96-31323. Niagara Mohawk Power Corporation Nine Mile Point, Unit 1; Order Imposing a Civil Monetary Penalty  

  • [Federal Register Volume 61, Number 238 (Tuesday, December 10, 1996)]
    [Notices]
    [Pages 65085-65088]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-31323]
    
    
    -----------------------------------------------------------------------
    
    
    NUCLEAR REGULATORY COMMISSION
    
    Niagara Mohawk Power Corporation Nine Mile Point, Unit 1; Order 
    Imposing a Civil Monetary Penalty
    
    [Docket No. 50-220, License No. DPR-63, EA 96-079]
    
    I.
    
        Niagara Mohawk Power Corporation (Licensee) is the holder of 
    Operating License No. DPR-63 (License), issued by the Nuclear 
    Regulatory Commission (NRC or Commission). The License authorizes the 
    Licensee to operate the Nine Mile Point Unit 1 nuclear facility in 
    accordance with the conditions specified therein.
    
    II.
    
        An inspection of the Licensee's activities was conducted between 
    February 17 and March 11, 1996. The results of this inspection 
    indicated that the Licensee had not conducted its activities in full 
    compliance with NRC requirements. A written Notice of Violation and 
    Proposed Imposition of Civil Penalty (Notice) was served upon the 
    Licensee by letter dated June 18, 1996. The Notice states the nature of 
    the violations, the provisions of the NRC's requirements that the 
    Licensee had violated, and the amount of the civil penalty proposed for 
    the violations.
        The Licensee responded to the Notice in a letter dated July 16, 
    1996. In its response, the Licensee admitted the two violations 
    assessed a civil penalty in Section I of the Notice, but requested that 
    the penalty be mitigated. In addition, the Licensee denied the two 
    violations in Section II of the Notice that were classified 
    individually at Severity Level IV and not assessed a civil penalty. The 
    Licensee provided a supplemental response, dated August 15, 1996, in 
    which the Licensee subsequently admitted one of the Severity Level IV 
    violations that it had denied in the July 16, 1996 response.
    
    III.
    
        After consideration of the Licensee's response and the statements 
    of fact, explanation, and argument for mitigation contained therein, 
    the NRC staff has determined, as set forth in the Appendix to this 
    Order, that the violations for which the civil penalty was proposed 
    occurred as stated in the Notice, and that an adequate basis was not 
    provided for mitigation of the civil penalty. Therefore, the penalty 
    proposed for the violations designated in Section I of the Notice 
    should be imposed.
    
    IV.
    
        In view of the foregoing and pursuant to Section 234 of the Atomic 
    Energy Act of 1954, as amended (Act), 42 U.S.C. 2282, and 10 CFR 2.205, 
    It Is Hereby Ordered That:
        The Licensee pay a civil penalty in the amount of $50,000 within 30 
    days of the date of this Order, by check, draft, money order, or 
    electronic transfer, payable to the Treasurer of the United States and 
    mailed to the Director, Office of Enforcement, U.S. Nuclear Regulatory 
    Commission, One White Plant North, 11555 Rockville Pike, Rockville, MD 
    20852-2738.
    
    V.
    
        The Licensee may request a hearing within 30 days of the date of 
    this Order. Where good cause is shown, consideration will be given to 
    extending the time to request a hearing. A request for extension of 
    time must be made in writing to the Director, Office of Enforcement, 
    U.S. Nuclear Regulatory Commission, Washington, D.C. 20555, and include 
    a statement of good cause for the extension. A request for a hearing 
    should be clearly marked as a ``Request for an Enforcement Hearing'' 
    and shall be addressed to the Director, Office of Enforcement, U.S. 
    Nuclear Regulatory Commission Washington, D.C. 20555, with a copy to 
    the Commission's Document Control Desk, Washington, D.C. 20555. Copies 
    also shall be sent to the Assistant General Counsel for Hearings and 
    Enforcement at the same address and to the Regional Administrator, NRC 
    Region I, 475 Allendale Road, King of Prussia, Pennsylvania 19406.
        If a hearing is requested, the Commission will issue an Order 
    designating the time and place of the hearing. If the Licensee fails to 
    request a hearing within 30 days of the date of this Order, or if 
    written approval of an extension of time in which to request a hearing 
    has not been granted, the provisions of this Order shall be effective 
    without further proceedings. If payment has not been made by that time, 
    the matter may be referred to the Attorney General for collection.
        In the event the Licensee requests a hearing as provided above, the 
    issues to be considered at such hearing shall be:
    
