95-29915. Transcontinental Gas Pipe Line Corporation; Notice of Application  

  • [Federal Register Volume 60, Number 236 (Friday, December 8, 1995)]
    [Notices]
    [Pages 63032-63033]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-29915]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP96-89-000]
    
    
    Transcontinental Gas Pipe Line Corporation; Notice of Application
    
    December 4, 1995.
        Take notice that on November 30, 1995, Transcontinental Gas Pipe 
    Line Corporation (``Transco''), P.O. Box 1396, Houston, Texas 77251, 
    filed in the above an abbreviated application pursuant to Section 7(c) 
    and Section 7(b) of the Natural Gas Act and the Regulations of the 
    Federal Energy Regulatory Commission (``Commission'') for (1) a 
    certificate of public convenience and necessity authorizing certain 
    Tombigbee River replacement crossings and certain interconnections at 
    that location for downstream delivery of gas to an industrial plant, 
    and (2) an order permitting and approving the abandonment of existing 
    facilities at the same location. For the reasons described herein, 
    Transco requests a certificate and construction clearance by January 8, 
    1996.
        Transco states that it has four pipelines across the Tombigbee 
    River in Alabama 30-inch diameter Main Line A, 30-inch diameter Main 
    Line B, 36-inch diameter Main Line C and 42-inch diameter Main Line D. 
    This river crossing is 29.03 miles east of the location where Transco's 
    system crosses the Mississippi-Alabama state line. At this location, 
    the Tombigbee River forms the boundary between Choctaw and Marengo 
    Counties, Alabama. Transco states that all gas produced onshore and 
    offshore, Texas and Louisiana, onshore Mississippi and the Mobile Bay 
    offshore Alabama area which moves on Transco's system to Transco's 
    markets in the Deep South, Atlantic Seaboard and eastern markets flows 
    through this Tombigbee River crossing.
        Transco states that because of chronic mass erosion of the river 
    banks, Main Line C is exposed and subject to potential physical damage 
    from boat and barge traffic. Main Line D is not yet exposed, but 
    Transco is concerned that it will become exposed because of the 
    continuing bank erosion.
        Transco states that it cannot perform these replacements pursuant 
    to Section 2.55(b) of the Regulations because of the Commission's 
    clarification of Section 2.55(b) in the order issued on May 12, 1994 in 
    Arkla Energy Resources Company, Docket No. CP91-2069-000 (67 FERC para. 
    61,173) (replacements outsides of existing right-of-way cannot be 
    performed pursuant to Section 2.55(b)). Transco states that it is 
    imperative that Transco complete the new crossings soon to ensure that 
    gas from the production areas described above is able to flow to 
    Transco's markets. Transco states that it proposes to install 
    approximately 2,000 feet of new 36-inch diameter Main Line C by 
    horizontal directional drilling under the Tombigbee River, at the 
    location of its existing pipeline crossings of the Tombigbee River.\1\ 
    The alignment of the new Main Line C will parallel Main Line B 
    (installed in 1991 by horizontal directional drilling) with a spacing 
    of approximately 75 feet to the south of Main Line B. Approximately 950 
    feet of 36-inch diameter pipe will be conventionally installed by 
    trenching from the entrance and exit of the bore and tied in to 
    existing Main Line C.
    
        \1\ Transco states that directionally drilled pipelines under 
    rivers are significantly more secure than the older pipelines which 
    are installed by way of trenching the river bed. The 36-inch and 42-
    inch pipeline crossings will be at an approximate depth of 45 feet 
    beneath the Tombigbee River navigation channel.
    ---------------------------------------------------------------------------
    
        Transco states that it also proposes to install approximately 2,300 
    feet of new 42-inch diameter Main Line D by horizontal directional 
    drilling under the Tombigbee River. Approximately 500 feet of 42-inch 
    diameter pipe will be conventionally installed from the entrance and 
    exit of the bore and tied in to existing Main Line D. The alignment of 
    the Main Line D will parallel the new Main Line C with a spacing of 
    approximately 75 feet to the south of Main Line C.
        Transco states that the proposed replacements will restore the 
    long-term integrity of Transco's transmission system at the Tombigbee 
    River crossings. Since 36-inch and 42-inch diameter crossings are being 
    replaced by identical 36-inch and 42-inch diameter crossings, system 
    capacity across the Tombigbee River will remain unchanged at 33,639,606 
    MCFD. The existing shallow, conventionally installed Main Lines C and D 
    at this location will be retired--portions by removal and portions in 
    place.
        The cost of installation of new Main Line C is estimated to be 
    $2,029,007, and the cost of installation of new Main Line D is 
    estimated to be $2,925,170.
        It is stated that Transco needs to replace Main Line C as soon as 
    possible because of its vulnerable condition. Coming quickly 
    thereafter, Transco plans to replace Main Line D beginning in May 1996 
    because of Transco's concern that its condition could rapidly worsen.
        Transco states that issuance of a certificate to Transco and 
    construction clearance by January 8 is justified for two reasons: (1) 
    the above-described need for security of gas service to Transco's 
    market areas, and (2) the de minimis impact on the environment of the 
    crossing project (as described below). With respect to the environment, 
    Transco states that the following are the significant points:
        1. On the east side of the river (where the drilling rig will be 
    set up) temporary 
    
