2013-31150. Federal Acquisition Regulation; Terms of Service and Open-Ended Indemnification and Unenforceability of Unauthorized Obligations  

  • Start Preamble

    AGENCIES:

    Department of Defense (DoD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).

    ACTION:

    Final rule.

    SUMMARY:

    DoD, GSA, and NASA have adopted as final, without change, an interim rule amending the Federal Acquisition Regulation (FAR) to address concerns raised in an opinion from the U.S. Department of Justice (DOJ) Office of Legal Counsel (OLC) involving the use of unrestricted, open-ended indemnification clauses in acquisitions for social media applications.

    DATES:

    Effective: December 31, 2013.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Ms. Marissa Petrusek, Procurement Analyst, at 202-501-0136, for clarification of content. For information pertaining to status or publication schedules, contact the Regulatory Secretariat at 202-501-4755. Please cite FAC 2005-72, FAR Case 2013-005.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background

    DoD, GSA, and NASA published an interim rule in the Federal Register at 78 FR 37686 on June 21, 2013, to implement a recent DOJ OLC opinion, entitled “Memorandum for Barbara S. Fredericks, Assistant General Counsel for Administration, United States Department of Commerce,” which noted that the Anti-Deficiency Act (ADA) (31 U.S.C. 1341) is violated when a Government contracting officer or other employee with authority to bind the Government agrees, without statutory authorization or other exception, to an open-ended, unrestricted indemnification clause. On April 4, 2013, the Office of Management and Budget (OMB) issued guidance outlining a series of management actions to ensure agencies act in compliance with the ADA and in accordance with OLC's opinion. See Start Printed Page 80383OMB Guidance M-13-10, Anti-deficiency Act Implications of Certain Online Terms of Service Agreements. The interim rule became effective on June 21, 2013. One respondent submitted comments on the interim rule.

    II. Discussion and Analysis

    The Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (the Councils) reviewed the comments in the development of the final rule. A discussion of the comments is provided as follows:

    A. Summary of Significant Changes

    No changes were made as a result of the public comments.

    B. Analysis of Public Comments

    1. Attachment of Clause to Licenses

    Comment: The respondent believed that the clause does not reliably attach to licenses because of situations where an End User License Agreement (EULA) or Terms of Service (TOS) is passed through an intermediary contractor or subcontractor to the Government. The respondent recommended that the Government directly negotiate with major commercial software and service providers to ensure that the clause “is included in those providers' EULAs or TOSs with the Government and that the interim rule make clear that commercial items and software can be accepted only where such an agreement has been made directly with the licensor”.

    Response: The clause does attach to licenses. The clause is not limited to instances in which the Government has directly negotiated with the indemnitees. No change is made in the final rule.

    2. Unintended Consequences

    Comment: The respondent expressed concern that this rule could lead commercial companies to forego doing business with the Government. Not all contractors may be able to accept the risk re-allocation effected by the interim rule, according to the respondent.

    Response: The interim rule became effective on June 21, 2013. The objective of the rule is to clarify that the inclusion of an open-ended indemnification clause in a EULA, TOS, or other agreement, is not binding on the Government unless expressly authorized by statute and specifically authorized under applicable agency regulations and procedures, and shall be deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement. Since the interim rule was published, the Councils have received no indications that the scenario envisioned by the respondent has come to pass. No change is made in the final rule.

    3. Alternative Solutions To Address the ADA Concerns

    Comment: The respondent suggested two alternatives. The first was for the Department of Justice to definitively indicate that agency disclosures are not required for (and contracting officers will not be prosecuted for) ADA violations stemming solely from open-ended indemnifications contained in commercial EULAs and TOSs so long as, once discovered, the Government negotiates with the licensor directly to limit the attendant open-ended risk. The other alternative was for the Government to retain the clause from the interim rule with a cap on licensors' liability at the amount of appropriated funds directed to the particular purchase.

    Response: This type of additional guidance would not be included in the FAR. Development of this additional guidance is outside the purview of the Councils. No change is made in the final rule.

    III. Executive Order 12866 and 13563

    Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is a significant regulatory action and, therefore, was subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.

    IV. Regulatory Flexibility Act

    DoD, GSA, and NASA have prepared a Final Regulatory Flexibility Analysis (FRFA) consistent with the Regulatory Flexibility Act, 5 U.S.C. 601, et seq. The FRFA is summarized as follows:

    This final rule is required to implement an opinion by the U.S. Department of Justice Office of Legal Counsel. The objective of the final rule is to clarify that the inclusion of an open-ended indemnification clause in a EULA, TOS, or other agreement, is not binding on the Government unless expressly authorized by statute and specifically authorized under applicable agency regulations and procedures, and shall be deemed to be stricken from the EULA, TOS, or similar legal instrument or agreement.

