DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Tendered for Filing With the Commission
December 4, 1998.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: New Major License.
b. Project No.: P-1218-014.
c. Date filed: November 25, 1998.
d. Applicant: Georgia Power Company.
e. Name of Project: Flint River Hydroelectric Project.
f. Location: The project is located on the Flint River near the
City of Albany, in Lee and Dougherty Counties, Georgia.
[[Page 68283]]
The project would not utilize any federal lands or facilities.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. Secs. 791(a)-
825(r).
h. Applicant Contact: Mr. Mike Phillips, Georgia Power Company, Bin
10151, 241 Ralph McGill Boulevard, NE, Atlanta, GA 30308-3374.
i. FERC Contact: Any questions on this notice should be addressed
to Allan E. Creamer, E-mail address allan.creamer@ferc.fed.us, or
telephone (202) 219-0365.
j. Description of Project: The project consists of the following
facilities: (1) The Muckafoonee Creek diversion dam, having (a) a 67-
foot non-overflow section, (b) a 22-foot sluice section with two 6- by
8-foot sluices, and (c) a 133-foot gated spillway section with six 21-
by 6-foot vertical lift gates; (2) a 500-foot-long reinforced concrete,
free-crested auxiliary spillway and a 2,600-foot-long earthen dike; (3)
the Flint River dam, having (a) a concrete intake structure, (b) a
powerhouse (integral with the dam) containing three 1.8-megawatt (MW)
generating units, for a total installed capacity of 5.4 MW, (c) a 464-
foot-long spillway with 16 Taintor gates, and (d) a 1,700-foot-long
earthen dike; (4) a 1,250-acre impoundment, impounding 10 miles of the
mainstem Flint River and the lower reaches of the Kinchafoonee and
Muckalee Creeks, at a water surface elevation of 181.8 feet plant
datum, with a total storage capacity of 7,800 acre-feet; and (5)
appurtenant facilities. The average annual generation is about 34.428
Gigawatt-hours.
k. Locations of the application: A copy of the application is
available for inspection and reproduction at the Commission's Public
Reference Room, located at 888 First Street, NE, Room 2A, Washington,
D.C. 20426, or by calling (202) 208-1371. The application may be viewed
on the web at www.ferc.fed.us. Call (202) 208-2222 for assistance. A
copy is also available for inspection and reproduction at the address
in item h above.
David P. Boergers,
Secretary.
[FR Doc. 98-32783 Filed 12-9-98; 8:45 am]