96-28742. Northeast Utilities Millstone Nuclear Power Station, Unit 1; Issuance of Director's Decision Under 10 CFR 2.206  

  • [Federal Register Volume 61, Number 218 (Friday, November 8, 1996)]
    [Notices]
    [Pages 57914-57917]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-28742]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-245, License No. DPR-21]
    
    
    Northeast Utilities Millstone Nuclear Power Station, Unit 1; 
    Issuance of Director's Decision Under 10 CFR 2.206
    
        Notice is hereby given that the Acting Director, Office of Nuclear 
    Reactor Regulation, has taken action with regard to a Petition dated 
    January 2, 1995, by Mr. Anthony J. Ross (Petition for action under 10 
    CFR 2.206). The Petition pertains to Millstone Nuclear Power Station, 
    Unit 1.
        In the Petition, the Petitioner asserted that (1) the Petitioner 
    was ``unjustly chastised'' by his first-line supervisor and department 
    manager about absenteeism, and his department manager threatened him in 
    a memorandum; (2) his first-line supervisor willfully falsified nuclear 
    documents in that he signed off on a surveillance of the gas turbine 
    battery as having met acceptance criteria when the requirements had not 
    been met; and (3) the Millstone Unit 1 organization failed to enter 
    into a 4-day Limiting Condition for Operation as required by the 
    Technical Specifications when the Operations Department was notified of 
    the failed surveillance, in violation of 10 CFR 50.5. In addition, the 
    Petitioner asserted that a number of violations have occurred in 1992 
    and 1993 related to the gas turbine battery, which have not been 
    handled appropriately by the NRC and Northeast Utilities, and that the 
    utility and NRC are engaged in an apparent ``cover-up'' of the 
    problems.
        The Petitioner requested that the Nuclear Regulatory Commission (1) 
    assess a Severity Level II violation and a Severity Level III violation 
    against his department manager and his first-line supervisor for their 
    apparent violations of 10 CFR 50.7; (2) institute sanctions against his 
    first-line supervisor, Northeast Utilities, and the Millstone Unit 1 
    organization for engaging in deliberate misconduct in violation of 10 
    CFR 50.5; and (3) remove his first-line supervisor from his position 
    until a ``satisfactory solution to the falsifying of nuclear 
    documents'' by this individual can be achieved.
        The Acting Director of the Office of Nuclear Reactor Regulation has 
    determined to deny the Petition. The reasons for this denial are 
    explained in the ``Director's Decision Under 10 CFR 2.206'' (DD-96-16), 
    the complete text of which follows this notice and is available for 
    public inspection at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the Learning Resources Center, Three Rivers 
    Community-Technical College, 574 New London Turnpike, Norwich, 
    Connecticut, and at the temporary local public document room located at 
    the Waterford Library, ATTN: Vince Juliano, 49 Rope Ferry Road, 
    Waterford, Connecticut.
        A copy of the Decision will be filed with the Secretary of the 
    Commission for the Commission's review in accordance with 10 CFR 
    2.206(c) of the Commission's regulations. As provided by this 
    regulation, the Decision will constitute the final action of the 
    Commission 25 days after the date of issuance unless the Commission, on 
    its own motion, institutes a review of the Decision in that time.
    
        Dated at Rockville, Maryland, this 31st day of October 1996.
    
        For the Nuclear Regulatory Commission.
    Ashok C. Thadani,
    Acting Director. Office of Nuclear Reactor Regulation.
    