    whether, on the basis of the violations set forth in Section I of the 
    Notice that the Licensee admitted, this Order should be sustained.
    
        Dated at Rockville, Maryland this 3rd day of December 1996.
    
    For the Nuclear Regulatory Commission.
    James L. Milhoan,
    Deputy Executive Director for Nuclear Reactor Regulation, Regional 
    Operations and Research.
    
    Appendix
    
    Evaluation and Conclusion
    
        On June 18, 1996, a Notice of Violation and Proposed Imposition of 
    Civil Penalty (Notice) in the amount of $50,000 was issued to the 
    Niagara Mohawk Power Corporation (licensee) for violations of NRC 
    requirements. Two of the violations were classified in the aggregate at 
    Severity Level III, and a $50,000 civil penalty was proposed. Two other 
    violations were classified individually at Severity Level IV. The 
    licensee responded to the Notice on July 16, 1996, and admitted the two 
    violations for which a penalty was proposed, but requested that the 
    penalty
    
    [[Page 65086]]
    
    be mitigated. The licensee also denied the two violations that were not 
    assessed a penalty. In a supplemental response, dated August 15, 1996, 
    the licensee admitted one of the Severity Level IV violations that it 
    had denied in the July 16, 1996 response. The NRC's evaluation and 
    conclusion regarding the licensee's requests are as follows:
    
    1. Restatement of Violations
    
        A. Title 10 of the Code of Federal Regulations, Part 50, (10 CFR 
    50), Appendix B, Criterion III, ``Design Control,'' requires that 
    measures be established to verify the adequacy of design, such as by 
    design reviews, alternate or simplified calculational methods, or 
    suitable testing.
        Nine Mile Point Unit 1 Updated Final Safety Analysis Report 
    (UFSAR), Sections VI.C.1.2 and III.A.1.2, state that the reactor and 
    turbine building pressure relief panels will blow out at 45 pounds per 
    square foot (psf) to prevent failure of the building superstructures at 
    an internal pressure in excess of 80 psf.
        Contrary to the above, between October 1993 and March 1995, 
    measures established failed to verify the adequacy of design for Unit 1 
    reactor and turbine building pressure relief panels to blow out at the 
    specified pressures. Specifically, in October 1993, NMPC made an error 
    in the assumptions for calculations regarding the installed, oversized 
    bolts in the reactor and turbine building pressure relief panels. The 
    error was not identified, during the review process, by either the 
    independent engineering reviewer or approver. It was not recognized 
    until March 1995 that the relief pressures were in excess of the 
    designed blowout pressure of the superstructures. (01013)
        B. 10 CFR 50.59(a)(1), allows, in part, the holder of a license to 
    make changes to the facility as described in the safety analysis report 
    unless the proposed change involves an unreviewed safety question.
        10 CFR 50.59(b)(1) requires, in part, the licensee to maintain 
    records of changes in the facility, to the extent that these changes 
    constitute changes in the facility as described in the safety analysis 
    report. The records must include a written safety evaluation which 
    provides the bases for the determination that the change does not 
    involve an unreviewed safety question.
        Nine Mile Point Unit 1 UFSAR Sections VI.C.1.2 and III.A.1.2 state 
    that the reactor and turbine building pressure relief panels will blow 
    out at 45 psf to prevent failure of the building superstructure at an 
    internal pressure in excess of 80 psf.
        Contrary to the above, from December 1969 to March 1995, the actual 
    design configuration of the reactor and turbine building pressure 
    relief panels was different from that described in the UFSAR, and 
    Niagara Mohawk Power Corporation (NMPC) did not perform the required 
    written safety evaluation to provide the bases for a determination that 
    the deviation from the UFSAR description did not involve an unreviewed 
    safety question. Specifically, in October 1993, NMPC identified that 
    the wrong size bolts had been installed in the relief panels during 
    initial construction. Calculations revealed that the reactor and 
    turbine building pressure relief panels would not relieve until 53 and 
    60 psf, respectively. Subsequent calculations revealed that the panels 
    would not relieve until the pressure was in excess of the 
    superstructure design blowout pressure of 80 psf stated in the UFSAR, 
    and the licensee neither performed the evaluation required by 10 CFR 
    50.59, nor did it undertake adequate corrective action to restore the 
    facility to the licensing basis configuration as specified in the 
    UFSAR. (01023)
        This is a Severity Level III problem (Supplement I). Civil 
    Penalty--$50,000
    
