    Willamette Falls Hydroelectric Project, Portland General Electric 
    Company, and Smurfit Newsprint Corporation; Notice of Scoping Meetings 
    Pursuant to the National Environmental Policy Act of 1969 for an 
    Applicant Prepared Environmental Assessment
    
    December 9, 1999.
        The Commission's regulations at Section 4.34 allow applicants the 
    option of preparing their own Environmental Assessment (EA) for 
    hydropower projects, and filing the EA with their application as part 
    of an alternative licensing procedure. On December 10, 1999, the 
    Commission approved the use of an alternative licensing procedure in 
    the preparation of a new license application for the Willamette Falls 
    Hydroelectric Project, No. 2233.
        The alternative procedures include provisions for the distribution 
    of an initial information package (IIP), and for the cooperative 
    scoping of environmental issues and needed studies. On December 31, 
    1998, Portland General Electric (PGE) distributed the Willamette Falls 
    Project IIP. Public meetings were held on the IIP on February 17 and 
    February 18, 1999. Several tours of project facilities were conducted 
    during 1999.
        PGE intends to distribute Scoping Document 1 (SD1) the week of 
    December 13, 1999. Copies of SD1 can be obtained by calling the PGE 
    hydro licensing department at 503-464-8683 or via the PGE hydro 
    licensing web site located at http://www.pge-hl.com. Two public 
    meetings will be held to discuss SD1.
    
    Scoping Meetings
    
        PGE will hold public scoping meetings on January 20, 2000, pursuant 
    to the National Environmental Policy Act (NEPA) of 1969. At the scoping 
    meetings, PGE will: (1) Summarize the environmental issues tentatively 
    identified for analysis in the EA, (2) outline any resources they 
    believe would not require a detailed analysis; (3) identify reasonable 
    alternatives to be addressed in the EA; (4) solicit from the meeting 
    participants all available information, especially quantitative data, 
    on the resources at issue; and (5) encourage statements from experts 
    and the public on issues that should be analyzed in the EA.
        Although PGE's intent is to prepare an EA, there is the possibility 
    that an Environmental Impact Statement (EIS) will be required. 
    Nevertheless, this meeting will satisfy the NEPA scoping requirements, 
    irrespective of whether an EA or EIS is issued by the Commission.
        The times and locations of the scoping meeting are:
    
    Morning Scoping Meeting
    
    January 20, 2000
    9 am to 12 pm  Two World Trade Center--Rooms A&B, 121 SW Salmon Street, 
    Portland, OR 97204
    
    Evening Scoping Meeting
    
    January 20, 2000
    7 pm to 9 pm  Oregon City High School Cafeteria, 1306 12th Street, 
    Oregon City, OR 97045
    
        All interested individuals, organizations, and agencies are invited 
    and encouraged to attend any or all of the meetings to assist in 
    identifying and clarifying the scope of environmental issues that 
    should be analyzed in the EA.
    
    Scoping Meeting Procedures
    
        The meetings will be conducted according to the procedures used at 
    Commission scoping meetings. Both scoping meetings will be recorded, 
    and the transcripts will become part of the formal record of the 
    proceedings for this project. Those who choose not to speak during the 
    scoping meetings may instead submit written comments on the project.
        Because this meeting will be a NEPA scoping meeting under the APEA 
    process, the Commission does not intend to conduct a NEPA scoping 
    meeting after PGE's application and EA are filed with the Commission. 
    Instead, Commission staff will attend the meetings on January 20, 2000.
    
    [[Page 70010]]
    
    Commenting Deadline
    
        Written comments should be mailed or e-mailed to: Mr. David 
    Heintzman, Portland General Electric (3WTC-BRHL), 121 SW Salmon Street, 
    Portland, OR 97204; David__Heintzman@pgn.com
        All correspondence should be postmarked no later than March 21, 
    2000. Comments should show the following caption on the first page: 
    Scoping Comments, Willamette Falls Hydroelectric Project, Project No. 
    2233. Any comments sent to the Commission must include an original and 
    eight copies and be addressed to: David P. Boergers, Secretary, Federal 
    Energy Regulatory Commission, 888 First Street, NE, Washington, DC 
    20426. Please put the docket number, P-2233, on the first page.
        For further information please contact Julie Keil PGE at (503) 464-
    8864 or John Blair of the Commission at (202) 219-2845.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-32434 Filed 12-14-99; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
12/15/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-32434
Pages:
70009-70010 (2 pages)
Docket Numbers:
Project No. 2233
PDF File:
99-32434.pdf