[Federal Register Volume 62, Number 237 (Wednesday, December 10, 1997)]
[Notices]
[Pages 65106-65107]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-32271]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Number 40-8452]
Bear Creek Uranium Company; Notice of Opportunity for Hearing
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of Receipt of Application from Bear Creek Uranium
Company to change two site-reclamation milestones in Condition 49 of
Source Material License No. SUA-1310 for the Bear Creek, Wyoming
Uranium Mill site.
-----------------------------------------------------------------------
SUMMARY: Notice is hereby given that the U.S. Nuclear Regulatory
Commission (NRC) has received, by letter dated October 24, 1997, an
application from Bear Creek Uranium Company (BCUC) to amend License
Condition (LC) 49 of Source Material License No. SUA-1310 for the Bear
Creek, Wyoming uranium mill site. By this amendment application, the
licensee proposes to modify LC 49 to change the completion date for two
site-reclamation milestones. The new dates proposed by BCUC would
extend the completion of placement of the final radon barrier by one
year and the completion of placement of the erosion protection cover by
five months. BCUC is requesting these extensions because
[[Page 65107]]
of delays caused by inclement weather conditions during this year's
construction season.
FOR FURTHER INFORMATION CONTACT: Charlotte E. Abrams, Uranium Recovery
Branch, Division of Waste Management, U.S. Nuclear Regulatory
Commission, Washington, DC 20555. Telephone (301) 415-5808.
SUPPLEMENTARY INFORMATION: The portion of LC 49 with the proposed
changes would read as follows:
A. (3) Placement of the final radon barrier designed and
constructed to limit radon emissions to an average flux of no more than
20 pCi/m \2\/s above background:
For tailings pile surface areas not covered by evaporation ponds
constructed as part of the groundwater corrective action program--
December 31, 1998.
For the total tailings pile surface after evaporation pond
removal--December 31, 1998.
B. Reclamation, to ensure required longevity of the covered
tailings and groundwater protection, shall be completed as
expeditiously as is reasonably achievable, in accordance with the
following target dates for completion:
(1) Placement of erosion protection as part of reclamation to
comply with Criterion 6 of Appendix A of 10 CFR Part 40--December 31,
1998.
BCUC's application to amend LC 49 of Source Material License SUA-
1310, which describes the proposed changes to the license condition and
the reasons for the request is being made available for public
inspection at the NRC's Public Document Room at 2120 L Street, NW
(Lower Level), Washington, DC 20555.
Notice of Opportunity for Hearing
The NRC hereby provides notice of an opportunity for a hearing on
the license amendment under the provisions of 10 CFR part 2, subpart L,
``Informal Hearing Procedures for Adjudications in Materials and
Operator Licensing Proceedings.'' Pursuant to Sec. 2.1205(a), any
person whose interest may be affected by this proceeding may file a
request for a hearing. In accordance with Sec. 2.1205(c), a request for
a hearing must be filed within 30 days of the publication of this
notice in the Federal Register. The request for a hearing must be filed
with the Office of the Secretary, either:
(1) By delivery to the Docketing and Service Branch of the Office
of the Secretary at One White Flint North, 11555 Rockville Pike,
Rockville, MD 20852; or
(2) By mail or telegram addressed to the Secretary, U.S. Nuclear
Regulatory Commission, Washington, DC 20555, Attention: Docketing and
Service Branch.
In accordance with 10 CFR 2.1205(e), each request for a hearing
must also be served, by delivering it personally or by mail, to:
(1) The applicant, Bear Creek Uranium Company, P.O. Box 366,
Casper, Wyoming 82602, Attention: Gary Chase; and
(2) The NRC staff, by delivery to the Executive Director for
Operations, One White Flint North, 11555 Rockville Pike, Rockville, MD
20852 or by mail addressed to the Executive Director for Operations,
U.S. Nuclear Regulatory Commission, Washington, DC 20555.
In addition to meeting other applicable requirements of 10 CFR Part
2 of the NRC's regulations, a request for a hearing filed by a person
other than an applicant must describe in detail:
(1) The interest of the requestor in the proceeding;
(2) How that interest may be affected by the results of the
proceeding, including the reasons why the requestor should be permitted
a hearing, with particular reference to the factors set out in
Sec. 2.1205(g);
(3) The requestor's areas of concern about the licensing activity
that is the subject matter of the proceeding; and
(4) The circumstances establishing that the request for a hearing
is timely in accordance with Sec. 2.1205(c).
The request must also set forth the specific aspect or aspects of
the subject matter of the proceeding as to which petitioner wishes a
hearing.
Dated at Rockville, Maryland, this 1st day of December 1997.
For the Nuclear Regulatory Commission.
Joseph J. Holonich,
Chief, Uranium Recovery Branch, Division of Waste Management, Office of
Nuclear Material Safety and Safeguards.
[FR Doc. 97-32271 Filed 12-9-97; 8:45 am]