04-27638. Federal Acquisition Regulation; Applicability of the Cost Principles and Penalties for Unallowable Costs  

  • Start Preamble

    AGENCIES:

    Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).

    ACTION:

    Final rule.

    SUMMARY:

    The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (Councils) have agreed on a final rule amending the Federal Acquisition Regulation (FAR) by increasing the contract dollar threshold for assessing a penalty if the contractor includes expressly unallowable costs in its claim for reimbursement.

    DATES:

    Effective Date: January 19, 2005.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    The FAR Secretariat at (202) 501-4755 for information pertaining to status or publication schedules. For clarification of content, contact Mr. Richard C. Loeb at (202) 208-3810. Please cite FAC 2001-26, FAR case 2001-018.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    A. Background

    DoD, GSA, and NASA published a proposed rule in the Federal Register at 68 FR 66988 on November 28, 2003, with request for comments. The Councils proposed to amend the FAR to: (1) remove the requirement to apply the cost principles and procedures at FAR Part 31 when pricing a contract if cost or pricing data are not obtained; (2) add a definition to FAR Part 31 for fixed-price contracts, subcontracts, and modifications; and (3) increase the contract dollar threshold for assessing a penalty if the contractor includes expressly unallowable costs in its claim for reimbursement (FAR Part 42). Three respondents submitted comments on the proposed FAR rule; a discussion of the comments are provided below. The Councils considered all comments and decided not to adopt the proposed revisions to FAR Parts 15 and 31, and to convert the proposed rule at FAR Part 42 to a final rule. Differences between Start Printed Page 76357the proposed rule and final rule are discussed in comments 1, 2, and 3, below.

    This is not a significant regulatory action and, therefore, was not subject to review under Section 6(b) of Executive Order 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

    Public Comments:

    Applicability of FAR Part 31

    1. Comment: Two of the three respondents believe the change should not be made.

    The first respondent urged the withdrawal of the proposed rule and expressed the position that the need for the proposed change was not clearly and fully disclosed. The respondent strongly believes that the Government's prenegotiation objective for cost based fixed-price contracts should continue to be predicated on the consistent application of applicable FAR Part 31 cost principles. Whether a contractor's submitted cost data is “certified” or “uncertified” should not alter the basis for determining the Government's prenegotiation objective, or a determination on whether the negotiated fixed-price is fair and reasonable.

    The respondent noted that FAR Part 31 has more than just unallowable costs within it, e.g., allocability, consistency, direct vs. indirect, and accounting methods. The respondent also made the following points:

    • If FAR Subpart 31.2 policies and procedures are not consistently applied to cost-based fixed-price contracts, what are the alternate policies, procedures and principles to be applied when performing a “cost analysis” of the “uncertified” information other than cost or pricing data?
    • What fundamental constructs will the proposing contractor have to comply with?
    • What will guide the cost analyst and/or auditor when performing the “cost analysis” of the contractor's uncertified data?

    After referencing the Councils' stated goal “...to reduce Government unique regulations when the risk to the Government is low,” the respondent opined:

    When negotiating fixed-price contracts based on a prenegotiation objective that was predicated on a “cost analysis” of contractor submitted information other than cost or pricing cost data, the respondent believes that the risk to the Government is higher, not lower, than if “certified” cost or pricing data had been obtained. Without certified data, there is less assurance that contractor submitted data are current, complete and accurate.

    The respondent concluded that FAR Part 31 contract cost principles should continue to be applied to pricing contracts whenever cost data is submitted to support a contract price, regardless of whether the contract type is fixed-price.

    The second respondent believes that the Government's policy objective should be clarified, and that the mention of cost analysis is potentially confusing and unnecessary. The respondent characterized the phrasing of the proposed rule as terribly awkward (due to using the passive voice) and suggested alternative language.

    The third respondent was concerned that the proposed coverage at FAR 31.000 appears to restrict in some way the underlying Truth in Negotiations Act (TINA) mandate to obtain cost or pricing data in the first place (as to both negotiated contracts and negotiated modifications).

    Councils' response: Concur that the proposed change should not be made. The Councils believe that the Government needs a consistent playing field when dealing with cost data whether “certified” or not. The Councils are also concerned that the proposed language could be construed as limiting the Government's use of FAR Part 31 for its prenegotiation positions. This would adversely affect any requests for audit support made by the contracting officer. The General Accepted Government Auditing Standards (GAGAS) under attestation standards AT 101.23, “Suitability of Criteria,” require auditors to have objective, measurable, complete, and relevant criteria to apply during their work. The Councils believe that the guidance in FAR Part 31 meets these requirements, as General Accepted Accounting Principles (GAAP) alone does not go to the level necessary to support contract pricing. Therefore, the Councils have withdrawn the proposed revisions to FAR Parts 15 and 31.