    2. Summary of Licensee Response Requesting Mitigation of the Penalty
    
        In its July 16, 1996 response, the licensee admitted the two 
    violations for which the civil penalty was proposed and stated its 
    belief that a civil penalty is not warranted. In support of this 
    belief, the licensee noted that the deficiencies in the blowout panel 
    construction do not represent a significant safety issue; the blowout 
    panels would have functioned as designed to prevent failure of the 
    building superstructures; and the panels would only function in the 
    event of a high energy line break outside containment, a scenario that 
    the licensee indicated is not considered a design basis event for NMP-
    1.
        The licensee also expressed concern that the violations and civil 
    penalty may be the result of applying a relatively recent regulatory 
    position and philosophy to actions that occurred over three years ago. 
    The licensee noted that it appears that the NRC is considering all 
    statements and commitments in the UFSAR as ``stand-alone'' regulatory 
    requirements, and has applied a new and restrictive interpretation to 
    the definition of ``margin of safety'' terminology in 10 CFR 50.59. The 
    licensee further notes that the plant condition was identified by its 
    staff as a result of a proactive evaluation to resolve a minor 
    discrepancy in the UFSAR.
        The licensee further noted in support of its mitigation request 
    that it had not been assessed a penalty since 1992; that it has 
    demonstrated a proactive approach to safety; and, contrary to a 
    statement in the NOV transmittal letter, that it took immediate actions 
    to restore the pressure relief panels to a condition consistent with 
    the UFSAR once the calculational error was discovered, and the NRC did 
    not appear to give any credit for this.
    
    3. NRC Evaluation of Licensee Response
    
        The NRC has carefully considered the licensee's response and 
    concludes that the licensee has not provided an adequate basis for 
    mitigation of the civil penalty.
        Although the licensee did not specifically contest the Severity 
    Level classification of the two violations in Section I of the Notice, 
    the licensee appears to take issue with that classification by 
    indicating that the deficiencies in the pressure relief panel 
    construction do not represent a significant safety issue. The NRC 
    concedes that the pressure relief panels likely would have functioned 
    as designed to prevent failure of the building superstructures,\1\ and 
    the panels function only in the event of a high energy line break 
    outside containment, which is not considered a design basis event for 
    NMP-1. However, the NRC notes that the full resolution of this issue is 
    still under the licensee's evaluation. Notwithstanding the result of 
    that resolution, the NRC maintains that the two violations represent a 
    significant regulatory concern and, therefore, were classified 
    appropriately in the aggregate at Severity Level III.
    ---------------------------------------------------------------------------
    
        \1\ This NRC position is based on more recent licensee reviews 
    performed after the enforcement conference, which determined that 
    both the reactor and turbine buildings would be capable of 
    withstanding internal pressures in excess of 100 psf without 
    superstructure failure.
    ---------------------------------------------------------------------------
    
