96-32994. Fee Adjustments for Testing, Evaluation, and Approval of Mining Products  

  • [Federal Register Volume 61, Number 250 (Friday, December 27, 1996)]
    [Notices]
    [Pages 68300-68303]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-32994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF LABOR
    Mine Safety and Health Administration
    
    
    Fee Adjustments for Testing, Evaluation, and Approval of Mining 
    Products
    
    AGENCY: Mine Safety and Health Administration, Labor.
    
    ACTION: Notice of fee adjustments.
    
    -----------------------------------------------------------------------
    
    SUMMARY: This notice revises the Mine Safety and Health 
    Administration's (MSHA) user fees for testing, evaluation, and approval 
    of certain products manufactured for use in underground mines. These 
    fees are based on fiscal year 1996 data and reflect changes in approval 
    processing operations, as well as costs incurred to process approval 
    actions.
    
    DATES: These fee schedules are effective from January 1, 1997, through 
    December 31, 1997. Approval applications postmarked before January 1, 
    1997, will be charged under the fee schedules as published on January 
    22, 1996.
    
    FOR FURTHER INFORMATION CONTACT: John Faini, Acting Chief, Approval and 
    Certification Center, R.R. 1, Box 251, Triadelphia, West Virginia 
    26059.
    
    SUPPLEMENTARY INFORMATION: In general, MSHA has computed the revised 
    fees based on the cost to the government to provide testing, 
    evaluation, and approval of products manufactured for use in 
    underground mines. On May 8, 1987 (52 FR 17506), MSHA published a final 
    rule, 30 CFR part 5-Fees for Testing, Evaluation, and Approval of 
    Mining Products, which established the specific procedures for fee 
    calculation, administration, and revisions. This revised fee schedule 
    is established in accordance with the procedures of that rule.
        The final rule for 30 CFR part 7, Subpart E--Diesel Engines 
    Intended for Use in Underground Coal Mines and Subpart F--Diesel Power 
    Packages Intended for Use in Areas of Underground Coal Mines Where 
    Permissible Electric Equipment is Required, was issued on October 25, 
    1996. This final rule also revised 30 CFR part 36 to apply to diesel 
    equipment for coal mines, and removed 30 CFR parts 31 and 32. Fees for 
    applications under this rule are listed in this notice. Approvals will 
    no longer be issued under 30 CFR parts 31 and 32.
    
        Dated: December 20, 1996.
    J. Davitt McAteer,
    Assistant Secretary for Mine Safety and Health.
    
                     Fee Schedule Effective January 1, 1997                 
                             [Based on FY 1996 data]                        
    ------------------------------------------------------------------------
                                                    Hourly rate   Flat rate 
                     Action title                    (dollars)    (dollars) 
    ------------------------------------------------------------------------
    30 CFR PART 7--PRODUCT TESTING BY THIRD PARTY:                          
        12 Approval Evaluation-Battery Assemblies.          $51  ...........
        12 Approval Evaluation-Brattice and                                 
         Ventilation Tubing.......................           57  ...........
        12 Approval Evaluation-Multiple-Shot                                
         Blasting Units...........................           51  ...........
        12 Approval Evaluation-Electric Motor                               
         Assemblies...............................           51  ...........
        12 Approval Evaluation-Electric Cables and                          
         Splice Kits..............................           56  ...........
        12 Approval Evaluation-Diesel Engines 1...           57  ...........
        12 Approval Evaluation-Diesel Power                                 
         Packages 2...............................           57  ...........
        14 Approval Extension-Battery Assemblies..           51  ...........
        14 Approval Extension-Brattice and                                  
         Ventilation Tubing.......................           53  ...........
        14 Approval Extension-Multiple-Shot                                 
         Blasting Units...........................           51  ...........
        14 Approval Extension-Electric Motor                                
         Assemblies...............................           51  ...........
        14 Approval Extension-Electric Cables and                           
         Splice Kits..............................           54  ...........
        14 Approval Extension-Diesel Engines 1....           57  ...........
        14 Approval Extension-Diesel Power                                  
         Packages 2...............................           57  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 15--EXPLOSIVES:                                             
        12 Approval Evaluation \3\................           61  ...........
            Permissibility Tests for Explosives:                            
                                                                            
                Weigh-in..........................  ...........          462
                Physical Exam: First size.........  ...........          325
                Chemical Analysis.................  ...........        1,977
                Air Gap-Minimum Product Firing                              
                 Temperature......................  ...........          460
                Air Gap-Room Temperature..........  ...........          352
                Pendulum Friction Test............  ...........          163
                Detonation Rate...................  ...........          352
                Gallery Test 7....................  ...........        7,436
                Gallery Test 8....................  ...........        5,533
    
    [[Page 68301]]
    
