99-32492. Niagara Mohawk Power Corporation; Nine Mile Point Nuclear Station, Unit No. 2; Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 64, Number 240 (Wednesday, December 15, 1999)]
    [Notices]
    [Pages 70073-70076]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-32492]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-410]
    
    
    Niagara Mohawk Power Corporation; Nine Mile Point Nuclear 
    Station, Unit No. 2; Environmental Assessment and Finding of No 
    Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering the issuance of an amendment to Facility Operating License 
    No. NPF-69 issued to Niagara Mohawk Power Corporation (the licensee), 
    for operation of the Nine Mile Point Nuclear Station, Unit 2 (NMP2), 
    located in Oswego County, New York.
    
    Environmental Assessment
    
    Identification of the Proposed Action
    
        The proposed amendment will revise the existing, or current, 
    Technical Specifications (CTS) for NMP2 in their entirety based on the 
    guidance provided in NUREG-1433 and NUREG-1434, ``Standard Technical 
    Specifications for General Electric Plants, BWR/4 and BWR/6,'' Revision 
    1, dated April 1995, and in the Commission's ``Final Policy Statement 
    on Technical Specifications Improvements for Nuclear Power Reactors,'' 
    published on July 22, 1993 (58 FR 39132). The proposed amendment is in 
    accordance with the licensee's amendment request dated October 16, 
    1998, as supplemented by letters dated December 30, 1998; and May 10, 
    June 15, July 30, August 11, 16, 19, 27, and September 10, 1999.
    
    The Need for the Proposed Action
    
        It has been recognized that nuclear safety in all nuclear power 
    plants would benefit from an improvement and standardization of plant 
    Technical Specifications (TS). The ``NRC Interim Policy Statement on 
    Technical Specification Improvements for Nuclear Power Plants,'' (52 FR 
    3788) contained proposed criteria for defining the scope of TS. Later, 
    the Commission's ``Final Policy Statement on Technical Specifications 
    Improvements for Nuclear Power Reactors,'' published on July 22, 1993 
    (58 FR 39132), incorporated lessons learned since publication of the 
    interim policy statement and formed the basis for revisions to 10 CFR 
    50.36, ``Technical Specifications.'' The ``Final Rule'' (60 FR 36953) 
    codified criteria for determining the content of TS. To facilitate the 
    development of standard TS for nuclear power reactors, each power 
    reactor vendor owners' group (OG) and the NRC staff developed standard 
    TS. For NMP2, the Improved Standard Technical Specifications (ISTS) are 
    in NUREG-1433 and NUREG-1434, Revision 1. These documents formed part 
    of the basis for the NMP2 Improved Technical Specifications (ITS) 
    conversion. The NRC Committee to Review Generic Requirements (CRGR) 
    reviewed the ISTS, made note of its safety merits, and indicated its 
    support of the conversion by operating plants to the ISTS.
    
    Description of the Proposed Change
    
        The proposed changes to the CTS are based on NUREG-1433 and NUREG-
    1434, Revision 1, and on guidance provided by the Commission in its 
    Final Policy Statement. The objective of the changes is to completely 
    rewrite, reformat, and streamline the CTS (i.e., to convert the CTS to 
    the ITS). Emphasis is placed on human factors principles to improve 
    clarity and understanding of the TS. The Bases section of the ITS has 
    been significantly expanded to clarify and better explain the purpose 
    and foundation of each specification. In addition to NUREG-1433 and 
    NUREG-1434, Revision 1, portions of the CTS were also used as the basis 
    for the development of the NMP2 ITS. Plant-specific issues (e.g., 
    unique design features, requirements, and operating practices) were 
    discussed with the licensee, and generic matters were discussed with 
    General Electric and other OGs.
