E5-6902. Proposed Draft Cost and Performance Goals for the Department of Energy's Coal and Related Technologies Program  

  • Start Preamble Start Printed Page 72634

    AGENCY:

    Office of Fossil Energy, Department of Energy (DOE).

    ACTION:

    Notice of proposed draft cost and performance for the Department of Energy's coal and related technologies program, and request for comments.

    SUMMARY:

    Section 962 of the Energy Policy Act of 2005 (EPAct), (42 U.S.C. 16292), directed the Secretary of Energy to conduct coal research and development programs and, in carrying out such programs, to identify proposed draft cost and performance goals for coal-based technologies that would permit the continued cost-competitive use of coal for the production of electricity, chemical feedstocks, and transportation fuels. In compliance with section 962(b) of EPAct, this notice requests public comment on the proposed goals.

    DATES:

    Comments on the draft cost and performance goals are due December 27, 2005.

    ADDRESSES:

    Comments should be sent to: U.S. Department of Energy, Office of the Assistant Secretary of Fossil Energy, ATTN: Darren Mollot, 1000 Independence Avenue, SW., Washington, DC 20585.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Dr. Darren Mollot, Office of Clean Coal, Office of Fossil Energy, (202) 586-0429, darren.mollot@hq.doe.gov or Mr. John Grasser, Director of Communications, Office of Fossil Energy, (202) 586-6803, john.grasser@hq.doe.gov, 1000 Independence Avenue, SW., Washington, DC 20585.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    Section 962 of EPAct directed DOE to conduct a program of technology research, development, demonstration, and commercial application for coal and power systems (42 U.S.C. 16292(a)). In carrying out these programs, DOE was also directed to identify proposed draft cost and performance goals for coal-based technologies that would permit the continued cost-competitive use of coal for the production of electricity, chemical feedstocks, and transportation fuels (42 U.S.C. 16292(b)). Proposed draft cost and performance goals for program activities currently funded and undertaken by DOE to facilitate production and generation of coal-based power are summarized in the table below.

    These aggressive goals are for technology that does not yet exist. The goals provide a basis for guiding technology development, and program funding. They are not being proposed as the basis for present or future regulations or legally binding standards, nor do they attempt to project dates by which technologies will be developed or commercially available. The dates for achieving the targeted goals relate to the projected need for maintaining existing coal-based electric plant capability and for significantly increasing coal-based electric power capacity beginning in the 2010 to 2020 time frame (Energy Information Administration, Annual Energy Outlook, February 2005). Achieving the performance goals within these dates will depend on continued availability of funding. The overall program objective is to develop coal-based technologies that will enable the continued use of coal as a valued energy resource for the Nation.

    These proposed goals were established based on a variety of information and data, including the status of current coal-based technology and results from on-going research and development programs carried out by industry, university, and national laboratories. They were developed through feedback from workshops held by DOE that resulted in developing a coal program roadmap to meet national needs and from workshops on advanced technology to improve environmental performance, energy system efficiency, and lower cost of coal-based energy systems. In establishing these goals, DOE consulted with coal-based technology equipment vendors, users (e.g. electric utilities), and technology developers. Consultations also included exchanges with the Coal Utilization Research Council, the Electric Power Research Institute, and with other organizations, including environmental and consumer groups.

    An integrated plan to achieve the performance and cost goals is presented in the DOE Office of Clean Coal Strategic Plan. The latest version of this Strategic Plan is undergoing internal review and will be issued shortly and then made available to the public on the National Energy Technology Laboratory Web site at http://www.netl.doe.gov/​coal/​index.html. Detailed program plans, roadmaps, and other documents related to the goals of individual programs are currently available on the Web site.

    Some of the program activities to facilitate production and generation of coal-based power listed in section 962(a) of EPAct have not been funded to date. Therefore, no cost and performance goals have been established for those activities, which include advanced combustion systems, the liquid fuels portion of coal-derived liquids and transportation fuels (except for hydrogen), liquid fuels derived from low rank coal water slurry, and solid fuels and feedstocks.

    The following table identifies cost and performance goals for currently funded program activities under DOE's coal and related technologies program. Some of the activities include more than one of those listed in section 962(a). Advanced Power Systems includes cost and performance goals for gasification systems, turbines for synthesis gas derived from coal, and advanced separation technologies (oxygen). Carbon Sequestration also includes advanced separation technologies (carbon dioxide) and work on advanced combustion technology. Hydrogen and Fuels activities are part of coal-derived chemicals and transportation fuels and also include advanced separation technologies (hydrogen). All of the below listed program activities encompass some aspect of advanced coal-related research activities.

    Program activityPerformance goals *Cost Goals *
    EfficiencyEnvironmental
    Innovations for Existing PlantsMaintain current plant efficiency while achieving the environmental performance and cost goalsMercury (Hg): 50-70% reduction by 2007; 90% reduction by 201070% of today's cost (per lb of mercury removed).
    Nitrogen Oxides (NOX): <0.15 lb/million Btu by 2007; <0.10 lb/million Btu by 201050-75% of current selective catalytic reduction (SCR) capital cost.
    Start Printed Page 72635
    Advanced Power Systems45-50% higher heating value (HHV) efficiency to electricity by 2010 Multi-product capability (e.g. power and hydrogen) with over 60% efficiency by 2015Sulfur Dioxide (SO2): >99% removal NOX: < 0.01 lb/million Btu Hg: >90% removal Carbon Dioxide (CO2) capture: >90%2012 goal: <10% increase in cost of electricity services in zero emission advanced gasification plants integrated with carbon sequestration.
    Carbon SequestrationEfficiency of current and new plants consistent with cost of electricity target90% CO2 capture and sequestration2012 goal: <10% increase in cost of electricity services to separate, capture, transport, and sequester carbon using either direct or indirect systems.
    Hydrogen and FuelsEfficiency consistent with advanced power systemsEmissions consistent with advanced power systemsHydrogen at $0.90/gal. gasoline equivalent (gge) by 2010 and $0.79 gge by 2015 with no incentives or tax credits when integrated with advanced coal power systems.
    Fuel Cell Systems (Coal-based fuel cell/turbine hybrids)40-60% (40% for kilowatt sizes; 60% for megawatt class hybrid systems integrated with coal gasification)Emissions consistent with advanced power systems$400/kW capital cost for fuel cell power modules (in kilowatt sizes by 2010 and megawatt class hybrids by 2015).
    * All dates shown are meant to indicate the completion dates for ongoing research. The referenced technologies will still have to be commercially demonstrated before they are ready or are available for commercial deployment.
    Start Signature

    Issued in Washington, DC, on November 30, 2005.

    Mark R. Maddox,

    Principal Deputy Assistant Secretary, Office of Fossil Energy.

    End Signature End Supplemental Information

    [FR Doc. E5-6902 Filed 12-5-05; 8:45 am]

    BILLING CODE 6450-01-P

Document Information

Published:
12/06/2005
Department:
Energy Department
Entry Type:
Notice
Action:
Notice of proposed draft cost and performance for the Department of Energy's coal and related technologies program, and request for comments.
Document Number:
E5-6902
Dates:
Comments on the draft cost and performance goals are due December 27, 2005.
Pages:
72634-72635 (2 pages)
PDF File:
e5-6902.pdf