    [DD-96-16]
    
    I. Introduction
    
        On January 2, 1995, Mr. Anthony J. Ross (Petitioner) filed a 
    Petition with the Executive Director for Operations of the Nuclear 
    Regulatory Commission (NRC) pursuant to Section 2.206 of Title 10 of 
    the Code of Federal Regulations (10 CFR 2.206). In the Petition, the 
    Petitioner raised concerns regarding (1) employee harassment and 
    intimidation by Northeast Utilities (NU); (2) the falsification of 
    nuclear documents concerning the gas turbine battery; (3) failure to 
    enter a Technical Specification Limiting Condition for Operation (LCO) 
    after a failed surveillance; and (4) his belief that numerous 
    violations have occurred in 1992 and 1993 regarding the gas turbine 
    battery. Because of these problems, the Petitioner alleges that the gas 
    turbine is still inoperable. In addition, the Petitioner asserts that 
    these problems have not been handled appropriately by the NRC and NU, 
    and that NU and the
    
    [[Page 57915]]
    
    NRC are engaged in an apparent ``cover-up'' of problems with 
    surveillances of the gas turbine battery.
        The Petitioner requested that the NRC (1) assess a Severity Level 
    II violation and a Severity Level III violation against his department 
    manager and his first-line supervisor for their apparent violations of 
    10 CFR 50.7; (2) institute sanctions against the Petitioner's first-
    line supervisor, NU, and the Millstone Unit 1 organization for engaging 
    in deliberate misconduct in violation of 10 CFR 50.5; and (3) remove 
    the Petitioner's first-line supervisor from his position until a 
    ``satisfactory solution to the falsifying of nuclear documents'' by 
    this individual can be achieved.
        On February 23, 1995, I informed the Petitioner that the Petition 
    had been referred to me pursuant to 10 CFR 2.206 of the Commission's 
    regulations. I also informed the Petitioner that the NRC would take 
    appropriate action within a reasonable time regarding the specific 
    concerns raised in the Petition. I also stated that the Petitioner's 
    allegations that the NRC has not been appropriately handling certain 
    violations and is engaged in a ``cover up'' of the problems related to 
    the gas turbine battery had been referred to the Office of the 
    Inspector General (OIG). Therefore, this Director's Decision does not 
    address that issue. On the basis of a review of the remaining issues 
    raised by the Petitioner, as discussed below, I have concluded that no 
    substantial health and safety issues have been raised that would 
    require the initiation of additional formal enforcement action.
    
    II. Discussion
    
    A. Background
    
        The Petitioner alleges that during an annual surveillance of the 
    gas turbine battery on September 20, 1994, he identified that some of 
    the intercell bolted connections of the gas turbine battery were 
    greater than 65 micro-ohms, which was greater than the acceptance 
    criteria specified in Procedure SP 779.5, ``Gas Turbine Battery Annual 
    Inspection.'' The Petitioner alleges that although he notified the 
    Operations Department shift supervisor and his first-line supervisor, 
    his first-line supervisor signed the surveillance as ``yes,'' referring 
    to the ``acceptance criteria met,'' when clearly the requirements were 
    not met as specified by Procedure SP 779.5. The Petitioner alleges 
    further that, when the Operations Department was notified by him of the 
    failed surveillance, the Millstone Unit 1 organization willfully failed 
    to enter a four-day LCO as required by the Technical Specifications, in 
    order to keep the unit on-line to produce revenues. In addition, the 
    Petitioner asserts that about a week after this incident, he received 
    copies of the 1992 and 1993 annual gas turbine battery surveillances 
    that indicated a number of problems and violations which have not been 
    handled appropriately by NU and the NRC, and that the gas turbine is 
    still inoperable due to these problems. Finally, the Petitioner alleges 
    that he has been subjected to harassment and intimidation by his first-
    line supervisor and department manager for raising these concerns.
    
