98-34045. Clean Air Act: Contractor Access to Confidential Business Information
[Federal Register Volume 63, Number 246 (Wednesday, December 23, 1998)]
[Notices]
[Pages 71116-71117]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-34045]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[FRL-6209-2]
Clean Air Act: Contractor Access to Confidential Business
Information
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: The EPA has authorized the following contractor to access
information that has been, or will be, submitted to EPA under section
112(r) of the Clean Air Act(CAA) as amended: Computer Based Systems
Inc., (CBSI), 2750 Prosperity Ave., Fairfax, VA 22031 (Contract #68-W-
98-045) and its subcontractor, Creative Information Technology, Inc.,
(CITI), 9064 Manorwood Rd., Laurel, MD 20723.
Some of the information may be claimed to be confidential business
information (CBI) by the submitter.
DATES: Access to confidential data submitted to EPA will occur no
sooner than ten days after issuance of this notice.
FOR FURTHER INFORMATION CONTACT: Dorothy McManus, Office of Solid Waste
and Emergency Response, MC: 5104, U.S. Environmental Protection Agency,
Washington, DC 20460.
SUPPLEMENTARY INFORMATION: The EPA is issuing this notice to inform all
submitters of information under section 112(r) of the CAA that EPA may
provide the above mentioned contractor and its subcontractor access to
these materials on a need-to-know basis. This contractor will provide
technical support to the Office of Solid Waste and Emergency Response
in the receipt, processing and storage of risk management plans
submitted to EPA under the CAA.
In accordance with 40 CFR 2.301(h), EPA has determined that the
contractor and its subcontractor require access to CBI submitted to EPA
under sections 112(r) and 114 of the CAA in order to perform work
satisfactorily under the above noted contract. The contractor's and
subcontractor's personnel will be given access to information submitted
[[Page 71117]]
under section 112(r) of the CAA. Some of the information may be claimed
or determined to be CBI. The contractor's and subcontractor's personnel
will be required to sign nondisclosure agreements and will be permitted
access to CBI. All contractor access to CAA CBI will take place at the
contractor's facility. The contractor will have appropriate procedures
and facilities in place to safeguard the CAA CBI to which the
contractor and its subcontractor have access.
Clearance for access to CBI is scheduled to expire on January 31,
2003 or at contract termination.
Dated: December 16, 1998.
Jim Makris,
Director, Chemical Emergency Preparedness and Prevention Office, Office
of Solid Waste and Emergency Response.
[FR Doc. 98-34045 Filed 12-22-98; 8:45 am]
BILLING CODE 6560-50-P
Document Information
- Published:
- 12/23/1998
- Department:
- Environmental Protection Agency
- Entry Type:
- Notice
- Action:
- Notice.
- Document Number:
- 98-34045
- Dates:
- Access to confidential data submitted to EPA will occur no sooner than ten days after issuance of this notice.
- Pages:
- 71116-71117 (2 pages)
- Docket Numbers:
- FRL-6209-2
- PDF File:
-