        In making this determination, the NRC considered the fact that this 
    condition (the actual design configuration of the pressure relief 
    panels was different from that described in the UFSAR) existed for 
    approximately 26 years, without any written safety evaluation to 
    provide the basis for a determination that the deviation from the UFSAR 
    description did not involve an unreviewed safety question. A number of 
    facts are most noteworthy: (1) the licensee identified, in October 
    1993, that the wrong size bolts (\1/4\-inch diameter, as opposed to the 
    correct sized \3/16\-inch diameter bolts) had been installed in the 
    relief
    
    [[Page 65087]]
    
    panels during initial construction, (2) the licensee's October 1993 
    evaluation of the wrong bolts utilized assumptions inconsistent with 
    the assumptions described in the UFSAR \2\ and (3) a subsequent review, 
    in March 1995, of the evaluation performed in October 1993, revealed 
    that the assumptions were incorrect and that the panels would not 
    relieve until the pressure was in excess of the superstructure design 
    blowout pressure stated in the UFSAR (80 psf). Nonetheless, the 
    licensee neither performed the required evaluation, nor undertook 
    adequate corrective action to restore the facility to the licensing 
    basis configuration as specified in the UFSAR. Given the length of time 
    this condition existed, the inappropriate and inconsistent use of 
    assumptions not described in the UFSAR, and the failure to promptly 
    resolve and take appropriate action to address the issue of building 
    overpressure when indications of a problem surfaced in 1993, the NRC 
    contends that the violations represent a significant regulatory concern 
    and were classified appropriately at Severity Level III.
    ---------------------------------------------------------------------------
    
        \2\ The UFSAR description of the failure mode was the panel 
    bolts shearing (one-way process analysis resulting in calculated 
    failures of 94 psf and 92 psf for the reactor and turbine building, 
    respectively). However, the licensee chose to analyze the panel 
    relieving process by using a metal tearing failure mode (two-way 
    process analysis resulting in calculated failures of 53 psf and 60 
    psf for the reactor and turbine building, respectively).
    ---------------------------------------------------------------------------
    
        With regard to the licensee's concern that the violations and 
    imposition of a civil penalty may be the result of applying a 
    relatively recent regulatory position and philosophy to actions that 
    occurred over three year ago, Violations I.A and B involve the 
    licensee's original construction installation of incorrect-sized bolts 
    on the pressure relief panels, resulting in a change to the facility 
    from that described in the plant's UFSAR, without preparing a written 
    safety evaluation as required by 10 CFR 50.59. The NRC has always 
    regarded such a change as requiring a written safety evaluation in 
    accordance with 10 CFR 50.59. Thus, there has been no change in the 
    NRC's interpretation of this requirement as it applies to the changes 
    addressed in Violations I.A and B.
        The NRC also acknowledges that this plant condition was identified 
    by the licensee staff as a result of a proactive evaluation to resolve 
    a discrepancy in the UFSAR, and the licensee has not been assessed a 
    penalty since 1992. These factors were considered by the NRC as part of 
    the civil penalty assessment process set forth in the NRC Enforcement 
    Policy (NUREG-1600), as were the licensee's corrective actions. In 
    addition, although the NRC acknowledges that the licensee took 
    immediate actions to restore the pressure relief panels to a condition 
    consistent with the UFSAR once the calculational error was discovered, 
    the NRC maintains that no credit was warranted for these corrective 
    actions. In October 1993, the licensee identified that the wrong bolts 
    had been installed in 1969, and calculated the relief pressures to be 
    53 psf for the reactor building and 60 psf for the turbine building. 
    This calculation was in error, and the relief pressures were actually 
    in excess of 80 psf as the licensee identified in March 1995, at which 
    time the licensee removed every other bolt to place themselves in a 
    condition that the licensee believed was in compliance with the UFSAR. 
    It was not until after being questioned by the NRC prior to the 
    conference, that the licensee identified that the March 1995 
    calculations were also wrong. In addition, the calculations used to 
    support the removal of every other bolt were flawed, yet the licensee, 
    at the time of the enforcement conference, had not completed the 
    evaluation required pursuant to 10 CFR 50.59 to change the UFSAR. 
    Therefore, the NRC maintains that credit is not warranted for the 
    licensee's corrective actions, which according to the Enforcement 
    Policy, results in a civil penalty of $50,000 being assessed. The NRC 
    concludes that the penalty for this Severity Level III problem should 
    not be mitigated.
    