                                                                            
                Toxic Gases (Large Chamber).......  ...........          805
            Permissibility Tests for Sheathed                               
             Explosives:                                                    
                Physical Examination..............  ...........          128
                Chemical Analysis.................  ...........        1,044
                Gallery Test 9....................  ...........        1,944
                Gallery Test 10...................  ...........        1,944
                Gallery Test 11...................  ...........        1,944
                Gallery Test 12...................  ...........        1,944
                Drop Test.........................  ...........          648
                Temperature Effects/Detonation....  ...........          672
                Toxic Gases.......................  ...........          580
        14 Approval Extension.....................           61  ...........
    30 CFR PART 18--ELECTRIC MOTOR DRIVEN                                   
     EQUIPMENT AND ACCESSORIES:                                             
        12 Approval--Machines (testing included)..           57  ...........
        12 Approval--Instruments (testing                                   
         included)................................           53  ...........
        14 Approval Extension--Machines (testing                            
         included)................................           57  ...........
        14 Approval Extension--Instruments                                  
         (testing included).......................           53  ...........
        15 Acceptance Evaluation 3................           54  ...........
            Acceptance Testing:                                             
                Explosion Test....................           47  ...........
                Wall Thickness Test...............           58  ...........
                Surface/Temperature Test..........           47  ...........
                Impact Test.......................           46  ...........
                Thermal Shock Test................           47  ...........
                Product Flame Test................           57  ...........
                Compressibility Test (asbestos                              
                 substitutes).....................           57  ...........
        16 Certification Evaluation (testing                                
         included)................................           49  ...........
        17 Acceptance Extension \3\...............           54  ...........
            Product Flame Test....................           57  ...........
        18 Certification Extension (testing                                 
         included)................................           49  ...........
        21 Field Modification (testing included)..           57  ...........
        23 Field Approval.........................  ...........           97
        26 Permit--Machines (testing included)....           58  ...........
        26 Permit--Instruments (testing included).           58  ...........
        30 Intrinsic Safety Determination (testing                          
         included)................................           58  ...........
        31 Intrinsic Safety Determination Ext                               
         (testing included).......................           56  ...........
        32 Simplified Certification (testing                                
         included)................................           49  ...........
        34 Simplified Certification Extension                               
         (testing included).......................           36  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
        41 Longwall Approval (testing included)...           57  ...........
        42 Longwall Approval Extension (testing                             
         included)................................           57  ...........
        45 Shearer Evaluation (testing included)..           58  ...........
        46 Shearer Evaluation Extension (testing                            
         included)................................           58  ...........
        47 Permit--Extension of Time..............  ...........          292
        48 Permit Modification--Machines..........           56  ...........
        48 Permit Modification--Instruments                                 
         (testing included).......................           54  ...........
    30 CFR PART 19--ELECTRIC CAP LAMPS:                                     
        12 Approval (testing included)............           53  ...........
        14 Approval Extension (testing included)..           52  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 20--ELECTRIC MINE LAMPS:                                    
        12 Approval (testing included)............           54  ...........
        14 Approval Extension (testing included)..           52  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 21--FLAME SAFETY LAMPS:                                     
        12 Approval (testing included)............           54  ...........
        14 Approval Extension (testing included)..           54  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 22--PORTABLE METHANE DETECTORS:                             
        12 Approval (testing included)............           54  ...........
        14 Approval Extension (testing included)..           54  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 23--TELEPHONES AND SIGNALING                                
     DEVICES:                                                               
        12 Approval (testing included)............           56  ...........
        14 Approval Extension (testing included)..           54  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 24--SINGLE-SHOT BLASTING UNITS:                             
        12 Approval (testing included)............           58  ...........
        14 Approval Extension (testing included)..           58  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    
    [[Page 68302]]
    