    
    [[Page 70074]]
    
        The proposed changes from the CTS can be grouped into the following 
    four categories: relocated requirements, administrative changes, less 
    restrictive changes involving deletion of requirements, and more 
    restrictive changes. These categories are as follows:
        1. Relocated requirements (i.e., the licensee's LG or R changes) 
    are items which are in the CTS but do not meet the criteria set forth 
    in 10 CFR 50.36. This regulation establishes a specific set of 
    objective criteria for determining which regulatory requirements and 
    operating restrictions should be included in the TS. Relocation of 
    requirements to documents with an established control program, 
    controlled by the regulations or the TS, allows the TS to be reserved 
    only for those conditions or limitations upon reactor operation which 
    are necessary to obviate the possibility of an abnormal situation or 
    event giving rise to an immediate threat to public health and safety, 
    thereby focusing the scope of the TS. In general, the proposed 
    relocation of items from the CTS to the Updated Safety Analysis Report 
    (USAR), appropriate plant-specific programs, plant procedures, or ITS 
    Bases follows the guidance of NUREG-1433 and NUREG-1434, Revision 1. 
    Once these items have been relocated to other licensee-controlled 
    documents, the licensee may revise them under the provisions of 10 CFR 
    50.59 or other NRC-approved control mechanisms, which provide 
    appropriate procedural means to control changes by the licensee.
        2. Administrative changes (i.e., the licensee's A changes) involve 
    the reformatting and rewording of requirements, consistent with the 
    style of the ISTS in NUREG-1433 and NUREG-1434, Revision 1, to make the 
    TS more readily understandable to plant operators and other users. 
    These changes are purely editorial in nature, or involve the movement 
    or reformatting of requirements without affecting the technical 
    content. Application of a standardized format and style will also help 
    ensure consistency is achieved among specifications in the TS. These 
    changes involve reformatting and rewording; no technical changes 
    (either actual or interpretational) to the TS will be made with respect 
    to these changes.
        3. Less restrictive changes and the deletion of requirements 
    involve portions of the CTS (i.e., the licensee's LS and TR changes) 
    which (1) provide information that is descriptive in nature regarding 
    the equipment, systems, actions, or surveillances, (2) provide little 
    or no safety benefit, and (3) place an unnecessary burden on the 
    licensee. This information is proposed to be deleted from the CTS and, 
    in some instances, moved to the proposed Bases, USAR, or procedures. 
    The removal of descriptive information to the Bases of the TS, USAR, or 
    procedures is permissible because these documents will be controlled 
    through a process that utilizes 10 CFR 50.59 and other NRC-approved 
    control mechanisms. The relaxations of requirements were the result of 
    generic NRC actions or other analyses. They will be justified on a 
    case-by-case basis for NMP2 and described in the safety evaluation to 
    be issued with the license amendment.
        4. More restrictive requirements (i.e., the licensee's M changes) 
    are proposed to be implemented in some areas to impose more stringent 
    requirements than are in the CTS. In some cases, these more restrictive 
    requirements are being imposed to be consistent with the ISTS. Such 
    changes have been made after ensuring the previously evaluated safety 
    analysis for NMP2 was not affected. Also, other more restrictive 
    technical changes have been made to achieve consistency, correct 
    discrepancies, and remove ambiguities from the TS. Examples of more 
    restrictive requirements include: placing a limiting condition for 
    operation (LCO) on plant equipment which is not required by the CTS to 
    be operable; more restrictive requirements to restore inoperable 
    equipment; and more restrictive surveillance requirements.
        There are other proposed changes to the CTS that may be included in 
    the proposed amendment to convert the CTS to the ITS. These are beyond-
    scope changes (changes that are not consistent with the CTS and/or 
    NUREG-1433 and NUREG-1434, Revision 1) in that they are changes to both 
    the CTS and the ISTS. For the NMP2, these are the following:
        1. ITS 3.1.8, changing the Scram Discharge Volume Vent and Drain 
    Valve ACTIONS to allow continued operation with one valve in a line 
    inoperable by isolating the penetration within 7 days (ACTION A) and to 
    allow continued operation with two valves in a line inoperable by 
    isolating the penetration within 8 hours (ACTION B). The ISTS requires 
    the valves(s) to be restored to Operable status within 7 days.
        2. ITS 3.3.1.1, ITS 3.3.6.1, ITS 3.5.1, and ITS 3.5.2, adding a 
    Note to the Reactor Protection System (RPS) (Functions 3 and 4) and 
    Isolation (Main Steam Line Isolation Valve (MSIV) Functions) 
    Instrumentation Specifications exempting the sensors from response time 
    testing and a Note to the Emergency Core Cooling System (ECCS)--
    Operating and--Shutdown Specifications exempting the instrumentation 
    from response time testing.
