97-33161. Koch Gateway Pipeline Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 62, Number 244 (Friday, December 19, 1997)]
    [Notices]
    [Pages 66620-66621]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-33161]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP98-126-000]
    
    
    Koch Gateway Pipeline Company; Notice of Request Under Blanket 
    Authorization
    
    December 15, 1997.
        Take notice that on December 11, 1997, Koch Gateway Pipeline 
    Company (Koch Gateway), P.O. Box 1478, Houston, Texas 77251-1478, filed 
    in Docket No. CP98-126-000, a request pursuant to Secs. 157.205 and 
    157.216(b) for approval to abandon an inactive 2-inch delivery tap and 
    meter station and 2-inch delivery lateral, under the blanket 
    certificate issued in Docket No. CP82-430-000, pursuant to Section 7(c) 
    of the Natural Gas Act, all as more fully set forth in the request 
    which is on file with the Commission and open to public inspection.
        Koch Gateway proposes to abandon by removal an inactive 2-inch tap 
    and meter station and to abandon in place approximately 150 feet of 2-
    inch delivery lateral that formerly served the Shelbyville city gate on 
    behalf of Entex Inc. (Entex), a local distribution company, in Shelby 
    County, Texas. Koch Gateway states that Entex would continue to serve 
    its customers from its existing distribution system. It is further 
    stated that service to the end-users would not be affected. Koch 
    Gateway verifies that Entex agrees to the
    
    [[Page 66621]]
    
    proposed abandonment. Koch Gateway states that Entex has not used this 
    point since 1988. Koch Gateway further states that it would plug and 
    remove the tap, remove all above ground facilities and after cleaning 
    the pipe and filling it with either water or nitrogen, would abandon 
    the lateral in place.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 97-33161 Filed 12-18-97; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
12/19/1997
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
97-33161
Pages:
66620-66621 (2 pages)
Docket Numbers:
Docket No. CP98-126-000
PDF File:
97-33161.pdf