    4. Restatement of Violation II.B
    
        10 CFR 50.72(b)(1)(ii)(B), requires, in part, that the licensee 
    shall notify the NRC as soon as practical and in all cases within one 
    hour of the occurrence of any event or condition, during operation, 
    that results in the nuclear power plant, including its principal safety 
    barriers, being seriously degraded or in a condition that is outside 
    the design basis of the plant.
        10 CFR 50.73(a)(2)(ii)(B) requires that the licensee shall submit a 
    Licensee Event Report (LER) within 30 days of the discovery of any 
    event or condition that results in the condition of the nuclear power 
    plant, including its principal safety barriers being seriously degraded 
    or in a condition that is outside the design basis of the plant.
        Contrary to the above, in October 1993, NMPC did not notify the NRC 
    within one hour of the discovery of a condition outside the design 
    basis of the plant, nor did NMPC submit a LER within 30 days of 
    discovery of a condition outside the design basis of the plant. 
    Specifically, with the plant operating, NMPC determined that the actual 
    blowout pressures of the reactor and turbine building pressure relief 
    panels were in excess of the buildings' design basis pressures 
    identified in the Unit 1 UFSAR, and NMPC failed to make and submit the 
    required reports in the required time periods. (02024)
        This is a Severity Level IV Violation (Supplement I).
    
    5. Licensee Response Denying Violation II.B
    
        The licensee, in disagreeing with this violation, noted that in 
    October of 1993, the calculations associated with the oversized bolts 
    in the blowout panels indicated that the reactor and turbine building 
    panels would relieve at internal pressures of 53 and 60 psf, 
    respectively, and the UFSAR indicated that the buildings' design basis 
    pressure was in excess of 80 psf. The licensee, therefore, concluded 
    that this situation was not reportable even though the calculated 
    blowout pressures did exceed the 45 psf nominal value for bolt failure 
    as indicated in the UFSAR.
        The licensee stated that in reaching this conclusion, it considered 
    the guidance in NUREG-1022, ``Event Reporting Guidelines 10 CFR 50.72 
    and 50.73,'' and various statements in the Federal Register (FR) 
    related to the reportability rule. The licensee notes that NUREG-1022 
    provides an example where high energy line break restraints are not 
    installed, but indicates that this would not be considered reportable 
    if analysis shows that the particular missing restraints are not needed 
    for compliance with the design basis. The licensee further indicates 
    that the preamble to the final rule in the August 29, 1983, FR notes, 
    in regard to this section of the rule, that ``[i]t is not intended that 
    this paragraph apply to minor variations in individual parameters or to 
    problems concerning single pieces of equipment.'' The licensee also 
    noted that an April 8, 1993 FR states: ``Furthermore, the wording of 
    the criteria and the guidance in the preamble to the final rule imply 
    that this impact on plant safety should be at a fairly high level,'' 
    and ``Therefore, failure, specification problems, and loss of safety 
    margins that apply to individual components are not reportable unless 
    they effect the ability to satisfy plant safety functions 3.''
    ---------------------------------------------------------------------------
    
        \3\ 58 FR 18167, 18174, April 8, 1993
    ---------------------------------------------------------------------------
    
        The licensee indicated that, based on the above guidance, it 
    concluded in October of 1993 that the calculated blowout pressures of 
    53 and 60 psf for the reactor and turbine buildings, respectively, 
    would still have the ability
    