        3. ITS 3.3.2.2, allowing the feedwater pump to be removed from 
    service in lieu of shutting down the unit to <25 percent="" rated="" thermal="" power="" (rtp)="" when="" the="" feedwater="" and="" main="" turbine="" high="" water="" level="" channels="" are="" inoperable="" and="" untripped.="" 4.="" its="" 3.3.3.1,="" its="" 3.3.3.2,="" its="" 3.3.8.2,="" its="" 3.3.8.3="" and="" its="" 3.4.7,="" adding="" a="" note="" to="" allow="" 6="" hours="" to="" do="" surveillance="" testing="" of="" the="" post="" accident="" monitoring,="" remote="" shutdown="" system,="" rps="" logic="" bus="" electrical="" power="" monitoring="" assemblies="" (epas),="" rps="" scram="" solenoid="" bus="" epas="" and="" leak="" detection="" system,="" instrumentation="" channels="" prior="" to="" entering="" actions.="" 5.="" its="" 3.3.4.2,="" adding="" an="" allowance="" to="" only="" remove="" the="" associated="" anticipated="" transient="" without="" scram="" (atws)-recirculation="" pump="" trip="" (rpt)="" breaker="" (fast="" speed="" or="" slow="" speed,="" as="" applicable)="" from="" service,="" in="" lieu="" of="" removing="" the="" entire="" pump="" from="" service.="" 6.="" its="" 3.3.5.1,="" its="" 3.3.8.1,="" its="" 3.3.8.2="" and="" its="" 3.3.8.3,="" changing="" the="" allowable="" values="" for="" (a)="" the="" low-pressure="" cooling="" injection="" (lpci)="" and="" high-pressure="" core="" spray="" (hpcs)="" minimum="" flow="" valves="" instrumentation;="" (b)="" the="" hpcs="" suppression="" pool="" water="" level="" swap="" over="" instrumentation;="" (c)="" the="" loss="" of="" voltage="" and="" degraded="" voltage="" functions,="" including="" time="" delays;="" (d)="" the="" undervoltage,="" overvoltage,="" and="" underfrequency="" functions="" for="" the="" rps="" logic="" bus="" epas;="" and="" (e)="" the="" undervoltage,="" overvoltage,="" and="" underfrequency="" functions="" for="" the="" rps="" scram="" solonoid="" bus="" epas.="" 7.="" its="" 3.3.6.1,="" deleting="" the="" mode="" 1="" and="" 2="" requirements="" for="" certain="" shutdown="" cooling="" isolation="" functions="" (residual="" heat="" removal="" (rhr)="" equipment="" area="" temperature,="" reactor="" building="" pipe="" chase="" temperature,="" reactor="" building="" temperature,="" and="" reactor="" vessel="" water="" level--low,="" level="" 3.)="" 8.="" its="" 3.3.8.1="" and="" its="" 3.3.5.1,="" deleting="" the="" group="" 4="" valves="" from="" isolation="" instrumentation="" requirements.="" 9.="" its="" 3.3.8.1,="" changing="" the="" requirement="" to="" only="" requiring="" 2="" channels="" of="" degraded="" voltage="" and="" loss="" of="" voltage="" in="" lieu="" of="" three="" channels.="" 10.="" its="" sr="" 3.4.1.1="" requiring="" verification="" every="" 12="" hours="" that="" operation="" is="" in="" the="" ``unrestricted="" zone''="" of="" its="" figure="" 3.4.1-1.="" 11.="" its="" 3.4.1,="" changing="" from="" 2="" hours="" to="" 8="" hours,="" the="" frequency="" for="" determining="" the="" average="" power="" range="" monitors="" (aprm)="" and="" low="" power="" range="" monitors="" (lprm)="" baseline="" noise="" level="" the="" first="" time="" the="" unit="" is="" in="" the="" restricted="" zone.="" [[page="" 70075]]="" 12.="" its="" 3.4.5,="" changing="" the="" frequency="" for="" monitoring="" the="" floor="" drain="" leakage="" rate="" from="" 8="" hours="" to="" 12="" hours,="" and="" changing="" the="" airborne="" radioactivity="" monitoring="" surveillance="" to="" be="" every="" 8="" hours.="" 13.="" its="" 3.5.1,="" changing="" the="" current="" number="" of="" automatic="" depression="" system="" (ads)="" valves="" required="" to="" operate="" from="" seven="" to="" six.="" 14.