    Updated Standard Review Plan Chapter 7: Availability
    
    AGENCY: Nuclear Regulatory Commission.
    
    ACTION: Notice of availability and request for comments.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Nuclear Regulatory Commission (NRC) has prepared an update 
    to Chapter 7 of NUREG-0800, ``Standard Review Plan for the Review of 
    Safety Analysis Reports for Nuclear Power Plants,'' (SRP) for review 
    and comments. The updated SRP Chapter 7 incorporates changes in the NRC 
    review criteria in the area of instrumentation and control (I&C) 
    systems, particularly digital computer-based I&C systems of nuclear 
    power plants that have occurred since the last major revision of the 
    SRP in 1981.
        The revisions were derived from the following programmatic areas: 
    NRC regulatory documents issued after the 1981 SRP revision; NRC staff 
    positions related to digital I&C retrofits at operating nuclear power 
    plants as documented in relevant safety evaluation reports; industry 
    consensus standards applicable to I&C systems; NRC staff positions 
    related to evolutionary and advanced light water reactor design reviews 
    as presented in SECY-91-292, ``Digital Computer Systems for Advanced 
    Light Water Reactors,'' and the Staff Requirements Memorandum on SECY-
    93-087, ``Policy, Technical, and Licensing Issues Pertaining to 
    Evolutionary and Advanced Light Water Reactor (ALWR) Designs;'' NRC 
    design certification safety evaluation reports for the General Electric 
    Advanced Boiling Water Reactor Design and the ABB-CE System 80+ Design; 
    and nuclear power plant operating experience.
    
    DATES: The comment period expires January 31, 1997. Comments received 
    after this date will be considered if practical to do so, but the 
    Commission is able to assure consideration only of comments received on 
    or before this date.
    ADDRESSES: Mail comments to: Chief, Rules Review and Directives Branch, 
    Division of Freedom of Information and Publication Services, Mail Stop 
    T-6D59, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. 
    Comments may be hand delivered to 11545 Rockville Pike, Rockville, MD 
    between 7:45 a.m. and 4:15 p.m. on Federal work-days. Comments may be 
    submitted electronically as specified in the supplementary information 
    section of this notice.
    
    FOR FURTHER INFORMATION CONTACT: Matthew Chiramal, Instrumentation and 
    Controls Branch, Office of Nuclear Reactor Regulation, Mail Stop O-8H3, 
    U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, 
    Telephone No. (301) 415-2845.
    SUPPLEMENTARY INFORMATION: The proposed revised text to Chapter 7 of 
    NUREG-0800, ``Standard Review Plan for the Review of Safety Analysis 
    Reports for Nuclear Power Plants--LWR Edition,'' (SRP), is being 
    published as a draft report for comments. Further NRC staff review and 
    evaluation, including resolution of public comments, will be needed 
    before a final revision of Chapter 7 of the SRP can be published.
        The draft Chapter 7 of the SRP that is available for public review 
    consists of revised SRP sections and appendices with side-bars that 
    show the major technical changes resulting from the updating of the 
    existing SRP Chapter 7 sections and new sections, appendices and branch 
    technical positions. Three new sections are added: Section 7.0, 
    Introduction, Section 7.8, Diverse Instrumentation and Control Systems, 
    and Section 7.9, Data Communication Systems. Section 7.1 which contains 
    the general I&C system requirements and guidance has been revised to 
    incorporate (1) references to new regulatory guides (RGs) and branch 
    technical positions (BTPs) on digital computer-based I&C system issues, 
    (2) review areas, acceptance criteria, and review process for digital 
    computer-based I&C systems, and (3) discussion of standard plant 
    reviews. Sections 7.2 through 7.9 that focus on specific nuclear power 
    plant I&C systems have been revised to add reference to the digital I&C 
    system guidance contained in the revised Section 7.1. Two new 
    appendices have been added and three have been revised. Appendix 7.0-A 
    is a new appendix that describes the overall NRC review process for 
    digital computer-based I&C systems and new Appendix 7.1-C provides 
    guidance with
    
