94-30154. Tennessee Valley Authority; Sequoyah Nuclear Plant, Unit 1; Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 59, Number 235 (Thursday, December 8, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-30154]
    
    
    [[Page Unknown]]
    
    [Federal Register: December 8, 1994]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-327]
    
     
    
    Tennessee Valley Authority; Sequoyah Nuclear Plant, Unit 1; 
    Environmental Assessment and Finding of No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an exemption from the requirements of Section 
    III.D.3 of Appendix J to 10 CFR Part 50 to the Tennessee Valley 
    Authority, licensee for the Sequoyah Nuclear Plant (SQN), Unit 1. The 
    plant is located at the licensee's site in Hamilton County, Tennessee.
    
    Environmental Assessment
    
    Identification of Proposed Action
    
        The proposed action would exempt the licensee from the provisions 
    in Section III.D.3 of Appendix J to 10 CFR Part 50 with respect to the 
    requirement to perform Primary Containment Type C local leak rate tests 
    (LLRTs) at intervals no greater than 2 years. The exemption would 
    affect Unit 1 only and allow certain Type C valve penetration LLRTs 
    that are specified in the submittal (126 valves out of a total of 242 
    valves subject to the LLRT program) to be delayed until the Cycle 7 
    refueling outage. This outage is scheduled to start approximately 5 
    months after the expiration date of the earliest Type C test.
        On March 2, 1993, SQN Unit 1 entered a forced outage and started 
    the Cycle 6 refueling outage. All Type B and Type C LLRTs were 
    performed during the outage, which ended in December 1993. The unit 
    returned to service on April 20, 1994. Due to the length of the outage, 
    a number of LLRTs that were performed early in the outage were retested 
    prior to conducting the containment integrated leak rate test (CILRT) 
    in December 1993. LLRTs of valves that were initially tested between 
    April 3 and July 19, 1993, however, were not retested because of 
    schedule restraints associated with the CILRT. Since the 2 year time 
    interval for the Type C valve penetrations that were not retested will 
    expire starting in April 1995, Unit 1 would be forced to shut down at 
    that time to perform the tests unless a schedular exemption is granted. 
    The next Unit 1 refueling outage is scheduled to start in September 
    1995. Therefore, the licensee has proposed an exemption to allow a one-
    time deferment of the Appendix J interval requirement for the affected 
    Type C valve penetration tests from April 3, 1995, until October 1, 
    1995, a total of approximately 181 days from the first valve tested 
    during the Cycle 6 outage.
        The proposed action is in accordance with the licensee's 
    application for exemption dated November 10, 1994.
    
    The Need for the Proposed Action
    
        The proposed action is required to exempt the licensee from the 
    requirement to conduct certain specified Type C containment local leak 
    rate tests on SQN Unit 1 at a 2-year frequency so the tests can be 
    performed during the Cycle 7 refueling outage scheduled to start in 
    September 1995. However, TVA has requested extension of the time 
    interval to October 1, 1995, to account for unforeseen circumstances.
    
    Environmental Impact of the Proposed Action
    
        With respect to the requested action, exemption from the above 
    requirement would allow the licensee to delay conducting certain Type C 
    local leak rate tests at Unit 1 approximately 181 days beyond the 
    scheduled expiration date of the 2-year period for the first LLRT 
    performed during the Cycle 6 outage. This relatively small increase in 
    the test interval does not significantly contribute to the total 
    leakage limits. The intent of Section III.D.3 of Appendix J is to 
    ensure that containment leakage is maintained within the prescribed 
    limits. Based on the following information, the exemption will not 
    significantly affect the ability of the individual primary containment 
    valves that are subject to the Type C tests to perform this safety 
    function:
        1. The valves for which the extension of the 2-year interval is 
    being requested have a history of being leak tight and in good 
    condition. The leak-tight condition of these components was last 
    verified by Type C LLRTs and by the Type A test conducted in December 
    1993. Based on the present containment leak rate that accounts for less 
    than 93 percent of the 0.75 La limit, the remaining margin is 
    sufficient to ensure any incremental increase in leakage resulting from 
    the extension would not cause unacceptable as-found test results.
        2. Based on historical data, any incremental increase in leakage 
    because of the extension will be small. Improved maintenance practices 
    implemented during the Unit 1 Cycle 5 outage and continued into the 
    Cycle 6 outage, including motor operated valve testing (MOVATS) of 
    containment isolation valves, provide increased assurance that these 
    components will perform their safety function.
        3. The valves for which the exemption is requested were included in 
    the Type A test performed in December 1993. This test indicated a 
    containment leak rate of 0.1742 percent per day, which is below the 
    0.1875 percent per day limit.
        The change will not increase the probability or consequences of 
    accidents, no changes are being made in the types of any effluents that 
    may be released offsite, and there is no significant increase in the 
    allowable individual or cumulative occupational radiation exposure. 
    Accordingly, the Commission concludes that there are no significant 
    radiological environmental impacts associated with the proposed action.
        With regard to potential nonradiological environmental impacts, the 
    proposed action does involve features located entirely within the 
    restricted area as defined in 10 CFR Part 20. It does not affect 
    nonradiological plant effluents and has no other environmental impacts. 
    Accordingly, the Commission concludes that there are no significant 
    nonradiological impacts associated with the proposed action.
    
    Alternatives to the Proposed Action
    
        Since the Commission has concluded that there is no measurable 
    environmental impact associated with the proposed exemption, any 
    alternatives with equal or greater environmental impact need not be 
    evaluated. The principal alternative would be to deny the request. Such 
    action would not enhance the protection of the environment and would 
    result in unjustified cost to the licensee.
    
    Alternative Use of Resources
    
        This action does not involve the use of resources not previously 
    considered in the ``Final Environmental Statement Related to the 
    Operation of the Sequoyah Nuclear Plant, Units 1 and 2,'' dated 
    February 21, 1974.
    
    Agencies and Persons Consulted
    
        The NRC staff consulted with the Tennessee State official regarding 
    the environmental impact of the proposed action. The State official had 
    no comments.
    
    Finding of No Significant Impact
    
        Based on the environmental assessment, the Commission concludes 
    that the proposed action will not have a significant effect on the 
    quality of the human environment. Accordingly, the Commission has 
    determined not to prepare an environmental impact statement for the 
    proposed action.
        For further details with respect to the proposed action, see the 
    licensee's letter dated November 10, 1994, which is available for 
    public inspection at the Commission's Public Document Room, The Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the Chattanooga-Hamilton County Library, 1101 
    Broad Street, Chattanooga, Tennessee 37402.
    
        Dated at Rockville, Maryland, this 2d day of December 1994.
    
        For the Nuclear Regulatory Commission.
    Frederick J. Hebdon,
    Director, Project Directorate II-4, Division of Reactor Projects--I/II, 
    Office of Nuclear Reactor Regulation.
    [FR Doc. 94-30154 Filed 12-7-94; 8:45 am]
    BILLING CODE 7590-01-M
    
    
    

Document Information

Published:
12/08/1994
Department:
Nuclear Regulatory Commission
Entry Type:
Uncategorized Document
Document Number:
94-30154
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: December 8, 1994, Docket No. 50-327