Start Preamble
AGENCY:
Environmental Protection Agency (EPA).
ACTION:
Final rule.
SUMMARY:
EPA is taking final action to approve the State Implementation Plan (SIP) submissions, submitted by the State of Florida, through the Florida Department of Environmental Protection (FDEP), as demonstrating that the State meets certain SIP requirements of sections 110(a)(1) and (2) of the Clean Air Act (CAA or the Act) for the 1997 annual and 2006 24-hour fine particulate matter (PM2.5) national ambient air quality standards (NAAQS). Section 110(a) of the CAA requires that each state adopt and submit a SIP for the implementation, maintenance, and enforcement of each NAAQS promulgated by EPA, which is commonly referred to as an “infrastructure” SIP. Florida certified that the Florida SIP contains provisions that ensure the 1997 annual and 2006 24-hour PM2 NAAQS are implemented, enforced, and maintained in Florida (hereafter referred to as “infrastructure submissions”). Florida's infrastructure submissions, provided to EPA on April 18, 2008, and September 23, 2009, with the exception of element 110(a)(2)(D)(i) which will be addressed in a separate rulemaking action.
DATES:
This rule is effective December 10, 2012.
ADDRESSES:
EPA has established a docket for this action under Docket Identification No. EPA-R04-OAR-2012-0382. All documents in the docket are listed on the www.regulations.gov web site. Although listed in the index, some information is not publicly available, i.e., Confidential Business Information or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, is not placed on the Internet and will be publicly available only in hard copy form. Publicly available docket materials are available either electronically through www.regulations.gov or in hard copy at the Regulatory Development Section, Air Planning Branch, Air, Pesticides and Toxics Management Division, U.S. Environmental Protection Agency, Region 4, 61 Forsyth Street SW., Atlanta, Georgia 30303-8960. EPA requests that if at all possible, you contact the person listed in the FOR FURTHER INFORMATION CONTACT section to schedule your inspection. The Regional Office's official hours of business are Monday through Friday, 8:30 to 4:30 excluding federal holidays.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Sean Lakeman, Regulatory Development Section, Air Planning Branch, Air, Pesticides and Toxics Management Division, U.S. Environmental Protection Agency, Region 4, 61 Forsyth Street SW., Atlanta, Georgia 30303-8960. The telephone number is (404) 562-9043. Mr. Lakeman can be reached via electronic mail at lakeman.sean@epa.gov.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
Table of Contents
I. Background
II. This Action
III. Final Action
IV. Statutory and Executive Order Reviews
I. Background
Upon promulgation of a new or revised NAAQS, sections 110(a)(1) and (2) of the CAA require states to address basic SIP requirements, including emissions inventories, monitoring, and modeling to assure attainment and maintenance for that new NAAQS. On July 18, 1997 (62 FR 38652), EPA promulgated a new annual PM2.5 NAAQS and on October 17, 2006 (71 FR 61144), EPA promulgated a new 24-hour NAAQS. On June 12, 2012, EPA proposed to approve Florida's April 18, 2008, and September 23, 2009, infrastructure submissions for the 1997 annual and 2006 24-hour PM2.5 NAAQS. See 77 FR 34906. A summary of the background for today's final action is provided below. See EPA's June 12, 2012, proposed rulemaking at 77 FR 34906 for more detail.
Section 110(a) of the CAA requires states to submit SIPs to provide for the implementation, maintenance, and enforcement of a new or revised NAAQS within three years following the promulgation of such NAAQS, or within such shorter period as EPA may prescribe. Section 110(a) imposes the obligation upon states to make a SIP submission to EPA for a new or revised NAAQS, but the contents of that submission may vary from depending upon the facts and circumstances. The data and analytical tools available at the time the state develops and submits the SIP for a new or revised NAAQS affects the content of the submission. The contents of such SIP submissions may also vary depending upon what provisions the state's existing SIP already contains. In the case of the 1997 Start Printed Page 66928annual and 2006 24-hour PM2.5 NAAQS, states typically have met the basic program elements required in section 110(a)(2) through earlier SIP submissions in connection with previous PM NAAQS.
More specifically, section 110(a)(1) provides the procedural and timing requirements for SIPs. Section 110(a)(2) lists specific elements that states must meet for “infrastructure” SIP requirements related to a newly established or revised NAAQS. As already mentioned, these requirements include SIP infrastructure elements such as modeling, monitoring, and emissions inventories that are designed to assure attainment and maintenance of the NAAQS. The requirements that are the subject of this final rulemaking are listed below [1] and in EPA's October 2, 2007, memorandum entitled “Guidance on SIP Elements Required Under Section 110(a)(1) and (2) for the 1997 8-Hour Ozone and PM2.5 National Ambient Air Quality Standards.” and September 25, 2009, memorandum entitled “Guidance on SIP Elements Required Under Section 110(a)(1) and (2) for the 2006 24-Hour Fine Particle (PM2.5) National Ambient Air Quality Standards.”
- 110(a)(2)(A): Emission limits and other control measures.
- 110(a)(2)(B): Ambient air quality monitoring/data system.
- 110(a)(2)(C): Program for enforcement of control measures.[2]
- 110(a)(2)(D): Interstate transport.[3]
- 110(a)(2)(E): Adequate resources.
- 110(a)(2)(F): Stationary source monitoring system.
- 110(a)(2)(G): Emergency power.
- 110(a)(2)(H): Future SIP revisions.
- 110(a)(2)(I): Areas designated nonattainment and meet the applicable requirements of part D.[4]
- 110(a)(2)(J): Consultation with government officials; public notification; and PSD and visibility protection.
- 110(a)(2)(K): Air quality modeling/data.
- 110(a)(2)(L): Permitting fees.
- 110(a)(2)(M): Consultation/participation by affected local entities.
II. This Action
EPA is taking final action to approve Florida's infrastructure submissions as demonstrating that the State meets certain applicable requirements of sections 110(a)(1) and (2) of the CAA for the 1997 annual and 2006 24-hour PM2.5 NAAQS. Section 110(a) of the CAA requires that each state adopt and submit a SIP for the implementation, maintenance, and enforcement of each NAAQS promulgated by EPA, which is commonly referred to as an “infrastructure” SIP. FDEP certified that the Florida SIP contains provisions that ensure the 1997 annual and 2006 24-hour PM2.5 NAAQS are implemented, enforced, and maintained in Florida.
EPA received no adverse comments on its June 12, 2012, proposed approval of Florida's April 18, 2008, and September 23, 2009, infrastructure submissions. Concerning elements 110(a)(2)(C) and (J), EPA signed a final rulemaking action on September 6, 2012, approving revisions to Florida's New Source Review (NSR) requirements addressing elements 110(a)(2)(C) and (J). EPA is not taking action today on Florida's NSR program, as these requirements are already approved in Florida's SIP. Additionally, on July 30, 2012, EPA published a final rulemaking action addressing the requirements of element 110(a)(2)(E)(ii). See 77 FR 44485.
EPA is today finalizing its determination that Florida's infrastructure submissions, provided to EPA on April 18, 2008, and September 23, 2009, satisfy the required infrastructure elements for the 1997 annual and 2006 24-hour PM2.5 NAAQS with the exception of 110(a)(2)(D)(i), which will be addressed in a separate rulemaking action.[5] EPA has determined that Florida's April 18, 2008, and September 23, 2009, submissions are consistent with section 110 of the CAA.
III. Final Action
As already described, EPA has determined that FDEP has addressed certain elements of the CAA 110(a)(1) and (2) SIP requirements pursuant to EPA's October 2, 2007, guidance to ensure that 1997 annual and 2006 24-hour PM2.5 NAAQS are implemented, enforced, and maintained in Florida, with the exception of section 110(a)(2)(D)(i) requirements. EPA is taking final action to approve Florida's April 18, 2008, and September 23, 2009, submissions for 1997 annual and 2006 24-hour PM2.5 NAAQS because these submissions are consistent with section 110 of the CAA. Today's action is not approving any specific rule, but rather making a determination that Florida's already approved SIP meets certain CAA requirements.
IV. Statutory and Executive Order Reviews
Under the CAA, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, EPA's role is to approve state choices, provided that they meet the criteria of the CAA. Accordingly, this action merely approves state law as meeting federal requirements and does not impose additional requirements beyond those imposed by State law. For that reason, this action:
- Is not a “significant regulatory action” subject to review by the Office of Management and Budget under Executive Order 12866 (58 FR 51735, October 4, 1993);
- Does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
- Is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.);
- Does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104-4);
- Does not have Federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999);
- Is not an economically significant regulatory action based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997);Start Printed Page 66929
- Is not a significant regulatory action subject to Executive Order 13211 (66 FR 28355, May 22, 2001);
- Is not subject to requirements of Section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA; and
- Does not provide EPA with the discretionary authority to address, as appropriate, disproportionate human health or environmental effects, using practicable and legally permissible methods, under Executive Order 12898 (59 FR 7629, February 16, 1994).
In addition, this rule does not have tribal implications as specified by Executive Order 13175 (65 FR 67249, November 9, 2000), because the SIP is not approved to apply in Indian country, and EPA notes that it will not impose substantial direct costs on tribal governments or preempt tribal law.
