96-32349. GPU Nuclear Corporation Oyster Creek Nuclear Generating Station Issuance of Director's Decision Under 10 CFR 2.206  

  • [Federal Register Volume 61, Number 246 (Friday, December 20, 1996)]
    [Notices]
    [Pages 67352-67354]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-32349]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-219]
    
    
    GPU Nuclear Corporation Oyster Creek Nuclear Generating Station 
    Issuance of Director's Decision Under 10 CFR 2.206
    
        Notice is hereby given that by letters dated May 11 and June 14, 
    1996, Mr. deCamp, on behalf of Oyster Creek Nuclear Watch (Petitioner), 
    requested NRC, pursuant to 10 CFR 2.206, to investigate and correct a 
    highly inaccurate public statement in the ``Neighborhood Update'' (the 
    licensee's news magazine) and apparently false public testimony given 
    by GPU management at a local zoning board hearing and to take 
    appropriate disciplinary action in the matter. Specifically, 
    Petitioner's concerns relate to (1) the statement that GPU and the 
    Commission agree that a license amendment request that involves the 
    movement of spent fuel from the Oyster Creek Nuclear Generating Station 
    spent fuel pool to the storage facility while the plant is at power 
    ``is not a safety issue but a procedural one'' and (2) whether there is 
    some special factor at Oyster Creek that would indeed justify Mr. 
    Barton's sworn statement that it is unsafe to operate the Oyster Creek 
    reactor without full core offload capacity. If no special situation is 
    found that prevents Oyster Creek from operating without full offload 
    capacity, Petitioner requests that the Commission take appropriate 
    disciplinary action against GPU Nuclear management for making a false 
    statement under oath.
        As a basis for the request regarding the first concern that the 
    statement in the ``Neighborhood Update'' is untrue, Petitioner 
    referenced the following excerpts from NRC Bulletin 96-02 (NRCB 96-02) 
    of April 11, 1996:
        The NRC staff audited both the initial and updated 10 CFR 50.59 
    evaluations performed by the licensee [GPU Nuclear] and determined 
    that the proposed cask movement activities represent an unreviewed 
    safety question that should be submitted to the NRC for review and 
    approval pursuant to the requirements of 10 CFR 50.59 and 50.90. * * 
    * Accordingly, as defined in 10 CFR 50.59(c), if an activity is 
    found to involve an unreviewed safety question, an application for a 
    license amendment must be filed with the Commission pursuant to 10 
    CFR 50.90.
    
        As a basis for the Petitioner's other concerns, the Petitioner sets 
    forth the relevant excerpts from Mr. Barton's testimony of March 7, 
    1994, and states that ``the NRC ruled in February 1985 in 10 CFR Part 
    53 that reactors may safely be run without full core offload 
    capacity.''
        Notice is hereby given that by a Director's Decision (DD 96-22) 
    dated December 11, 1996, the Acting Director, Office of Nuclear Reactor 
    Regulation, has denied the Petitions. The staff concluded that the 
    issues raised by the Petitioner are without merit and that there is no 
    basis to take disciplinary action against GPU, as explained in the 
    ``Director's Decision Pursuant to 10 CFR 2.206'' (DD 96-22), the 
    complete text of which follows this notice and is available for 
    inspection at the Commission's Public Document Room at 2120 L Street, 
    NW, Washington DC, and at the local public document room located at 
    Ocean County Library, Reference Department, 101 Washington Street, 
    Tom's River, NJ.
    
        Dated at Rockville, Maryland, this 11th day of December 1996.
    
        For The Nuclear Regulatory Commission
    Frank J. Miraglia,
    Acting Director, Office of Nuclear Reactor Regulation.
    