="" its="" 3.5.1,="" modifying="" the="" current="" requirement="" of="" manually="" opening="" the="" ads="" valves="" to="" only="" require="" the="" ads="" actuators="" to="" be="" cycled.="" 15.="" its="" 3.6.1.3,="" changing="" the="" current="" requirement="" that="" each="" excess="" flow="" check="" valve="" (efcv)="" must="" ``check="" flow''="" to="" requiring="" each="" efcv="" to="" actuate="" to="" its="" isolation="" position="" on="" an="" actual="" or="" simulated="" instrument="" line="" break="" signal.="" 16.="" its="" 3.6.1.3,="" changing="" the="" evolution="" to="" suspend="" the="" purging="" and="" venting="" lco="" actions="" to="" within="" 1="" hour,="" when="" standby="" gas="" treatment="" (sgt)="" subsystem(s)="" are="" inoperable.="" 17.="" its="" 3.6.1.6,="" its="" 3.6.2.3="" and="" its="" 3.5.2.4,="" deleting="" the="" current="" requirements="" to="" verify="" position="" of="" ``automatic''="" valves="" in="" the="" rhr="" drywell="" spray,="" rhr="" suppression="" cooling,="" and="" rhr="" suppression="" pool="" spray="" systems.="" 18.="" its="" 3.6.1.6="" and="" its="" 3.6.2.4,="" deleting="" the="" current="" requirement="" that="" drywell="" spray="" and="" suppression="" pool="" spray="" flows="" be="" through="" the="" heat="" exchanger.="" 19.="" its="" 3.7.2="" and="" its="" 3.7.3,="" allowing="" a="" 7-day="" restoration="" time="" when="" both="" control="" room="" envelope="" filtration="" (cref)="" subsystems="" are="" inoperable="" and="" a="" 30-day="" restoration="" time="" when="" both="" control="" room="" envelope="" alternating="" current="" (ac)="" subsystems="" are="" inoperable,="" provided="" the="" remaining="" components="" of="" the="" cref="" system="" or="" control="" room="" envelope="" ac="" system="" maintains="" the="" cref="" system="" or="" control="" room="" envelope="" ac="" system="" safety="" function,="" as="" applicable.="" 20.="" its="" 3.8.1,="" its="" 3.8.2,="" and="" its="" 3.8.3,="" changing="" ac="" sources--="" operating,="" ac="" sources--shutdown="" and="" diesel="" fuel="" oil,="" lube="" oil,="" and="" starting="" air="" specifications="" to="" include:="" (a)="" more="" restrictive="" upper="" and="" lower="" voltage="" limits="" for="" various="" diesel="" generator="" (dg)="" surveillances;="" (b)="" increasing="" the="" killowatt="" (kw)="" value="" for="" the="" single="" largest="" load="" surveillance="" requirement="" (sr)="" for="" the="" division="" 3="" dg;="" (c)="" relaxing="" the="" load="" range="" values="" for="" the="" 24-hour="" dg="" run="" to="" be="" consistent="" with="" regulatory="" guide="" (rg)="" 1.9="" revision="" 3="" (ists="" bases="" says="" 100="" percent="" for="" 22="" hours="" and="" 110="" percent="" for="" 2="" hours="" is="" consistent="" with="" rg="" 1.9="" reference="" 3,="" which="" is="" not="" accurate);="" (d)="" increasing="" the="" dg="" start="" time="" in="" the="" event="" of="" a="" loss="" of="" voltage="" signal="" from="" 13="" seconds="" to="" 13.12="" seconds;="" (e)="" adding="" a="" note="" which="" exempts="" surveillances="" pertaining="" to="" a="" dg="" starting="" on="" a="" loss-of-coolant="" accident="" (loca)="" signal="" and="" a="" loca/loss="" of="" offsite="" power="" (loop)="" signal="" while="" in="" modes="" 4="" and="" 5="" and="" during="" handling="" of="" irradiated="" fuel="" in="" the="" secondary="" containment="" when="" the="" eccs="" subsystems="" are="" not="" required="" to="" be="" operable;="" and="" (f)="" increasing="" the="" fuel="" oil="" storage="" tank="" limits="" for="" the="" division="" 1="" and="" 2="" dgs="" as="" well="" as="" the="" 6-="" day="" limits="" for="" all="" three="" dgs.="" 21.