95-31255. Northeast Utilities, Millstone Nuclear Power Station, Unit 1; Issuance of Director's Decision Under 10 CFR 2.206  

  • [Federal Register Volume 60, Number 247 (Tuesday, December 26, 1995)]
    [Notices]
    [Page 66807]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-31255]
    
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-245]
    
    
    Northeast Utilities, Millstone Nuclear Power Station, Unit 1; 
    Issuance of Director's Decision Under 10 CFR 2.206
    
        Notice is hereby given that the Director, Office of Nuclear Reactor 
    Regulation, has taken action with regard to a Petition dated January 8, 
    1995, by Mr. Anthony J. Ross. The Petition pertains to Millstone 
    Nuclear Power Station, Unit 1.
        In the Petition, the Petitioner raised concerns regarding the 
    Millstone station site paging and site siren evacuation alarm system at 
    Millstone Unit 1. The Petitioner requested that the U.S. Nuclear 
    Regulatory Commission (NRC) institute at least three sanctions against 
    his department manager and institute sanctions against the Petitioner's 
    coworker and maintenance first-line supervisor for engaging in 
    deliberate misconduct in violation of 10 CFR 50.5. As grounds for this 
    request, the Petitioner alleged that on numerous occasions since 
    January 1994, his department manager had instructed the Petitioner's 
    coworkers to shut off or turn down the volume on the site paging and 
    site siren evacuation alarm system in the Unit 1 maintenance shop, and 
    the Petitioner's first-line supervisor and coworker had complied with 
    this request, in violation of Technical Specification 6.8.1 and NUREG-
    0654.
        The Director of the Office of Nuclear Reactor Regulation has 
    determined to deny the Petition. The reasons for this denial are 
    explained in the ``Director's Decision Pursuant to 10 CFR 2.206'' (DD-
    95-23), the complete text of which follows this notice and is available 
    for public inspection at the Commission's Public Document Room, the 
    Gelman Building, 2120 L Street, NW., Washington, DC, and at the local 
    public document room located at the Learning Resources Center, Three 
    Rivers Community-Technical College, 574 New London Turnpike, Norwich, 
    CT 06360.
        A copy of the Decision will be filed with the Secretary of the 
    Commission for the Commission's review in accordance with 10 CFR 
    2.206(c) of the Commission's regulations. As provided by this 
    regulation, the Decision will constitute the final action of the 
    Commission 25 days after the date of issuance unless the Commission, on 
    its own motion, institutes a review of the Decision in that time.
    
        Dated at Rockville, Maryland, this 19th day of December 1995.
    
        For the Nuclear Regulatory Commission.
    William T. Russell,
    Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 95-31255 Filed 12-22-95; 8:45 am]
    BILLING CODE 7590-01-P
    
    

Document Information

Published:
12/26/1995
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
95-31255
Pages:
66807-66807 (1 pages)
Docket Numbers:
Docket No. 50-245
PDF File:
95-31255.pdf