97-32841. Notice of Application Ready for Environmental Analysis  

  • [Federal Register Volume 62, Number 242 (Wednesday, December 17, 1997)]
    [Notices]
    [Pages 66075-66076]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-32841]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    
    
    Notice of Application Ready for Environmental Analysis
    
    December 11, 1997.
        Take notice that the following hydroelectric application has been 
    filed with the Commission and is available for public inspection:
        a. Type of Application: New Major License.
        b. Project No.: 1991-09.
        c. Date filed: April 1, 1996.
        d. Applicant: City of Bonners Ferry.
        e. Name of Project: Moyie River Hydroelectric.
        f. Location: On the Moyie River in Boundary County, Idaho.
        g. Filed Pursuant to: Federal Power Act 16 U.S.C. Sec. Sec. 791(a)-
    825(r).
        h. Applicant Contact: Mike Woodward, P.E., City of Bonners Ferry, 
    7232 Main Street, Bonners Ferry, ID 83805, 208 267-3105.
        i. FERC Contact: Tim Looney at (202) 219-2852.
        j. The project would consist of: (1) a 92-foot-concrete dam, 
    impounding a 450-acre-foot reservoir, (2) a combination penstock/
    pressure tunnel about 990 feet long, (3) three powerhouses with a total 
    installed capacity of 3,950 kilowatts, (4) a 1.3-mile-long, 13.8-
    kilovolt transmission line, and (5) appurtenant facilities.
        k. Status of Environmental Analysis: This application is now ready 
    for
    
    [[Page 66076]]
    
    environmental analysis--see attached paragraph D9.
        l. Deadline for comments, recommendations, terms and conditions, 
    and prescriptions: See paragraph D9.
        m. This notice also consists of the following standard paragraphs: 
    A4 and D9.
        n. Available Locations of Application: A copy of the application, 
    is available for inspection and reproduction at the Commission's Public 
    Reference and Files Maintenance Branch, located at 888 First Street, 
    N.E., Washington, D.C. 20426, or by calling (202) 208-1371. A copy is 
    also available for inspection and reproduction at the address shown in 
    item h above.
        A4. Development Application--Public notice of the filing of the 
    initial development application, which has already been given, 
    established the due date for filing competing applications or notices 
    of intent. Under the Commission's regulations, any competing 
    development application must be filed in response to and in compliance 
    with public notice of the initial development application. No competing 
    applications or notices of intent may be filed in response to this 
    notice.
        D9. Filing and Service of Responsive Documents:--The application is 
    ready for environmental analysis at this time, and the Commission is 
    requesting comments, reply comments, recommendations, terms and 
    conditions, and prescriptions.
        The Commission directs, pursuant to Section 4.34(b) of the 
    Regulations (see Order No. 533 issued May 8, 1991, 56 FR 23108, May 20, 
    1991) that all comments, recommendations, terms and conditions and 
    prescriptions concerning the application be filed with the Commission 
    within 60 days from the issuance date of this notice. All reply 
    comments must be filed with the Commission within 105 days from the 
    date of this notice.
        Anyone may obtain an extension of time for these deadlines from the 
    Commission only upon a showing of good cause or extraordinary 
    circumstances in accordance with 18 CFR 385.2008.
        All filings must (1) bear in all capital letters the title 
    ``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND 
    CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
    name of the applicant and the project number of the application to 
    which the filing responds; (3) furnish the name, address, and telephone 
    number of the person submitting the filing; and (4) otherwise comply 
    with the requirements of 18 CFR 385.2001 through 385.2005. All 
    comments, recommendations, terms and conditions or prescriptions must 
    set forth their evidentiary basis and otherwise comply with the 
    requirements of 18 CFR 4.34(b). Any of these documents must be filed by 
    providing the original and the number of copies required by the 
    Commission's regulations to: The Secretary, Federal Energy Regulatory 
    Commission, 888 First Street, N.E., Washington, D.C. 20426. An 
    additional copy must be sent to Director, Division of Project Review, 
    Office of Hydropower Licensing, Federal Energy Regulatory Commission, 
    at the above address. Each filing must be accompanied by proof of 
    service on all persons listed on the service list prepared by the 
    Commission in this proceeding, in accordance with 18 CFR 4.34(b), and 
    385.2010.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 97-32841 Filed 12-16-97; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
12/17/1997
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
97-32841
Pages:
66075-66076 (2 pages)
PDF File:
97-32841.pdf