E6-22211. Notice of Application Accepted for Filing and Soliciting Motions To Intervene, Protests, and Comments  

  • Start Preamble December 19, 2006.

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection:

    a. Type of Application: Preliminary Permit.

    b. Project No.: 12748-000.

    c. Date filed: November 1, 2006.

    d. Applicant: The City of Corpus Christi (City).

    e. Name of Project: City of Corpus Christi Hydroelectric Project.

    f. Location: The project would be located at the City's existing Wesley E. Seale Dam, on the Nueces River in Nueces County, Texas. Start Printed Page 78183

    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).

    h. Applicant Contacts: Mr. George “Skip” Noe, City Manager, City of Corpus Christi, 1201 Leopard Street, Corpus Christi, TX 78401, (361) 826-3220. Ms. Mary Kay Fischer, City Attorney, City of Corpus Christi, 1201 Leopard Street, Corpus Christi, TX 78401, (361) 826-3360. Ms. Nancy J. Skancke, Law Offices of GKRSE, 1500 K Street, N.W., Suite 330, Washington, DC 20005, (202) 408-5400.

    i. FERC Contact: Etta Foster, (202) 502-8769.

    j. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice.

    The Commission's Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    k. Description of Project: The proposed project would consist of: (1) the existing 5,970-foot-long, gated, concrete-gravity Wesley E. Seale Dam; (2) an existing impoundment, Lake Corpus Christi, with a surface area of 18,256 acres and a storage capacity of 257,260 acre-feet at normal maximum water surface elevation of 94.0 feet above mean sea level; (3) two 2.5 MW turbine generating units with a total installed capacity of 5 megawatts; (4) an existing 69 kV transmission line, and (5) appurtenant facilities. The project would have an average annual generation of 5.2 gigawatt-hours.

    l. Locations of Applications: A copy of the application is available for inspection and reproduction at the Commission in the Public Reference Room, located at 888 First Street NE., Room 2A, Washington, DC 20426, or by calling (202) 502-8371. This filing may also be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1-866-208-3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is also available for inspection and reproduction at the address in item h above.

    m. Individuals desiring to be included on the Commission's mailing list should so indicate by writing to the Secretary of the Commission.

    n. Competing Preliminary Permit: Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36.

    o. Competing Development Application: Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36.

    p. Notice of Intent: A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice.

    q. Proposed Scope of Studies under Permit: A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project.

    r. Comments, Protests, or Motions to Intervene: Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, 385.214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application.

    Comments, protests and interventions may be filed electronically via the Internet in lieu of paper; See 18 CFR 385.2001 (a)(1)(iii) and the instructions on the Commission's Web site under “e-filing” link. The Commission strongly encourages electronic filing.

    s. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title “COMMENTS”, “RECOMMENDATIONS FOR TERMS AND CONDITIONS”, “PROTEST”,”COMPETING APPLICATION” or “MOTION TO INTERVENE”, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission's regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. A copy of any motion to intervene must also be served upon each representative of the Applicant specified in the particular application.

    t. Agency Comments: Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency's comments must also be sent to the Applicant's representatives.

    Start Signature

    Magalie R. Salas,

    Secretary.

    End Signature End Preamble

    [FR Doc. E6-22211 Filed 12-27-06; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Comments Received:
0 Comments
Published:
12/28/2006
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
E6-22211
Pages:
78182-78183 (2 pages)
EOCitation:
of 2006-12-19
PDF File:
e6-22211.pdf