    Director's Decision Under 10 CFR 2.206
    
    I. Introduction
    
        By letters dated May 11 and June 14, 1996, Mr. William deCamp, Jr., 
    requested on behalf of Oyster Creek Nuclear Watch (the Petitioner) that 
    the U.S. Nuclear Regulatory Commission (NRC or Commission) take action 
    to investigate statements made by GPU Nuclear Corporation (GPU) in the 
    April 1996 publication ``Neighborhood Update'' (the licensee's news 
    magazine) and during sworn testimony on March 7, 1996, before the Lacey 
    Township Zoning Board of Adjustment (the Zoning Board). The Petitioner 
    asserts that the statements are false. The Petitioner further requests 
    that NRC take appropriate disciplinary action against GPU management. 
    The Petitioner's requests are being treated as Petitions pursuant to 
    Section 2.206 of Title 10 of the Code of Federal Regulations (10 CFR 
    2.206).
        The specific statements of concerns are (1) the statement in the 
    ``Neighborhood Update'' that GPU and the Commission agree that a 
    license amendment request that involves the movement of spent fuel from 
    the Oyster
    
    [[Page 67353]]
    
    Creek Nuclear Generating Station spent fuel pool to the storage 
    facility while the plant is at power ``is not a safety issue but a 
    procedural one'' and (2) a sworn statement by Mr. Barton, who was the 
    Director of the Oyster Creek Nuclear Generating Station, before the 
    Zoning Board that it is unsafe to operate the Oyster Creek reactor 
    without full core offload capacity. The Petitioner, furthermore, 
    requests that if no special situation is found that prevents Oyster 
    Creek from operating without full offload capacity, the Commission take 
    appropriate disciplinary action against GPU management for making a 
    false statement under oath.1
    ---------------------------------------------------------------------------
    
        \1\ The petitioner is not asserting that the licensee has 
    provided false information to the Nuclear Regulatory Commission. A 
    licensee's obligation to ensure the completeness and accuracy of its 
    communications with the Commission is set forth in 10 CFR 50.9(a). 
    This regulation requires, in part, that ``[i]nformation provided to 
    the Commission by an applicant for a license or by a licensee or 
    information required by statute or by the Commission's regulations, 
    orders, or license conditions to be maintained by the applicant or 
    the licensee shall be complete and accurate in all material 
    respects.''
    ---------------------------------------------------------------------------
    
        For the reasons stated below, I am denying the relief requested by 
    the Petitioner.
    
    II. Discussion
    
    A. GPU Statement That the Movement of the Fuel Raises a Procedural 
    Issue, Not a Safety Issue
    
        As a basis for the request regarding the first concern that the 
    statement in the ``Neighborhood Update'' is untrue, Petitioner 
    referenced the following excerpts from NRC Bulletin 96-02 (NRCB 96-02), 
    ``Movement of Heavy Loads Over Spent Fuel, Over Fuel in the Reactor 
    Core, or Over Safety-Related Equipment,'' of April 11, 1996:
    
        The NRC staff audited both the initial and updated 10 CFR 50.59 
    evaluations performed by the licensee [GPU Nuclear] and determined 
    that the proposed cask movement activities represent an unreviewed 
    safety question that should be submitted to the NRC for review and 
    approval pursuant to the requirements of 10 CFR 50.59 and 50.90 * * 
    *. Accordingly, as defined in 10 C.F.R. 50.59(c), if an activity is 
    found to involve an unreviewed safety question, an application for a 
    license amendment must be filed with the Commission pursuant to 10 
    CFR 50.90.
    
        GPU met with the NRC staff on November 19, 1993, to discuss plans 
    for using the reactor building crane to move spent fuel out of the 
    spent fuel pool in a transfer cask for transportation to the dry cask 
    storage facility during power operations at Oyster Creek. During the 
    discussions, the NRC staff raised concerns regarding the use of the 
    crane and its ability to meet the heavy load criteria of NUREG-0612, 
    ``Control of Heavy Loads at Nuclear Power Plants.'' GPU indicated that 
    this special application of the crane would be evaluated pursuant to 10 
    CFR 50.59.2 NRC stated that it would conduct an audit of the 50.59 
    evaluation.
    ---------------------------------------------------------------------------
    