="" its="" 3.8.4,="" changing="" the="" dc="" sources--operating="" specification="" by:="" (a)="" revising="" the="" battery="" load="" profile="" to="" be="" consistent="" with="" the="" load="" profile="" specified="" in="" the="" usar;="" and="" (b)="" adding="" an="" allowance="" to="" perform="" a="" modified="" performance="" discharge="" test="" every="" cycle="" in="" lieu="" of="" a="" service="" test.="" 22.="" its="" 3.8.7,="" requiring="" that="" the="" inverters="" be="" capable="" of="" being="" powered="" from="" an="" uninterruptible="" power="" supply="" (direct="" current="" (dc)="" source).="" currently,="" this="" is="" not="" required;="" this="" is="" a="" more="" restrictive="" change.="" 23.="" its="" 3.3.8.3,="" specifying="" an="" allowable="" value="" in="" the="" its="" for="" the="" time="" delay="" setting="" of="" the="" rps="" epa--solenoid="" instrumentation.="" 24.="" its="" 3.3.8.1,="" deleting="" a="" requirement="" in="" the="" ists="" for="" performing="" a="" channel="" check="" on="" undervoltage="" relays;="" the="" status="" of="" relays="" are="" continuously="" monitored.="" 25.="" its="" 3.3.8.2,="" specifying="" allowances="" in="" allowable="" values="" for="" the="" time="" delay="" settings="" of="" the="" rps="" epa="" logic="" instrumentation.="" 26.="" its="" 3.3.4.2,="" adding="" additional="" verification="" of="" atws="" trip="" function="" bypass="" and="" time="" delays.="" 27.="" its="" 3.3.8.1,="" the="" sts="" allows="" a="" 2-hour="" delay="" from="" entering="" into="" the="" associated="" conditions="" and="" required="" actions="" for="" a="" channel="" placed="" in="" an="" inoperable="" status="" solely="" for="" the="" performance="" of="" required="" surveillances,="" provided="" the="" associated="" function="" maintains="" dg="" initiation="" capability.="" this="" is="" changed="" in="" the="" its="" ``provided="" the="" associated="" function="" maintains="" ``lop''="" [loss="" of="" power]="" initiation="" capability.''="" 28.="" its="" 5.5.9.1.a,="" adding="" ``specific="" gravity''="" to="" the="" acceptability="" of="" new="" fuel="" oil="" before="" adding="" to="" the="" dg="" fuel="" tanks.="" 29.="" its="" sr="" 3.6.3.1.2,="" adding="" a="" description="" of="" an="" additional="" requirement="" in="" the="" bases="" sr="" 3.6.3.1.2="" regarding="" when="" to="" perform="" the="" surveillance="" (``within="" 30="" minutes="" following="" heatup="" of="" the="" system="" to="" normal="" operating="" temperature.'')="" 30.="" its="" sr="" 3.3.1.1.16,="" modifying="" the="" response="" time="" testing="" requirement="" for="" function="" 9,="" turbine="" control="" valve="" fast="" closure,="" trip="" oil="" pressure--low="" by="" stating="" that="" the="" response="" time="" is="" measured="" from="" the="" start="" of="" the="" control="" valve="" fast="" closure,="" not="" when="" the="" sensor="" (oil="" pressure="" sensor)="" exceeds="" its="" setpoint.="" 31.="" its="" 3.3.5.1,="" specifying="" an="" ads="" pressure="" setpoint="" of="" 150="" psig,="" implementing="" topical="" report="" nedc-32291,="" and="" making="" other="" changes="" associated="" with="" moving="" group="" 4="" isolation="" valves="" into="" the="" eccs="" ts="" in="" the="" its.="" 32.="" its="" 3.3.5.1,="" table="" 3.3.5.1-1,="" specifying="" an="" ads="" pressure="" setpoint="" for="" low-pressure="" core="" spray="" (lpcs)="" pump="" discharge="" pressure--="" high="" to="" be="" 150="" psig="" based="" on="" implementation="" of="" topical="" report="" nedc-="" 32291.="" 33.="" its="" 3.3.2.1,="" deleting="" operational="" details="" in="" cts="" table="" 3.3.6-2="" (control="" rod="" block="" instrumentation="" set="" points)="" not="" required="" to="" be="" ts,="" and="" providing="" allowable="" values="" based="" on="" nedo-2411="" which="" is="" not="" referenced="" in="" the="" ists.