    B. Petitioner's Concern Regarding Falsification of Nuclear Documents
    
        During an inspection held September 27 through November 15, 1994, 
    as documented in Inspection Report (IR) 50-245/94-31; 50-336/94-30; 50-
    423/94-28 (IR 94-31), dated December 16, 1994, and an inspection held 
    May 15 through June 23, 1995, as documented in IR 50-245/95-22; 50-336/
    95-22; 50-423/95-22 (IR 95-22), dated July 21, 1995, the NRC reviewed 
    gas turbine battery maintenance and surveillance activities at 
    Millstone Unit 1. The inspection determined that on September 20, 1994, 
    the date the Petitioner alleges the gas turbine battery failed the 
    surveillance, the licensee for Millstone Unit 1 (Northeast Nuclear 
    Energy Company--NNECO) performed the annual surveillance of the gas 
    turbine battery as specified by Procedure SP 779.5. This annual 
    preventive maintenance identified three intercell connection resistance 
    readings that did not meet the surveillance acceptance criterion in 
    that the resistance readings were greater than the accepted values. The 
    electricians notified the shift supervisor and the maintenance foreman 
    of the unsatisfactory readings and documented the results in the 
    surveillance procedure.
        The NRC reviewed the completed surveillance and noted that the 
    ``acceptance criteria met'' block was checked ``yes,'' indicating 
    satisfactory surveillance results; however, the resistance readings for 
    the three intercell connections were documented as unsatisfactory. The 
    inspection therefore confirmed that the classification of this 
    surveillance as acceptable was incorrect and, as a result, it bypassed 
    NNECO's administrative control procedures for system operability 
    1, and procedural review and approval. However, on the basis of 
    interviews and a review of the completed surveillance procedure, the 
    NRC determined that the first-line supervisor documented the high 
    resistance readings on the cover page of the surveillance, discussed 
    the issue with the Electrical Engineering Department to determine if 
    the high resistance readings affected operability of the battery and, 
    on the basis of the discussion with Engineering, determined that 
    Engineering had previously reviewed the effect of the high resistance 
    readings and had found the battery operable. Therefore, the first-line 
    supervisor concluded that the battery was acceptable as is 2. 
    Further, the inspection confirmed that the licensee's previous 
    operability evaluation was acceptable and that the gas turbine battery 
    was operable. As discussed below, the NRC took enforcement action 
    regarding a number of procedural violations associated with the gas 
    turbine battery surveillance. Therefore, based on the above, the NRC 
    has concluded that the first-line supervisor did not willfully falsify 
    documents.
    ---------------------------------------------------------------------------
    
        \1\ If the classification of the surveillance had been 
    determined to be ``unsatisfactory'' (``acceptance criteria block'' 
    checked ``no''), a determination of operability would be performed 
    and the related Technical Specification LCO would be entered, if the 
    gas turbine battery was inoperable.
        \2\ Although the first-line supervisor was technically correct 
    that the gas turbine battery was operable, the determination of 
    battery operability did not follow the licensee's administrative 
    controls as discussed above.
    ---------------------------------------------------------------------------
    
    C. Petitioner's Concern Regarding Failure To Enter Technical 
    Specification LCO
    
        The inspection determined that the classification of the resistance 
    readings as ``unsatisfactory'' (``acceptance criteria block'' checked 
    ``no'') would have ensured that a determination of operability would 
    have been performed by the licensee and the related Technical 
    Specification LCO would have been entered if appropriate. However, 
    since the first-line supervisor documented the high resistance 
    readings, discussed the readings with Engineering, and on the basis of 
    the discussion, determined that the battery was acceptable, the 
    licensee did not willfully fail to enter the LCO in that the licensee 
    determined that the previous operability determination was valid and, 
    therefore, that the surveillance procedure criteria had been met.
        In response to the NRC IR results, the Millstone Unit 1 Director 
    issued a memorandum to Millstone Unit 1 personnel to reinforce the 
    expectation that if an acceptance criterion is not met, the ``no'' 
    block must be checked. The Unit Director stated that he held
    