        \2\ 10 CFR 50.59 provides, in part, that a licensee may make 
    changes in the facility or procedures as defined in the safety 
    analysis report without prior Commission approval unless the 
    proposed change involves a change in the technical specifications or 
    an unreviewed safety question. The regulation, furthermore, requires 
    the licensee to prepare and maintain a written safety evaluation 
    addressing the issue of whether the proposal involves an unreviewed 
    safety question. A proposal is deemed to involve an unreviewed 
    safety question if (1) it involves an increase in the probability or 
    consequences of an accident previously evaluated; or (2) creates the 
    possibility of a new or different kind of accident from any accident 
    previously evaluated; or (3) involves a reduction in a margin of 
    safety as defined in the basis for any technical specification.
    ---------------------------------------------------------------------------
    
        In April 1995, GPU informed NRC that the 50.59 evaluation for use 
    of the crane to move the transfer cask was complete. On May 2 and 3, 
    June 12, and October 12 and 13, 1995, the NRC staff conducted onsite 
    audits and met with GPU at Oyster Creek regarding the use of the crane. 
    On November 2, 1995, in a telephone call between the NRC staff and Mr. 
    Keaten, Vice President and Director, Technical Functions, GPU, the NRC 
    staff advised GPU that the staff's concerns regarding the use of the 
    non-single-failure-proof crane to move the 100-ton transfer cask while 
    the plant was at power had not been resolved by its 50.59 evaluation. 
    Specifically, the staff was concerned that the activity involved the 
    movement of loads heavier than previously considered in the final 
    safety analysis report (FSAR) and, therefore, might reduce the margin 
    of safety, and that a load drop in the reactor building might result in 
    consequences greater than previously evaluated in the FSAR and, 
    therefore, may pose an unreviewed safety question.
        Consequently, Mr. Keaten advised the staff that GPU was considering 
    a plant modification, including reactor building crane upgrades, that 
    would address the staff's concerns.
        The NRC staff inspected the licensee's updated 10 CFR 50.59 
    evaluation which considered the reactor building crane upgrades. The 
    NRC staff's inspections included sending a team to Oyster Creek. The 
    staff concluded that its safety concerns had been addressed and 
    resolved. The NRC staff also determined that the licensee's planned 
    movement of spent fuel to the dry storage facility during plant 
    operation was safe and in accordance with all license requirements. 
    Notwithstanding the technical acceptability of the licensee's 
    methodology and analysis in the updated 10 CFR 50.59 evaluation, NRC 
    staff determined that since the possibility of an unreviewed safety 
    question (USQ) had been involved before the licensee made modifications 
    to upgrade the reactor building crane, GPU must submit a license 
    amendment application for the proposed cask movement activities. At the 
    public meeting on February 29, 1996, GPU was informed by the NRC staff 
    that an amendment was required. When the NRC receives an amendment 
    application, it is required to follow specific procedures set forth in 
    10 CFR 50.91.3
    ---------------------------------------------------------------------------
    
        \3\  10 CFR 50.91 requires the Commission to use specified 
    procedures when it receives an application requesting an amendment 
    to an operating license including procedures that concern consulting 
    the State in which the facility is located and procedures concerning 
    providing notification to the public of the licensee's amendment, 
    the Commission's findings or determinations regarding the amendment, 
    and opportunity for a hearing.
    ---------------------------------------------------------------------------
    
        Accordingly, the staff finds, after its review and evaluation of 
    the licensee's proposed action, that there are no safety issues 
    preventing the adoption of the proposal, but procedures require 
    amendment approval before the proposal can be implemented.
    
    B. GPU Statement Concerning Safe Operation and Full Core Discharge 
    Capability
    
        As basis for the Petitioner's request concerning GPU statements 
    about safety and full core discharge capability, the Petitioner sets 
    forth excerpts from Mr. Barton's testimony of March 7, 1994, before the 
    Zoning Board, and states that ``the NRC ruled in February 1985 in 10 
    CFR Part 53 that reactors may safely be run without full core offload 
    capacity.'' 4
    ---------------------------------------------------------------------------
    
        \4\ The Commission has stated that a full core reserve 
    capability is not an NRC safety requirement. 50 FR 5548, 5549 (1985)
    ---------------------------------------------------------------------------
    
        The Petitioner quoted in a letter and enclosed, underlined in red, 
    copied portions of Mr. Barton's testimony as follows:
    