    Definition of fixed-price contracts

    2. Comment: Two respondents believe the proposed FAR 31.001 definition of fixed-price contracts, subcontracts and modifications would lead to confusion in the area of Time-and-Material (T&M) type contracting actions.

    The first respondent stated that it strongly opposes the proposed “redefinition” of fixed-price contracts to include the fixed hourly portion of a T&M and labor-hour (LH) contract, and that it flies in the face of law and common sense. The respondent cited GSBCA decision CACI, Inc.—Federal v. General Services Administration, dated December 13, 2002, to support its position that T&M/LH contracts are not fixed-price. The respondent believes that the Council's attempt to rationalize a portion a T&M/LH contract as “fixed-price” is a shameful capitulation to contractors interests, and an abrogation of the Council's duty to taxpayers.

    The second respondent was concerned the proposed definition may impact T&M orders placed under GSA's Multiple Award Schedule (MAS) contracts. The proposed definition would include the fixed hourly rate portion of the T&M and LH contracts and subcontracts in FAR Subpart 16.6. The respondent believes this may suggest that time-and-material orders with a fixed labor hour component are fixed-price in nature for any contracting or FAR purpose. GSA mandates that all T&M orders placed under MAS contracts include the contract clause at FAR 52.232-7, Payments under Time-and-Materials and Labor-Hour Contracts. This clause provides contracting officers with an ability to require more substantiation of hours worked under a time-and-materials order. Because such task orders have fixed labor components, the respondent is concerned that contracting officers may—based on this proposed FAR change—consider such task orders to be fixed price and not invoke the controls attendant with this clause or other necessary safeguards to the use of such vehicles.

    Councils' response: Partially concur. The Councils believe there is a limited risk that contracting officers could be confused by the inclusion of the “fixed rate portion” of a T&M contracting action in the proposed definition. However, due to the Council's decision not to adopt the proposed revisions discussed at Comment 1, above, this definition is no longer required.

    Dollar threshold for assessing penalties—FAR 42.709

    3. Comment: One respondent stated that it had no objection to the proposed change in the threshold from the current $500,000 to $550,000 to adjust for inflation. The other two respondents did not address the proposed change.

    Councils' response: Concur. The Councils agree that the contract dollar threshold for assessing a penalty if the contractor includes expressly unallowable costs in its claim for reimbursement should be increased from $500,000 to $550,000, to adjust for inflation. This increase is authorized by 10 U.S.C. 2324(l) and 41 U.S.C. 256(1). Therefore, the dollar threshold amounts Start Printed Page 76358in FAR 42.709(b) and FAR 42.709-6 are increased from $500,000 to $550,000.

    B. Regulatory Flexibility Act

    The Department of Defense, the General Services Administration, and the National Aeronautics and Space Administration certify that this final rule will not have a significant economic impact on a substantial number of small entities within the meaning of the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because most contracts awarded to small entities use simplified acquisition procedures or are awarded on a competitive, fixed-price basis, and do not require application of the cost principles discussed in this rule.

    C. Paperwork Reduction Act

    The Paperwork Reduction Act does not apply because the changes to the FAR do not impose information collection requirements that require the approval of the Office of Management and Budget under 44 U.S.C. 3501, et seq.

    Start List of Subjects

    List of Subjects in 48 CFR Part 42

    • Government procurement
    End List of Subjects Start Signature

    Dated: December 9, 2004.

    Laura Auletta,

    Director, Contract Policy Division.

    End Signature Start Amendment Part

    Therefore, DoD, GSA, and NASA amend 48 CFR part 42 as set forth below:

    End Amendment Part Start Part

    PART 42—CONTRACT ADMINISTRATION AND AUDIT SERVICES

    End Part Start Amendment Part

    1. The authority citation for 48 CFR part 42 is revised to read as follows:

    End Amendment Part Start Authority

    Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 42 U.S.C. 2473(c).

    End Authority Start Amendment Part

    2. Amend sections 42.709(b) and 42.709-6 by removing “$500,000” and adding “$550,000” in its place.

    End Amendment Part End Supplemental Information

    [FR Doc. 04-27638 Filed 12-17-04; 8:45 am]

    BILLING CODE 6820-EP-S

Document Information

Published:
12/20/2004
Department:
National Aeronautics and Space Administration
Entry Type:
Rule
Action:
Final rule.
Document Number:
04-27638
Pages:
76356-76358 (3 pages)
Docket Numbers:
FAC 2001-26, FAR Case 2001-018, Item VI
RINs:
9000-AJ77
PDF File:
04-27638.pdf
CFR: (1)
48 CFR 42.709 and 42.709-6