                                                                            
    30 CFR PART 26--LIGHTING EQUIPMENT FOR                                  
     ILLUMINATION:                                                          
        12 Approval (testing included)............           58  ...........
        14 Approval Extension (testing included)..           58  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 27--METHANE MONITORING SYSTEMS:                             
        16 Certification (testing included).......           53  ...........
        18 Certification Extension (testing                                 
         included)................................           54  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 28--D.C. CURRENT FUSES:                                     
        12 Approval (testing included)............           59  ...........
        14 Approval Extension (testing included)..           59  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 29--PORTABLE DUST ANALYZERS AND                             
     METHANE MONITORS:                                                      
        12 Approval (testing included)............           54  ...........
        14 Approval Extension (testing included)..           54  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 33--DUST COLLECTORS:                                        
        12 Approval without Cert. of Performance                            
         (testing included).......................           58  ...........
        14 Approval Extension (testing included)..           58  ...........
        16 Certification Evaluation (testing                                
         included)................................           58  ...........
        18 Certification Extension (testing                                 
         included)................................           58  ...........
        21 Field Modification.....................           58  ...........
        29 Dust Collector Approval with Cert. of                            
         Performance..............................  ...........          181
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 35--FIRE-RESISTANT HYDRAULIC                                
     FLUIDS:                                                                
        12 Approval (testing included)............           54  ...........
        14 Approval Extension (testing included)..           53  ...........
    30 CFR PART 36--MOBILE DIESEL-POWERED                                   
     EQUIPMENT:                                                             
        12 Approval...............................           60  ...........
        14 Approval Extension.....................           57  ...........
        16 Certification-Engines (testing                                   
         included)................................           54  ...........
        18 Certification Extension-Engines                                  
         (testing included).......................           54  ...........
        21 Field Modification.....................           58  ...........
        27 Certification-Diesel Components                                  
         (testing included).......................           57  ...........
        28 Certification Ext-Diesel Components                              
         (testing included).......................           57  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
    30 CFR PART 74--COAL MINE DUST PERSONAL                                 
     SAMPLER UNITS:                                                         
        12 Approval...............................           54  ...........
    00 OTHER A&CC SERVICES:                                                 
        15 Acceptance--Overcurrent Relays (testing                          
         included)................................           54  ...........
        15 Statement of Test and Evaluation (ST&E)  ...........           61
        15 Material Acceptance (testing included).           54  ...........
        15 Monitor and Power System (MAPS)                                  
         (testing included).......................           55  ...........
        15 Acceptance-Ground Check Monitor/Ground                           
         Wire Devices (testing included)..........           54  ...........
        17 Acceptance Ext-Overcurrent Relays                                
         (testing included).......................           54  ...........
        17 Acceptance Ext-Interim Criteria                                  
         (testing included).......................           52  ...........
        17 Statement of Test and Evaluation (ST&E)                          
         Extension................................           32  ...........
        17 Material Acceptance Extension (testing                           
         included)................................           54  ...........
        17 Acceptance Extension-Ground Check                                
         Monitor/Ground Wire Devices (testing                               
         included)................................           54  ...........
        20 Stamped Revision Acceptance (SRA) 4....  ...........          305
        24 Acceptance--Panic Bar..................           54  ...........
        33 Generic Statement of Test and                                    
         Evaluation (ST&E)........................           54  ...........
        35 Administration Records Update..........           15  ...........
        37 Acceptance--Interim Criteria \3\.......           56  ...........
            Interim Criteria Testing: Product                               
             Flame Test...........................           58  ...........
        40 Stamped Notification Acceptance Program                          
         (SNAP)...................................  ...........          363
        40 Stamped Notification Acceptance Program                          
         (SNAP) ST&E..............................           32  ...........
        41 Approval--Longwall Area Lighting.......           56  ...........
        42 Approval Extension--Longwall Area                                
         Lighting.................................           54  ...........
        50 Mine Wide Monitoring System (MWMS)                               
         Evaluation...............................           56  ...........
        52 Mine Wide Monitoring System (MWMS)                               
         Barrier Classification...................  ...........           80
        54 Mine Wide Monitoring System (MWMS)                               
         Sensor Classification....................           57  ...........
        00 Retesting for Approval as a Result of                            
         Post-Approval Product Audit \5\..........  ...........  ...........
    ------------------------------------------------------------------------
    \1\ Applications for Diesel Engines (Subpart E) postmarked after        
      November 25, 1996, must be submitted under 30 CFR Part 7 Third Party  
      Testing.                                                              
    \2\ Diesel Power Packages (Subpart F) final rule was issued October 25, 
      1996. The phase-in period for this program is 3 years.                
    \3\ Full approval fee consists of evaluation cost plus applicable test  
      costs.                                                                
    \4\ Fee covers SRA application accompanied by up to five documents.     
    \5\ Fee based upon the approval schedule in effect at the time of       
      retest.                                                               
    
    
    
    [[Page 68303]]
    
        Note: When testing and evaluation are required at locations 
    other than MSHA's premises, the applicant shall reimburse MSHA for 
    traveling, subsistence, and incidental expenses of MSHA's 
    representation in accordance with standardized government travel 
    regulations. This reimbursement is in addition to the fees charged 
    for evaluation and testing.
    
    [FR Doc. 96-32994 Filed 12-26-96; 8:45 am]
    BILLING CODE 4510-43-P
    
    
    

Document Information

Effective Date:
1/1/1997
Published:
12/27/1996
Department:
Mine Safety and Health Administration
Entry Type:
Notice
Action:
Notice of fee adjustments.
Document Number:
96-32994
Dates:
These fee schedules are effective from January 1, 1997, through December 31, 1997. Approval applications postmarked before January 1, 1997, will be charged under the fee schedules as published on January 22, 1996.
Pages:
68300-68303 (4 pages)
PDF File: