98-31873. NorAm Gas Transmission Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 63, Number 230 (Tuesday, December 1, 1998)]
[Notices]
[Pages 66151-66152]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-31873]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP99-60-000]
NorAm Gas Transmission Company; Notice of Request Under Blanket
Authorization
November 24, 1998.
Take notice that on November 6, 1998, NorAm Gas Transmission
Company (NGT), 1111 Louisiana, Houston, Texas 77002-5231, filed in
Docket No. CP99-60-000 a request pursuant to Sections 157.205 and
157.211 of the Commission's Regulations under the Natural Gas Act (18
CFR 157.205 and 157.211) for authorization to operate certain
facilities in Arkansas under NGT's blanket certificate issued in Docket
No. CP82-384-000 and CP82-384-001 pursuant to
[[Page 66152]]
Section 7 of the Natural Gas Act, all as more fully set forth in the
request that is on file with the Commission and open to public
inspection.
NGT specifically requests authority to continue operating three
delivery taps installed and one that is in the process of being
constructed solely to provide service authorized under Section 311 of
the Natural Gas Policy Act and Subpart B, of the Commission's
Regulations under Subpart G of Part 284 of the Commission's Regulations
to ARKLA, a distribution division of NorAm Energy Corp. (ARKLA). The
estimated volumes to be delivered through these facilities are
approximately 10,200 MMBtu annually and 91 MMBtu on a peak day. The
facility upgrades have an estimated cost of $6,975, and $5,985 will be
reimbursed by ARKLA.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under Natural Gas Act (18 CFR 157.205) a protest to the
request. If no protest is filed within the time allowed therefore, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 98-31873 Filed 11-30-98; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 12/01/1998
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 98-31873
- Pages:
- 66151-66152 (2 pages)
- Docket Numbers:
- Docket No. CP99-60-000
- PDF File:
-
98-31873.pdf