacts in the Final 
    Environmental Statement--Operating license (FES-OL) and concluded that 
    the assessment presented in the FES-CP remains valid. The staff is 
    currently reviewing updated environmental information and plans to 
    issue findings in a supplement to the FES-OL in early 1995. The 
    construction of Unit 1 is essentially 100 percent complete; therefore, 
    most of the construction impacts discussed in the FES have already 
    occurred.
        Since this action would only extend the period of construction, it 
    does not involve impacts different from those described and analyzed in 
    the original environmental impact statement. The proposed extension 
    will not allow any work to be performed that is not already allowed by 
    the existing construction permit. The extension will merely grant the 
    permittee more time to complete construction and modification in 
    accordance with the previously approved construction permit. The 
    activities related to the various corrective activities will result in 
    additional workforce, being primarily engineering and technical 
    personnel rather than construction personnel. At the present time, this 
    workforce is basically dedicated to the completion of Unit 1. This 
    previously increased workforce is declining as the corrective 
    activities are completed and the unit approaches fuel loading. A large 
    percentage of the additional workforce is contractors and consultants 
    who do not live in the area and use only temporary quarters. While the 
    current workforce level has caused a temporary, increased demand for 
    services in the community and increased traffic on local roads, there 
    are no major impacts due to the arrival of workers' families and 
    demands for services necessary to support permanent residents (for 
    example, housing and schools).
        Based on the foregoing, the NRC staff has concluded that the 
    proposed action would have no significant environmental impact. Since 
    this action would only extend the period of construction activities 
    described in the FES, it does not involve any different impacts or a 
    significant change to those impacts described and analyzed in the 
    original environmental impact statement. Consequently, an environmental 
    impact statement addressing the proposed action is not required.
    
    Alternatives Considered
    
        A possible alternative to the proposed action would be to deny the 
    request. Under this alternative, the permittee would not be able to 
    complete construction of the facility. This would result in denial of 
    the benefit of power production. This option would not eliminate the 
    environmental impacts of construction already incurred.
        If construction were halted and not completed, site redress 
    activities would restore some small areas to their natural states. This 
    would be a slight environmental benefit, but much outweighed by the 
    economic losses from denial of use of a facility that is nearly 
    completed. Therefore, this alternative is rejected.
    
    Alternative Use of Resources
    
        This action does not involve the use of resources not previously 
    considered in the FES for Watts Bar.
    
    Agencies and Persons Consulted
    
        The NRC staff reviewed the permittee's request and applicable 
    documents referenced therein that support this extension. The NRC did 
    not consult other agencies or persons.
    
    Finding of No Significant Impact
    
        The Commission has determined not to prepare an environmental 
    impact statement for this action. Based upon the environmental 
    assessment, the staff concludes that this action will not have a 
    significant effect on the quality of the human environment.
        For details with respect to this action, see the request for 
    extension dated September 19, 1994, which is available for public 
    inspection at the Commission Public Document Room, 2120 L Street NW., 
    Washington, D.C. and at the Local Public Document Room, Chattanooga-
    Hamilton County Library, 1001 Broad Street, Chattanooga, Tennessee 
    37402.
    
        Dated at Rockville, Maryland this 31st day of October 1994.
    
        For the Nuclear Regulatory Commission.
    Frederick J. Hebdon,
    Director, Project Directorate II-4, Division of Reactor Projects I/II, 
    Office of Nuclear Reactor Regulation.
    [FR Doc. 94-27612 Filed 11-7-94; 8:45 am]
    BILLING CODE 7590-01-M
    
    
    

Document Information

Published:
11/08/1994
Department:
Nuclear Regulatory Commission
Entry Type:
Uncategorized Document
Document Number:
94-27612
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: November 8, 1994, Docket No. 50-390