    [[Page 57916]]
    
    managers and supervisors personally accountable for ensuring that their 
    personnel understood the message in the memorandum. In addition, NNECO 
    held several management team meetings to ensure a full appreciation of 
    the type of performance characteristics that can lead to procedural 
    violations and to reinforce the licensee's expectation concerning the 
    ``acceptance criterion met'' block. NNECO also revised the acceptance 
    criterion within Procedure SP 779.5 for the three connections that have 
    the intercell connection cables with higher resistance because of the 
    cable length. In addition, the official plant record was corrected for 
    the annual battery surveillance that was incorrectly marked as meeting 
    its acceptance criterion. In a subsequent inspection report, IR 50-245/
    95-31, 50-336/95-31, 50-423/95-31 (IR 95-31), dated September 19, 1995, 
    the NRC reviewed the licensee's corrective actions in the above areas. 
    The NRC staff found the licensee's corrective actions to be timely and 
    thorough.
        In summary, on the basis of the above information, the staff found 
    that the Petitioner's first-line supervisor did incorrectly mark the 
    acceptance criterion met block ``yes;'' however, he annotated the high 
    resistance readings on the cover page of the surveillance and marked 
    the block ``yes'' based on his determination that Engineering had 
    previously reviewed the issue and determined the battery to be 
    operable. Further, the staff found that since the licensee determined 
    that this was previously reviewed by Engineering and found acceptable, 
    the licensee erroneously did not follow its administrative control 
    procedures for determining operability and entering of appropriate 
    LCOs. Therefore, the NRC determined that (1) the Petitioner's first-
    line supervisor did not willfully falsify nuclear documents or 
    deliberately violate NRC regulations or the Millstone Unit 1 operating 
    license; (2) neither he, Northeast Utilities, nor the Millstone Unit 1 
    organization violated the provisions of 10 CFR 50.5; (3) the requested 
    removal of the first-line supervisor is not warranted based on these 
    concerns; and (4) the licensee's corrective actions were acceptable. As 
    discussed below, the NRC took enforcement action regarding a number of 
    procedural violations associated with the gas turbine battery 
    surveillance.
    
    D. Additional Concerns Regarding Inoperability of the Emergency Gas 
    Turbine
    
        The Petitioner provides a number of examples of what he alleges 
    demonstrate inadequate procedural compliance by the licensee regarding 
    gas turbine battery surveillances which indicate that the gas turbine 
    is inoperable due to battery problems.3 In IR 94-31, the NRC 
    determined that during implementation of Procedure SP 779.5, there were 
    a number of examples (including the examples the Petitioner provided) 
    in which the Procedure SP 779.5 was not followed, nor was the job 
    stopped and the procedure revised to correct the identified errors. For 
    example, the procedure included a caution statement following step 6.19 
    that required the generation of a plant information report (PIR) and 
    subsequent determination of operability if the battery acceptance 
    criteria are not met. The PIR was not generated until this issue was 
    questioned by the NRC. Step 6.17 of the procedure requires that if any 
    resistance reading was greater than 65 micro-ohms, then the terminals 
    and straps must be cleaned. The licensee did not clean the terminal and 
    strap connections. Step 6.22 requires that the readings taken during 
    the surveillance be compared with previous battery surveillance 
    readings to determine if there is any deterioration of the battery 
    system. The licensee did not perform this review and evaluate the 
    battery for deterioration until the NRC raised the issue. The NRC 
    determined that these examples in which the procedure steps were not 
    implemented constituted a violation of Technical Specification 6.8.1 
    and Procedure SP 779.5 and issued a Notice of Violation to the licensee 
    (categorizing this as a Severity Level IV Violation, Violation 50-245/
    94-31-02). Further, the NRC noted in IR 94-31 that neither the 
    recognition of the procedure errors during two prior implementations of 
    this annual surveillance procedure (1992 and 1993) 4, nor the 
    biennial procedure review completed on December 8, 1993, resulted in 
    revisions to preclude the problems encountered during the 1994 
    surveillance. As discussed above, in IR 95-31, the NRC reviewed the 
    licensee's corrective actions for this violation and found them 
    acceptable.
    ---------------------------------------------------------------------------
    
        \3\ The Petitioner asserted that these problems have not been 
    handled by the NRC and NU, and that NU and the NRC are engaged in an 
    apparent ``cover-up'' of problems. As explained above, the ``cover-
    up'' issue has been referred to the OIG.
        \4\ The NRC noted similar examples in which the procedure was 
    not followed or corrected during the annual surveillance in 1992 and 
    1993.
    ---------------------------------------------------------------------------
    
