94-31165. East Tennessee Natural Gas Company; Notice of Application  

  • [Federal Register Volume 59, Number 243 (Tuesday, December 20, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-31165]
    
    
    [[Page Unknown]]
    
    [Federal Register: December 20, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP95-118-000]
    
     
    
    East Tennessee Natural Gas Company; Notice of Application
    
    December 14, 1994.
        Take notice that on December 12, 1994, East Tennessee Natural Gas 
    Company (East Tennessee), P.O. Box 2511, Houston, Texas 77252, filed in 
    Docket No. CP95-118-000 an application pursuant to Section 7(c) of the 
    Natural Gas Act for a certificate of public convenience and necessity 
    permitting it to construct and operate certain pipeline loop and 
    compression facilities to ensure continued transportation service to 
    its shippers, all as more fully set forth in the application which is 
    on file with the Commission and open to public inspection.
        East Tennessee proposes to construct and operate 2.14 miles of 12-
    inch pipeline loop and 3.02 miles of pipeline loop, both in Washington 
    County, Virginia as well as uprate three existing turbines at its 
    Compressor Station No. 3110, in Morgan County, Tennessee to Solar 
    Saturn Model T-1300's, each with an I.S.O. rating of 1360 horsepower, 
    resulting in an increase of 960 horsepower. East Tennessee estimates a 
    construction cost of $4,264,978, which would be financed initially with 
    funds on hand, funds generated internally, borrowing under revolving 
    credit agreements or short-term financing and which would be rolled 
    into permanent financing.
        East Tennessee states that its current total firm contractual 
    commitment is approximately 476,507 dt equivalent of natural gas per 
    day. It is indicated that since 1988 East Tennessee's system has been 
    designed to meet this obligation in part by receiving approximately 
    5,000 dt equivalent of natural gas per day from Columbia Gas 
    Transmission Corporation (Columbia Gas) and delivering it to Roanoke 
    Gas Company (Roanoke) via an interconnect between Roanoke and Columbia 
    Gas. It is stated that in 1988 East Tennessee and Roanoke entered into 
    an operating agreement specifically providing that approximately 5,000 
    dt equivalent of natural gas per day of Roanoke's total transportation 
    quantity of 9,789 dt equivalent of natural gas per day could be 
    delivered to Roanoke at the Columbia Gas interconnect. It is stated 
    that this arrangement enabled East Tennessee to reduce the volumes that 
    it was required to transport on its system to Roanoke and thus make 
    those volumes available for East Tennessee's other customers.
        East Tennessee states that the operating agreement has expired by 
    its own terms and that Roanoke has advised that it was not interested 
    in extending the agreement. It is indicated that, as a result of 
    terminated agreement, East Tennessee now proposes to construct and 
    operate the above-described facilities.
        Any person desiring to be heard or to make any protest with 
    reference to said application should on or before January 4, 1995, file 
    with the Federal Energy Regulatory Commission, Washington, D.C. 20426, 
    a motion to intervene or a protest in accordance with the requirements 
    of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
    385.211) and the Regulations under the Natural Gas Act (18 CFR 157.10). 
    All protests filed with the Commission will be considered by it in 
    determining the appropriate action to be taken but will not serve to 
    make the protestants parties to the proceeding. Any person wishing to 
    become a party to a proceeding or to participate as a party in any 
    hearing therein must file a motion to intervene in accordance with the 
    Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to the jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and Procedure, a hearing will be 
    held without further notice before the Commission or its designee on 
    this application if no motion to intervene is filed within the time 
    required herein, if the Commission on its own review of the matter 
    finds that a grant of the certificate is required by the public 
    convenience and necessity. If a motion for leave to intervene is timely 
    filed, or if the Commission on its own motion believes that a formal 
    hearing is required, further notice of such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for East Tennessee to appear or be represented 
    at the hearing.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 94-31165 Filed 12-19-94; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
12/20/1994
Department:
Energy Department
Entry Type:
Uncategorized Document
Document Number:
94-31165
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: December 20, 1994, Docket No. CP95-118-000