        If we do not install the dry spent fuel storage modules by 1996, 
    the plant would not have the capacity of totally off-loading fuel 
    from the reactor to the in-plant spent fuel pools. (transcript pp. 
    94-95)
        In order to operate safely we should be able to remove this fuel 
    from the reactor and store it in the spent storage pool * * * 
    (transcript p. 95)
        Without dry storage and without the ability to remove this fuel 
    from the reactor, the plant would not be able to operate. 
    (transcript p. 95)
    
        Mr. Barton's full testimony in context with the Petitioner's 
    extracted quotes is as follows:
    
    
    [[Page 67354]]
    
    
        The fall of 1996 is a critical time for plant operations. If we 
    do not install the dry spent fuel storage modules by 1996, the plant 
    would not have the capability of totally off-loading fuel from the 
    reactor to the in-plant spent fuel pool. This is not a desirable 
    operating configuration, should the plant need to conduct internal 
    inspections of the reactor vessel that would require fuel to be 
    removed from the reactor. In order to operate safely we should be 
    able to remove this fuel from the reactor and store it in the spent 
    fuel storage pool inside the plant, and after 1996 we will not have 
    the flexibility to do that. Without dry storage and without the 
    ability to remove all the fuel from the reactor, the plant would not 
    be able to operate. (transcript p. 95)
    
        Taken in context, it appears that what Mr. Barton is stating is 
    that he is concerned with operations management due to the inability to 
    have full core off-load capability and that having full core off-load 
    capability can in certain situations enhance safety. The plant has the 
    capacity to complete one more refueling operation before they will not 
    be able to operate without dry storage capability as Mr. Barton stated. 
    The Commission has stated a similar view with regard to the issue of 
    maintaining full core reserve storage capability:
    
        While a full core reserve capability is not an NRC licensing or 
    safety requirement, maintenance of full core reserve would enhance 
    safety to some extent, and would also be needed to prevent extended 
    reactor outages in the event a core must be discharged in order to 
    inspect the reactor pressure vessel and perform other routine and 
    unscheduled maintenance operations.5
    ---------------------------------------------------------------------------
    
        \5\  The NRC's Statements of Consideration concerning the 
    amendment of 10 CFR Parts 1 and 53 entitled, ``Criteria and 
    Procedures for Determining the Adequacy of Available Spent Nuclear 
    Fuel Storage Capacity,'' 50 FR 5548, 5549 (1985)
    
        The December 6, 1993, Zoning Board hearing testimony of Mr. Gordon 
    Bond, Director of Nuclear Analysis and Fuel for GPU Nuclear, also 
    supports the view that the concern is with operations management. When 
    asked whether it is important to maintain full core discharge 
    ---------------------------------------------------------------------------
    capability, Mr. Bond responded as follows:
    
        We believe it is. It's not required by Federal Regulations, but 
    we believe it's prudent to allow sufficient reserve capacity in our 
    pool to be able to offload the core any time that we may have to. 
    For example, you may want to do some inspections inside the vessel, 
    and to do that you'll need to remove all of the fuel. (transcript p. 
    32)
    
    Accordingly, the staff finds that the statements and remarks of Mr. 
    Barton in their context are not false or misleading.
    
    V. Conclusion
    
        The NRC staff has reviewed the statements made by GPU in the April 
    1996 ``Neighborhood Update'' (the licensee's news magazine) and the 
    testimony of GPU managers before a local Zoning Board and concluded 
    that the assertions raised by the Petitioner are without merit and that 
    there is no basis to take any action against GPU. Accordingly, the 
    Petitioner's requests are denied.
        A copy of this Director's Decision will be filed with the Secretary 
    of the Commission for the Commission to review as stated in 10 CFR 
    2.206(c). This Decision will become the final action of the Commission 
    25 days after issuance unless the Commission, on its own motion, 
    institutes a review of the Decision within that time.
    
        Dated at Rockville, Maryland, this 11th day of December 1996.
    
        For the Nuclear Regulatory Commission
    Frank J. Miraglia,
    Acting Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 96-32349 Filed 12-19-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
12/20/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
96-32349
Pages:
67352-67354 (3 pages)
Docket Numbers:
Docket No. 50-219
PDF File:
96-32349.pdf