        In IR 94-31, the NRC concluded that the previous operability 
    evaluation of the gas turbine battery was acceptable and, therefore, 
    that the gas turbine battery was operable at that time due to the 
    previous evaluation. The violation cited in the Notice of Violation 
    included the issues the Petitioner raised, specifically that NNECO 
    failed to perform an operability determination and subsequently did not 
    enter the Technical Specification LCO for the gas turbine. While the 
    NRC staff did not take the actions the Petitioner requested, the staff 
    did take enforcement action based on its findings. Therefore, since the 
    NRC found the licensee's determination of operability acceptable and 
    the NRC took enforcement action for the related violation described 
    above, the NRC has concluded that additional enforcement action is not 
    warranted.
    
    E. Petitioner's Allegations Regarding Harassment and Intimidation
    
        With regard to the Petitioner's assertion of harassment and 
    intimidation, the Petitioner alleges that (1) on October 7, 1994, he 
    was given a memorandum concerning absenteeism; (2) on October 27, 1994, 
    he was unjustly chastised by his first line supervisor and department 
    manager about absenteeism; and (3) on December 14, 1994, he was given a 
    memorandum that threatened him. The Petitioner further alleges that he 
    believes these actions by his supervision illustrate that NU management 
    harasses, intimidates, and retaliates against individuals who raise 
    safety concerns with outside agencies.
        As indicated in a letter to the Petitioner dated November 28, 1995, 
    from the NRC Deputy Executive Director for Nuclear Reactor Regulation, 
    Regional Operations and Research, the Petitioner has raised several 
    complaints since 1993 with the NRC or the Department of Labor (DOL) 
    concerning harassment, intimidation, or discrimination by individuals 
    at NU because the Petitioner raised safety concerns to NU or the NRC. 
    As explained in the letter, the NRC conducted investigations into some 
    of the harassment and intimidation allegations that the Petitioner had 
    raised. The NRC did not substantiate that the Petitioner suffered 
    discrimination for raising safety concerns. Further, of the complaints 
    of harassment and intimidation that the Petitioner raised that were 
    investigated by the DOL, none have been substantiated.
        The staff has, in addition, reviewed the Petitioner's remaining 
    allegations of harassment and intimidation, including those in the 
    Petition, and has concluded that they do not present sufficient 
    information warranting further investigatory effort. Accordingly, 
    absent a finding of discrimination by the Secretary of Labor or an 
    Administrative Law Judge on any pending complaints, or significant new 
    evidence from the
    
    [[Page 57917]]
    
    Petitioner that would support the allegations that NU has harassed, 
    intimidated, or discriminated against him, the NRC staff plans no 
    further followup of the harassment and intimidation complaints. Based 
    on the above, no further action is warranted.
    
    III. Conclusion
    
        On the basis of the above assessment, I have concluded that some of 
    the Petitioner's concerns were substantiated and resulted in 
    appropriate enforcement action. Other concerns were not substantiated. 
    Therefore, no additional enforcement action is being taken in this 
    matter.
        The Petitioner's request for action pursuant to 10 CFR 2.206 is 
    denied. As provided in 10 CFR 2.206(c), a copy of this Decision will be 
    filed with the Secretary of the Commission for the Commission's review. 
    This Decision will constitute the final action of the Commission 25 
    days after issuance unless the Commission, on its own motion, 
    institutes review of the Decision in that time.
    
        Dated at Rockville, Maryland, this 31st day of October 1996.
    
        For the Nuclear Regulatory Commission.
    Ashok C. Thadani,
    Acting Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 96-28742 Filed 11-7-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
11/08/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
96-28742
Pages:
57914-57917 (4 pages)
Docket Numbers:
Docket No. 50-245, License No. DPR-21
PDF File:
96-28742.pdf