    The Chief Counsel for Advocacy of the Small Business Administration did not submit any comments in response to the rule.

    This rule will impact all small entities with a supply or service contract subject to a supplier license agreement. There may be a small beneficial impact on small entities because these revisions to the FAR will help save time and streamline processes since small entities will no longer have to individually renegotiate, on a prospective basis, a EULA, TOS, or similar agreement containing an indemnification provision. Further, clauses like open-ended, unrestricted indemnification clauses have generally been unenforceable against the Government, unless expressly authorized by statute, and the FAR is being revised to reflect this.

    DoD, GSA and NASA estimate that this rule will impact approximately 3,538 small entities. Many supplies or services are acquired subject to supplier license agreements. These are particularly common in information technology acquisitions, but they may apply to any supply or service. DoD, GSA and NASA considered that the majority of the information technology purchases associated with this rule will be purchased through the GSA Information Technology Schedule 70 contracts. As such, DoD, GSA, and NASA used, as a basis for the estimate, the number of GSA Information-Technology Schedule 70 vendors, plus an estimate for contractors other than information technology acquisitions.

    There are currently 4,988 GSA Information-Technology Schedule 70 vendors. DoD, GSA and NASA estimate that this rule will impact 75 percent, or 3,741, of those vendors because they have EULAs or TOS in their Government contracts. Of those affected entities, it is estimated that around 86 percent, or 3,217, will be small entities. DoD, GSA, and NASA estimate that there are approximately 10 percent, or 321, more small entities across the Government with information technology acquisitions and other than information-technology acquisition with Government contracts that include EULAs or TOS and therefore impacted. As a result, it is estimated that this rule will impact approximately 3,538 small entities.

    DoD, GSA, and NASA do not anticipate an impact on small entities in acquisitions conducted through Government purchase cards. This is because the rule does not require entities to negotiate or change their agreement language.

    There is no record keeping or reporting requirement for this rule.

    Steps have been taken in this interim rule to minimize the impact on small entities which help to save them time and streamline their processes; for example, this would greatly reduce the requirement to negotiate all EULAs, TOS, or similar arrangements on a case-by-case basis.

    Interested parties may obtain a copy of the FRFA from the Regulatory Secretariat. The Regulatory Secretariat Start Printed Page 80384has submitted a copy of the FRFA to the Chief Counsel for Advocacy of the Small Business Administration.

    V. Paperwork Reduction Act

    The final rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).

    Start List of Subjects

    List of Subjects in 48 CFR Parts 12, 13, 32, 43, and 52

    • Government procurement
    End List of Subjects Start Signature

    Dated: December 19, 2013.

    William Clark,

    Acting Director, Office of Government-wide Acquisition Policy, Office of Acquisition Policy, Office of Government-wide Policy.

    End Signature

    Interim Rule Adopted as Final Without Change

    Accordingly, the interim rule amending 48 CFR parts 12, 13, 32, 43, and 52, which was published in the Federal Register at 78 FR 37686 on June 21, 2013, is adopted as a final rule without change.

    End Supplemental Information

    [FR Doc. 2013-31150 Filed 12-30-13; 8:45 am]

    BILLING CODE 6820-EP-P

Document Information

Effective Date:
12/31/2013
Published:
12/31/2013
Department:
National Aeronautics and Space Administration
Entry Type:
Rule
Action:
Final rule.
Document Number:
2013-31150
Dates:
Effective: December 31, 2013.
Pages:
80382-80384 (3 pages)
Docket Numbers:
FAC 2005-72, FAR Case 2013-005, Item III, Docket 2013-0005, Sequence 1
RINs:
9000-AM45: Federal Acquisition Regulation (FAR); FAR Case 2013-005, Terms of Service and Open-Ended Indemnification, and Unenforceability of Unauthorized Obligations
RIN Links:
https://www.federalregister.gov/regulations/9000-AM45/federal-acquisition-regulation-far-far-case-2013-005-terms-of-service-and-open-ended-indemnification
Topics:
Government procurement
PDF File:
2013-31150.pdf
CFR: (5)
48 CFR 12
48 CFR 13
48 CFR 32
48 CFR 43
48 CFR 52