The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. EPA will submit a report containing this action and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rule in the Federal Register. A major rule cannot take effect until 60 days after it is published in the Federal Register. This action is not a “major rule” as defined by 5 U.S.C. 804(2).
Under section 307(b)(1) of the CAA, petitions for judicial review of this action must be filed in the United States Court of Appeals for the appropriate circuit by January 7, 2013. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this action for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements. See section 307(b)(2).
Start List of SubjectsList of Subjects in 40 CFR Part 52
- Environmental protection
- Air pollution control
- Incorporation by reference
- Intergovernmental relations
- Nitrogen dioxide
- Particulate matter
- Reporting and recordkeeping requirements
- Volatile organic compounds
Dated: September 13, 2012.
A. Stanley Meiburg,
Acting Regional Administrator, Region 4.
40 CFR part 52 is amended as follows:
Start PartPART 52—[AMENDED]
End Part Start Amendment Part1. The authority citation for part 52 continues to read as follows:
End Amendment PartSubpart K—Florida
Start Amendment Part2. Section 52.520(e), is amended by adding two new entries for “110(a)(1) and (2) Infrastructure Requirements for the 1997 Fine Particulate Matter National Ambient Air Quality Standards” and “110(a)(1) and (2) Infrastructure Requirements for the 2006 Fine Particulate Matter National Ambient Air Quality Standards” at the end of the table to read as follows:
End Amendment PartIdentification of plan.* * * * *(e) * * *
EPA-Approved Florida Non-Regulatory Provisions
Provision State effective date EPA approval date Federal Register notice Explanation * * * * * * * 110(a)(1) and (2) Infrastructure Requirements for 1997 Fine Particulate Matter National Ambient Air Quality Standards 4/18/2008 11/8/2012 [Insert citation of publication] With the exception of section 110(a)(2)(D)(i). 110(a)(1) and (2) Infrastructure Requirements for 2006 Fine Particulate Matter National Ambient Air Quality Standards 9/23/2009 11/8/2012 [Insert citation of publication] With the exception of section 110(a)(2)(D)(i). Footnotes
1. Two elements identified in section 110(a)(2) are not governed by the three year submission deadline of section 110(a)(1) because SIPs incorporating necessary local nonattainment area controls are not due within three years after promulgation of a new or revised NAAQS, but rather are due at the time the nonattainment area plan requirements are due pursuant to section 172. These requirements are: (1) Submissions required by section 110(a)(2)(C) to the extent that subsection refers to a permit program as required in part D Title I of the CAA, and (2) submissions required by section 110(a)(2)(I) which pertain to the nonattainment planning requirements of part D, Title I of the CAA. Today's final rulemaking does not address infrastructure elements related to section 110(a)(2)(I) or the nonattainment plan requirements of section 110(a)(2)(C).
Back to Citation2. This rulemaking only addresses requirements for this element as they relate to attainment areas.
Back to Citation3. Today's final rule does not address element 110(a)(2)(D)(i) (Interstate Transport) for the 1997 and 2006 PM2.5 NAAQS.
Back to Citation4. This requirement was inadvertently omitted from EPA's October 2, 2007, memorandum entitled “Guidance on SIP Elements Required Under Section 110(a)(1) and (2) for the 1997 8-Hour Ozone and PM2.5 National Ambient Air Quality Standards,” but as mentioned above is not relevant to today's final rulemaking.
Back to Citation5. As noted above, today's final rulemaking also does not address section 110(a)(2)(C) requirements related nonattainment area plan requirements and section 110(a)(2)(I) requirements.
Back to Citation[FR Doc. 2012-27223 Filed 11-7-12; 8:45 am]
BILLING CODE 6560-50-P
Document Information
- Comments Received:
- 0 Comments
- Effective Date:
- 12/10/2012
- Published:
- 11/08/2012
- Department:
- Environmental Protection Agency
- Entry Type:
- Rule
- Action:
- Final rule.
- Document Number:
- 2012-27223
- Dates:
- This rule is effective December 10, 2012.
- Pages:
- 66927-66929 (3 pages)
- Docket Numbers:
- EPA-R04-OAR-2012-0382, FRL-9734-6
- Topics:
- Air pollution control, Environmental protection, Incorporation by reference, Intergovernmental relations, Nitrogen dioxide, Particulate matter, Reporting and recordkeeping requirements, Volatile organic compounds
- PDF File:
- 2012-27223.pdf
- Supporting Documents:
- » Florida 2011 105 Grant Status
- » Florida PM2.5 Monitoring Plan
- » Florida PM2.5 110(a)(1)-(2) Submission
- CFR: (1)
- 40 CFR 52.520