2023-27982. Willimantic Power Corporation; Notice Soliciting Applications  

  • Start Preamble

    On August 31, 2020, Willimantic Power Corporation (licensee), a subsidiary of Enel Green Power North America filed a Notice of Intent (NOI) to file an application for a subsequent license for its Willimantic #2 Hydroelectric Project, No. 8047, pursuant to section 16.19(b)(3) of the Start Printed Page 88060 Commission's regulations.[1] On October 23, 2020, Commission staff noticed the NOI and approved the use of the traditional licensing process (TLP) to develop the license application. The existing license for Project No. 8047 expires on September 30, 2025.

    The 684-kilowatt (kW) Willimantic #2 Project is located on the Willimantic River, in Windham County, Connecticut.

    The principal project works consist of: (1) an upper dam with (i) a 12-foot-high and 175-foot-long granite block spillway with a crest elevation of 206.10 feet mean sea level (msl), (ii) a reservoir with a surface area of 2.5 acres, (iii) a 419-foot long power canal, (iv) trashracks with 2-inch clear bar spacing, (v) a 275-foot-long, 9-foot-diameter penstock, (vi) a powerhouse containing a Kaplan turbine-generator unit with an installed capacity of 684 kilowatts (kW), and (vii) a 50-foot-long tailrace with a tailwater elevation of 182.6 feet msl; (2) a lower dam with (i) a 15.2-foot-high and 125-foot-long granite block spillway with a crest elevation of 193.7 feet msl, and (ii) a reservoir with a surface area of 3.0 acres; (3) 1,000-foot-long, 4,160-Volt (V) generator lead, and a 1,500-kVA 600/2,400–V transformer bank; (4) a 520-foot-long, 23,500–V transmission line; and (5) appurtenant facilities. The project operates run-of-river and generates and estimated average of 1,201,000 kW hours a year.

    Pursuant to section 16.20(c) of the Commission's regulations, an existing licensee with a minor license not subject to sections 14 and 15 of the Federal Power Act must file an application for a subsequent license at least 24 months prior to the expiration of the current license.[2] As stated above, Willimantic Power Corporation's NOI indicated that it would be filing an application for a subsequent license; however, it did not file an application for a subsequent license or an application for an exemption from licensing for the Willimantic #2 Project by the October 2, 2023 deadline.[3]

    Therefore, pursuant to section 16.25(a) of the Commission's regulations, we are soliciting applications from potential applicants other than the existing licensee.[4] Interested parties have 90 days from the date of this notice to file a NOI to file an application for a subsequent license. An application for subsequent license or exemption for the Willimantic #2 Project (No. 8047) may be filed within 18 months of the date of filing the NOI. The existing licensee is prohibited from filing an application either individually or in combination with other entities.[5]

    Questions concerning this notice should be directed to Jeanne Edwards at (202) 502–6181 or jeanne.edwards@ferc.gov.

    Start Signature

    Dated: December 14, 2023.

    Debbie-Anne A. Reese,

    Deputy Secretary.

    End Signature End Preamble

    Footnotes

    1.  On March 22, 2021, Hydroland Omega, LLC, notified the Commission that the Willimantic Power Corporation is a wholly owned subsidiary of Hydroland Omega, LLC and replaced Enel Green Power North America, Inc. as the parent company.

    Back to Citation

    3.  The Commission's Rules of Practice and Procedure provide that if a filing deadline falls on a Saturday, Sunday, holiday, or other day when the Commission is closed for business, the filing deadline does not end until the close of business on the next business day. 18 CFR 385.2007(a)(2) (2022). Because the 24-month deadline fell on a Saturday ( i.e., September 30, 2023), the filing deadline was extended until the close of business on Monday, October 2, 2023.

    Back to Citation

    5.   Id. § 16.24(b)(2) (2022).

    Back to Citation

    [FR Doc. 2023–27982 Filed 12–19–23; 8:45 am]

    BILLING CODE 6717–01–P

Document Information

Published:
12/20/2023
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2023-27982
Pages:
88059-88060 (2 pages)
Docket Numbers:
Project No. 8047-015
PDF File:
2023-27982.pdf