    [[Page 64177]]
    
    respect to the NRC review according to IEEE Standard 603. Revised 
    Appendix 7.1-A addresses rule changes (10 CFR Part 52 and revisions to 
    10 CFR Part 50) and identifies new regulatory guides on the digital 
    system design process. Revised Appendix 7.1-B incorporates digital I&C 
    system topics into the review for compliance with the requirements of 
    IEEE Standard 279 as stated in 10 CFR 50.55a(h). Revised Appendix 7-A 
    includes the new BTPs.
        The updated SRP Chapter 7 does not, by itself, establish any new or 
    revised requirements. It incorporates lessons learned from the 
    completed reviews of I&C systems in the advanced light water reactors 
    and digital I&C system retrofits of operating reactors. The review 
    guidance described in the updated SRP Chapter 7 will be used by the NRC 
    staff in the evaluation of submittals in connection with applications 
    for construction permits, standard design certifications and design 
    approvals, combined operating licenses, and operating plant license 
    amendments.
        Work related to updating SRP Chapter 7 was performed in accordance 
    with the guidance in NUREG-1447, ``Standard Review Plan Update and 
    Development Program--Implementing Procedures Document,'' dated May 
    1992.
        The purpose of this notice is to solicit public comment on whether 
    the revised text accurately and fully reflects established NRC staff 
    review criteria, positions and existing regulations. The updated draft 
    SRP Chapter 7 and the supporting referenced documents provide 
    traceability back to the changes made to the SRP Chapter 7 currently in 
    effect. The draft SRP Chapter 7 is made available to the public as part 
    of the NRC's policy to inform the nuclear industry and the general 
    public of regulatory procedures and policies. Comments will be 
    considered and revisions made to the draft SRP Chapter 7 as appropriate 
    based on the comments received. The final SRP Chapter 7 update will be 
    issued in approximately mid-1997. SRP Chapter 7 will be revised 
    periodically, as appropriate, to accommodate future new technologies, 
    information, and experience. The NRC encourages comment from interested 
    parties; however, public review is not intended to reopen a dialogue on 
    the merits of the requirements themselves, but should be focused on the 
    purpose stated above. The NRC also requests specific comments on 
    whether an appropriate level of detailed guidance has been provided for 
    the NRC staff reviewers in the proposed Chapter 7 update particularly 
    with regard to digital I&C review criteria.
    
    Electronic Submission of Comments
    
        The draft SRP Chapter 7 can be accessed from the NRC Homepage on 
    the World Wide Web--URL: http://www.nrc.gov under the ``News and 
    Information'' or the ``Nuclear Reactors'' menu options by selecting 
    ``Standard Review Plan Chapter 7, Instrumentation and Controls--Draft 
    report for comments.'' Specific guidance is provided on-line to guide 
    the user on the various options available for reading, commenting on, 
    and downloading the document.
        Chapter 7 of the SRP is available in printed form on paper for 
    inspection and copying for a fee at the NRC Public Document Room, 2120 
    L Street NW (Lower Level), Washington, DC 20555.
        A limited number of copies of the draft SRP Chapter 7 in the 
    printed form on paper are available free, to the extent of supply, upon 
    written request to the Office of Administration, Distribution Section, 
    U.S. Nuclear Regulatory Commission, Washington, DC 20555.
    
        Dated at Rockville, Maryland, this 25th day of November, 1996.
    
        For the Nuclear Regulatory Commission.
    Jared Wermiel,
    Chief, Instrumentation and Controls Branch, Division of Reactor 
    Controls and Human Factors, Office of Nuclear Reactor Regulation.
    [FR Doc. 96-30713 Filed 12-2-96; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
12/03/1996
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Action:
Notice of availability and request for comments.
Document Number:
96-30713
Dates:
The comment period expires January 31, 1997. Comments received after this date will be considered if practical to do so, but the Commission is able to assure consideration only of comments received on or before this date.
Pages:
64176-64177 (2 pages)
PDF File:
96-30713.pdf