    [[Page 65088]]
    
    to satisfy the plant design basis. Specifically, the blowout panels 
    would still protect the buildings' superstructure from failure, which 
    was considered the plant design basis. The licensee contended that the 
    45 psf value is not considered the plant design basis for reportability 
    considerations and none of the principle safety barriers was seriously 
    degraded. Therefore, the licensee does not consider that this condition 
    was reportable given the information available in October 1993, and 
    therefore disagrees with this violation.
        The licensee also notes that the description of the violation in 
    the Notice of Violation, and particularly, the discussion of the 
    violation in the transmittal letter, suggests that the NRC is applying 
    a relatively recent regulatory position regarding the status of 
    numerical values within the UFSAR. Specifically, the licensee states 
    that it appears that the NRC is considering all statements and 
    commitments in the UFSAR as ``stand-alone'' requirements. The licensee 
    further notes that while stated in the second paragraph on page two of 
    the NOV transmittal letter, but not cited as such in any of the 
    violations, it appears that the NRC considers that the failure of the 
    blowout panels to function at the UFSAR stated pressure of 45 psf is, 
    in itself, a violation of regulatory requirements and a reportable 
    situation. The licensee disagrees with this interpretation of the legal 
    significance of the UFSAR, and is participating with the Nuclear Energy 
    Institute (NEI) to initiate a dialogue with the NRC regarding the 
    resolution of this generic issue. The licensee further states that 
    notwithstanding its efforts to reach agreement on what the 
    interpretation of information in the UFSAR should be, the licensee 
    believes that it is clear that the NRC's regulatory interpretation is 
    inconsistent with the previously issued guidance on reportability as 
    referenced in the licensee's response.
    
    6. NRC Evaluation of Licensee Response
    
        The NRC agrees that the licensee, based on its erroneous 
    calculations in October 1993, concluded that the pressure relief panels 
    would provide relief at values below the reactor and turbine building 
    superstructure failure pressure of 80 psf. While the licensee clearly 
    should have been aware that the pressure relief panels would provide 
    relief at values above the 80 psf superstructure pressures if the 
    calculation had been adequately performed, it is also clear that the 
    licensee could not report a condition that it was not aware of, even 
    though it should have been aware of the condition. Nonetheless, the 
    licensee was aware that the panels' pressure relief values calculated 
    in 1993 were above the stated value of 45 psf stated in the UFSAR at 
    which the panels were supposed to provide relief. The NRC maintains 
    that the licensee was outside of its design basis and decreased the 
    margin to the pressure that would cause building failure and, 
    therefore, the deviation from the UFSAR should have been reported to 
    the NRC.
        The NRC maintains this position, notwithstanding the licensee's 
    contention that the guidance in NUREG-1022 would suggest that the 
    condition was not reportable. The NRC believes that the licensee 
    misinterpreted the NUREG-1022 guidance and in so doing, failed to 
    report the subject condition to the NRC. Simply stated, the licensee's 
    analogy of a missing high energy line break restraint, which 
    subsequently is analyzed as not being required for compliance with the 
    design basis, is not applicable to the pressure relief panels, a single 
    component which provides a significant function in protecting the 
    building superstructure in the event of an overpressure transient of 
    the reactor or turbine buildings.
    
    7. NRC Conclusion
    
        The NRC concludes that the licensee has not provided an adequate 
    basis for mitigating the civil penalty. Accordingly, the NRC has 
    determined that a monetary civil penalty in the amount of $50,000 
    should be imposed for the violations in Section I of the June 18, 1996 
    Notice. In addition, the licensee has not provided an adequate basis 
    for the withdrawal of Violation II.B in the Notice.
    
    [FR Doc. 96-31323 Filed 12-9-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
12/10/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
96-31323
Pages:
65085-65088 (4 pages)
PDF File:
96-31323.pdf