="" 34.="" its="" 3.3.6.1,="" deleting="" the="" reactor="" core="" isolation="" cooling="" (rcic)="" drywell="" pressure="" high="" isolation="" functions,="" providing="" new="" rcic/rhr="" steam="" flow="" timer="" and="" sgt="" exhaust="" radiation="" high="" isolation="" functional="" allowable="" values,="" and="" deleting="" the="" main="" steam="" line="" (msl)="" radiation="" high="" isolation="" function.="" 35.="" its="" 3.6.1.2,="" changing="" the="" requirement="" to="" verify="" that="" the="" air="" lock="" door="" seal="" leakage="" rate="" is="" within="" limit="" from="" ``once="" per="" 7="" days''="" to="" ``once="" in="" 30="" days.''="" 36.="" its="" 3.6.1.7,="" adding="" a="" note="" to="" allow="" a="" separate="" condition="" entry="" for="" each="" suppression="" chamber-to-drywell="" vacuum="" breaker.="" 37.="" its="" 3.6.1.7,="" changing="" the="" action="" statement="" into="" two="" action="" statements:="" its="" 3.6.1.7="" action="" b="" addresses="" the="" closing="" of="" the="" open="" vacuum="" breaker="" within="" 72="" hours,="" while="" its="" 3.6.1.7="" action="" c="" addresses="" the="" verification/closing="" of="" the="" other="" vacuum="" breaker="" in="" the="" line="" within="" 2="" hours.="" however,="" both="" its="" 3.6.1.7="" conditions="" b="" and="" c="" have="" been="" modified="" such="" that="" the="" words="" ``one="" or="" more="" lines="" with''="" have="" been="" added.="" 38.="" its="" 3.4.4,="" increasing="" the="" lift="" setpoint="" tolerance="" for="" the="" safety/relief="" valves="" to="" 3="" percent.="" 39.="" its="" 3.3.1.1,="" deleting="" the="" msl="" radiation="" monitor="" reactor="" trip="" requirement="" and="" surveillance="" requirement="" based="" on="" the="" application="" of="" nedo-31400a.="" 40.="" its="" 3.7.2,="" sr="" 3.7.2.1,="" deleting="" the="" staggered="" testing="" requirement="" for="" the="" cref="" subsystem.="" 41.="" its="" 3.3.1.2,="" adding="" a="" note="" to="" its="" sr="" 3.3.1.2.5="" that="" defers="" determination="" of="" the="" signal-to-noise="" ratio="" in="" mode="" 5="" if="" less="" than="" or="" equal="" to="" four="" fuel="" assemblies="" are="" adjacent="" to="" the="" source="" range="" monitors="" (srm)="" and="" no="" fuel="" is="" in="" the="" quadrant.="" 42.="" its="" 3.3.1.2,="" changing="" the="" sts="" action="" to="" ``initiate="" action="" to="" insert="" all="" [[page="" 70076]]="" insertable="" control="" rods="" *="" *="" *''="" to="" ``initiate="" action="" to="" ``fully''="" insert="" all="" insertable="" control="" rods="" *="" *="" *''="" 43.="" its="" 3.3.5.1,="" its="" table="" 3.3.5.1-1,="" changing="" footnote="" (a)="" from="" the="" sts="" to="" include="" a="" citation="" of="" lco="" 3.5.2="" which="" amplifies="" the="" eccs="" equipment="" instrumentation="" requirements.="" 44.="" its="" 5.5.2.b,="" adding="" a="" note="" that="" the="" provisions="" of="" sr="" 3.0.2="" apply="" to="" integrated="" leak="" tests="" at="" 24="" months.="" 45.="" its="" 3.8.8,="" incorporating="" changes="" to="" condition="" a,="" b="" and="" c="" of="" the="" sts="" applicable="" to="" ``one="" or="" more''="" divisions="" and="" to="" ``one="" or="" both.''="" 46.="" its="" 3.6.4.1,="" incorporating="" wording="" changes="" that="" alter="" the="" meaning="" of="" containment="" operability="" with="" respect="" to="" meeting="" surveillance="" requirements="" which="" relates="" to="" whether="" the="" inoperability="" of="" the="" standby="" gas="" treatment="" system="" constitutes="" a="" failure="" of="" the="" surveillance="" of="" the="" secondary="" containment="" integrity="" test.