    [[Page 63033]]
    work space will occupy 8.82 acres. Of this east side work space only 
    0.54 acre is presently forested (0.25 acres is forested wetland). The 
    remainder of the work space on the east side is located either on 
    existing permanent right-of-way or in a cultivated field, both of which 
    have previously been cleared.
        On the west side of the river (where crossing segment fabrication 
    and pre-testing will occur) temporary work space will occupy 22.94 
    acres. Of this west side work space only 3.12 acres is presently 
    forested (2.56 acres is forested wetland). The remainder of the work 
    space on the west side is located either on existing permanent right-
    of-way or in a cultivated field, both of which have previously been 
    cleared.
        In summary, areas requiring additional clearing for the 
    installation of Main Lines C and D are relatively minor. Of these 
    additional cleared areas only 3.66 acres are forested and of those only 
    2.81 acres are forested wetland.
        2. Clearance has been received with respect to endangered/
    threatened species from the U.S. Fish and Wildlife Service. The Alabama 
    Natural Heritage Program provided Transco with a list of candidate and 
    protected species within the general area of the project. Transco 
    evaluated this list in the context of the project to ensure that the 
    project will not impact these species; the evaluation verified that the 
    project will not impact these species.
        3. Clearance has been received from the Alabama State Historical 
    Preservation Officer (``SHPO'') with respect to cultural resources 
    related to the project area. There is a known archaeological site on 
    the east bank of the Tombigbee River to the north of the project area 
    that will not be impacted by this project; thus, the SHPO has no 
    concern with regard to this site. Transco has contacted several Native 
    American groups. Transco states that it does not consider in situ 
    replacement a practical option because such conventional replacement 
    would be subject to the same erosive forces of the river.
        4. Transco states that the proposed installation and removals will 
    improve the visual or aesthetic value of the river banks at the 
    Tombigbee River crossing by allowing native revegetation and dynamics 
    of the river to control the natural succession of the banks at the 
    crossing. Transco will implement measures to restore and stabilize the 
    construction work spaces and abandoned rights-of-way.
        Therefore, Transco states that in view of (1) the essential need 
    for the Tombigbee River crossings to be able to move gas from Transco's 
    production areas to Transco's market areas, and (2) the de minimis 
    environmental impact of such project, Transco requests the Commission 
    to issue a certificate and construction clearance by January 8, 1996 so 
    that security of the Tombigbee River crossings can be assured as soon 
    as possible. By this application, Transco also seeks authorization to 
    abandon in place and by removal the portions of its Main Lines C and D 
    at the Tombigbee River which will be replaced. Gas transmission across 
    the Tombigbee River will be unaffected by these abandonments. The cost 
    of the Line C removal work is estimated to be $140,000. The cost of the 
    Line D removal work is estimated to be $201,540.
        It is further stated that on the west bank at the location of the 
    Tombigbee River crossings, Transco has interconnections on Main Lines C 
    and D that enable gas to flow into a meter and regulator (M&R) station 
    for downstream delivery to a plant owned by American Can Company 
    (``American Can''), which is north of the crossings on the west bank. 
    As a result of the replacements of Lines C and D, as above described, a 
    reconfiguration of the American Can interconnections will be necessary. 
    One new interconnection with the M&R station will involve conventional 
    installation of approximately 1,200 feet of 4-inch diameter pipe from 
    the M&R station west to a tap on the new segment of Line C. This will 
    effectuate delivery of gas from of Line C to the M&R station. A second 
    new interconnection will involve conventional installation of 
    approximately 30 feet of 4-inch diameter pipe from a new tap on Line D 
    to a tee near the western terminus of the above-described 1,200-foot 4-
    inch line. This will effectuate delivery of gas from Line D to the M&R 
    station.
        The estimated cost of installation of the 1,200-foot line is 
    $154,718. The estimated cost of installation of the 30-foot line is 
    $83,924.
        By this application, Transco also seeks authorization to abandon by 
    removal the interconnections between existing Main Lines C and D and 
    the M&R station. Gas supply to the American Can plant will be 
    unaffected by these abandonments. The estimated cost of removal of the 
    interconnection between Main Line C and the M&R station is $5,000. The 
    estimated cost of removal of the interconnection between Main Line D 
    and the M&R station is $12,000.
        Any person desiring to be heard or to make any protest with 
    reference to said application should on or before December 14 1995, 
    file with the Federal Energy Regulatory Commission, Washington, DC 
    20426, a motion to intervene or a protest in accordance with the 
    requirements of the Commission's Rules of Practice and Procedure (18 
    CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act 
    (18 157.10). All protests filed with the Commission will be considered 
    by it in determining the appropriate action to be taken, but will not 
    serve to make the protestants parties to the proceedings. Any person 
    wishing to become a party to a proceeding or to participate as a party 
    in any hearing therein must file a motion to intervene in accordance 
    with the Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to the jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
    Commission's Rules of Practice and Procedure, a hearing will be held 
    without further notice before the Commission or its designee on this 
    application if not motion to intervene is filed within the time 
    required herein, if the Commission on its own review of the matter 
    finds that a grant of the certificate is required by the public 
    convenience and necessity. If a motion for leave to intervene is timely 
    filed, or if the Commission on its own motion believes that a formal 
    hearing is required, further notice of such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for Transco to appear or be represented at the 
    hearing.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 95-29915 Filed 12-7-95; 8:45 am]
    BILLING CODE 6717-01-M
    
    

Document Information

Published:
12/08/1995
Department:
Energy Department
Entry Type:
Notice
Document Number:
95-29915
Pages:
63032-63033 (2 pages)
Docket Numbers:
Docket No. CP96-89-000
PDF File:
95-29915.pdf