="" environmental="" impacts="" of="" the="" proposed="" action="" the="" commission="" has="" completed="" its="" evaluation="" of="" the="" proposed="" conversion="" of="" the="" cts="" to="" the="" its="" for="" nmp2,="" including="" the="" beyond-scope="" issues="" discussed="" above.="" changes="" which="" are="" administrative="" in="" nature="" have="" been="" found="" to="" have="" no="" effect="" on="" the="" technical="" content="" of="" the="" ts.="" the="" increased="" clarity="" and="" understanding="" these="" changes="" bring="" to="" the="" ts="" are="" expected="" to="" improve="" the="" operators'="" control="" of="" nmp2="" in="" normal="" and="" accident="" conditions.="" relocation="" of="" requirements="" from="" the="" cts="" to="" other="" licensee-="" controlled="" documents="" does="" not="" change="" the="" requirements="" themselves.="" future="" changes="" to="" these="" requirements="" may="" then="" be="" made="" by="" the="" licensee="" under="" 10="" cfr="" 50.59="" and="" other="" nrc-approved="" control="" mechanisms="" which="" will="" ensure="" continued="" maintenance="" of="" adequate="" requirements.="" all="" such="" relocations="" have="" been="" found="" to="" be="" consistent="" with="" the="" guidelines="" of="" nureg-1433="" and="" nureg-1434="" and="" 10="" cfr="" 50.36="" does="" not="" require="" that="" the="" requirements="" be="" included="" in="" the="" ts.="" changes="" involving="" more="" restrictive="" requirements="" have="" been="" found="" to="" enhance="" plant="" safety.="" changes="" involving="" less="" restrictive="" requirements="" have="" also="" been="" reviewed.="" when="" requirements="" have="" been="" shown="" to="" provide="" little="" or="" no="" safety="" benefit,="" or="" to="" place="" an="" unnecessary="" burden="" on="" the="" licensee,="" their="" removal="" from="" the="" ts="" was="" justified.="" in="" most="" cases,="" relaxations="" previously="" granted="" to="" individual="" plants="" on="" a="" plant-specific="" basis="" were="" the="" result="" of="" a="" generic="" action,="" or="" of="" agreements="" reached="" during="" discussions="" with="" the="" og,="" and="" found="" to="" be="" acceptable="" for="" the="" plant.="" generic="" relaxations="" contained="" in="" nureg-1433="" and="" nureg-1434,="" revision="" 1,="" have="" been="" reviewed="" by="" the="" nrc="" staff="" and="" found="" to="" be="" acceptable.="" in="" summary,="" the="" proposed="" revisions="" to="" the="" ts="" were="" found="" to="" provide="" control="" of="" plant="" operations="" such="" that="" reasonable="" assurance="" will="" be="" provided="" that="" the="" health="" and="" safety="" of="" the="" public="" will="" be="" adequately="" protected.="" the="" proposed="" amendment="" will="" not="" increase="" the="" probability="" or="" consequences="" of="" accidents,="" will="" not="" change="" the="" quantity="" or="" types="" of="" any="" effluent="" that="" may="" be="" released="" offsite,="" and="" will="" not="" significantly="" increase="" the="" occupational="" or="" public="" radiological="" exposure.="" also,="" these="" changes="" do="" not="" increase="" the="" licensed="" power="" and="" allowable="" effluents="" for="" the="" plant.="" the="" changes="" will="" not="" create="" any="" new="" or="" unreviewed="" environmental="" impacts="" that="" were="" not="" considered="" in="" the="" final="" environmental="" statement="" (fes)="" related="" to="" the="" operation="" of="" nmp2,="" (nureg-="" 1085,="" dated="" may="" 1985).="" therefore,="" there="" are="" no="" significant="" radiological="" impacts="" associated="" with="" the="" proposed="" amendment.="" with="" regard="" to="" potential="" non-radiological="" impacts,="" the="" proposed="" amendment="" involves="" features="" located="" entirely="" within="" the="" restricted="" area="" for="" the="" plant="" defined="" in="" 10="" cfr="" part="" 20="" and="" does="" not="" involve="" any="" historical="" sites.="" they="" do="" not="" affect="" non-radiological="" plant="" effluents="" and="" have="" no="" other="" environmental="" impact.="" they="" do="" not="" increase="" any="" discharge="" limit="" for="" the="" plant.="" therefore,="" there="" are="" no="" significant="" non-="" radiological="" environmental="" impacts="" associated="" with="" the="" proposed="" amendment.="" accordingly,="" the="" commission="" concludes="" that="" there="" are="" no="" significant="" environmental="" impacts="" associated="" with="" the="" proposed="" amendment.="" alternatives="" to="" the="" proposed="" action="" as="" an="" alternative="" to="" the="" proposed="" action,="" the="" staff="" considered="" denial="" of="" the="" proposed="" action="" (i.e.,="" the="" ``no-action''="" alternative).="" denial="" of="" the="" application="" would="" result="" in="" no="" change="" in="" current="" environmental="" impacts.="" the="" environmental="" impacts="" of="" the="" proposed="" action="" and="" the="" alternative="" action="" are="" similar.="" alternative="" use="" of="" resources="" this="" action="" does="" not="" involve="" the="" use="" of="" any="" resources="" not="" previously="" considered="" in="" the="" final="" environmental="" statement="" for="" nmp2,="" dated="" may="" 1985.="" agencies="" and="" persons="" consulted="" in="" accordance="" with="" its="" stated="" policy,="" the="" staff="" consulted="" with="" the="" new="" york="" state="" official,="" jack="" spath,="" of="" the="" new="" york="" energy="" and="" research="" authority="" on="" november="" 4,="" 1999,="" regarding="" the="" environmental="" impact="" of="" the="" proposed="" amendment.="" the="" state="" official="" had="" no="" comments.="" finding="" of="" no="" significant="" impact="" on="" the="" basis="" of="" the="" environmental="" assessment,="" the="" commission="" concludes="" that="" the="" proposed="" amendment="" will="" not="" have="" a="" significant="" adverse="" effect="" on="" the="" quality="" of="" the="" human="" environment.="" accordingly,="" the="" commission="" has="" determined="" not="" to="" prepare="" an="" environmental="" impact="" statement="" for="" the="" proposed="" action.="" for="" further="" details="" with="" respect="" to="" the="" proposed="" action,="" see="" the="" licensee's="" application="" dated="" october="" 16,="" 1998,="" as="" supplemented="" by="" letters="" dated="" december="" 30,="" 1998;="" and="" may="" 10,="" june="" 15,="" july="" 30,="" august="" 11,="" 16,="" 19,="" 27,="" and="" september="" 10,="" 1999,="" which="" are="" available="" for="" public="" inspection="" at="" the="" commission's="" public="" document="" room,="" the="" gelman="" building,="" 2120="" l="" street,="" nw.,="" washington,="" dc.="" publically="" available="" records="" will="" be="" accessible="" electronically="" from="" the="" adams="" public="" library="" component="" on="" the="" nrc="" web="" site,="">http://www.nrc.gov (the Electronic 
    Reading Room).
    
        Dated at Rockville, Maryland, this 9th day of December 1999.
    
        For the Nuclear Regulatory Commission.
    Alexander W. Dromerick,
    Acting Chief, Section 1, Project Directorate I, Division of Licensing 
    Project Management, Office of Nuclear Reactor Regulation.
    [FR Doc. 99-32492 Filed 12-14-99; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
12/15/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-32492
Pages:
70073-70076 (4 pages)
Docket Numbers:
Docket No. 50-410
PDF File:
99-32492.pdf